Transcript Slide 1

Lecture
5
Project Management
Chapter 17
1
Project Management

How is it different?

Limited time frame
 Narrow focus, specific objectives

Why is it used?

Special needs
 Pressures for new or improves products or services

Definition of a project

Unique, one-time sequence of activities designed
to accomplish a specific set of objectives in a
limited time frame
2
Project Management

What are the Key Metrics

Time
 Cost
 Performance objectives

What are the Key Success Factors?

Top-down commitment
 Having a capable project manager
 Having time to plan
 Careful tracking and control
 Good communications
3
Project Management

What are the tools?

Work breakdown structure
 Network diagram
 Gantt charts
4
Project Manager
Responsible for:
Work
Human Resources
Communications
Quality
Time
Costs
5
Key Decisions

Deciding which projects to implement

Selecting a project manager

Selecting a project team

Planning and designing the project

Managing and controlling project resources

Deciding if and when a project should be
terminated
6
Ethical Issues

Temptation to understate costs

Withhold information

Misleading status reports

Falsifying records

Compromising workers’ safety

Approving substandard work

http://www.pmi.org/
7
PERT and CPM
PERT: Program Evaluation and Review Technique
CPM: Critical Path Method





Graphically displays project activities
Estimates how long the project will take
Indicates most critical activities
Show where delays will not affect project
PERT and CPM have been used to plan, schedule, and control
a wide variety of projects:




R&D of new products and processes
Construction of buildings and highways
Maintenance of large and complex equipment
Design and installation of new systems
8
PERT/CPM

PERT/CPM

used to plan the scheduling of individual
activities that make up a project.

Projects may have as many as several
thousand activities.
 Complicating factor in carrying out the
activities

some activities depend on the completion of
other activities before they can be started.
9
PERT/CPM

Project managers rely on PERT/CPM to help
them answer questions such as:

What is the total time to complete the project?
 What are the scheduled start and finish dates for
each specific activity?
 Which activities are critical?


must be completed exactly as scheduled to keep
the project on schedule?
How long can non-critical activities be delayed

before they cause an increase in the project
completion time?
10
Planning and Scheduling
Activity
0
2
4
6
8
10 12
14
16
18
Locate new
facilities
Interview staff
Hire and train staff
Select and order
furniture
Remodel and install
phones
Furniture setup
Move in/startup
11
20
Project Network

Project network

constructed to model the precedence of the
activities.
 Nodes represent activities
 Arcs represent precedence relationships of the
activities

Critical path for the network

a path consisting of activities with zero slack
12
Project Network – An Example
8 weeks
Locate
facilities
A
6 weeks
Order
furniture
B
F
11 weeks
Remodel
E
S
4 weeks
Interview
C
3 weeks
Furniture
setup
G
Move
in
1 week
9 weeks
Hire and
train
D
13
Management Scientist Solution
Critical Path
Path
Length
Slack
(weeks)
A-B-F-G
A-E-G
C-D-G
18
20
14
2
0
6
14
Uncertain Activity Times

Three-time estimate approach


the time to complete an activity assumed to
follow a Beta distribution
An activity’s mean completion time is:
t = (a + 4m + b)/6




a = the optimistic completion time estimate
b = the pessimistic completion time estimate
m = the most likely completion time estimate
An activity’s completion time variance is
2 = ((b-a)/6)2
15
Uncertain Activity Times

In the three-time estimate approach, the critical
path is determined as if the mean times for the
activities were fixed times.
 The overall project completion time is assumed to
have a normal distribution

with mean equal to the sum of the means of
activities along the critical path, and
 variance equal to the sum of the variances of
activities along the critical path.
16
Example
Immediate
Activity Predecessor
Optimistic
Time (a)
Most Likely
Time (m)
Pessimistic
Time (b)
A
--
4
6
8
B
--
1
4.5
5
C
A
3
3
3
D
A
4
5
6
E
A
0.5
1
1.5
F
B,C
3
4
5
G
B,C
1
1.5
5
H
E,F
5
6
7
I
E,F
2
5
8
J
D,H
2.5
2.75
4.5
K
G,I
3
5
7
17
Management Scientist Solution
18
Key Terminology

Network activities

ES: early start
 EF: early finish
 LS: late start
 LF: late finish

Used to determine

Expected project duration
 Slack time
 Critical path
19
The Network Diagram (cont’d)

Path



Critical path


The longest path; determines expected project duration
Critical activities


Sequence of activities that leads from the starting node
to the finishing node
AON path: S-1-2-6-7
Activities on the critical path
Slack

Allowable slippage for path; the difference the length
of path and the length of critical path
20
Advantages of PERT

Forces managers to organize

Provides graphic display of activities

Identifies

Critical activities

Slack activities
4
2
1
5
6
3
21
Limitations of PERT

Important activities may be omitted

Precedence relationships may not be correct

Estimates may include a fudge factor

May focus solely on critical path
22
Linear Programming
George Dantzig – 1914 -2005
 Concerned with optimal allocation of limited
resources such as


Materials
 Budgets
 Labor
 Machine time

among competitive activities
 under a set of constraints
George Dantzig – 1914 -2005
23
Product Mix Example (from session 1)
Type 1
Type 2
Profit per unit
$60
$50
Assembly time per
unit
4 hrs
10 hrs
Inspection time per
unit
2 hrs
Storage space per
unit
3 cubic ft
Resource
Amount available
Assembly time
100 hours
Inspection time
22 hours
Storage space
39 cubic feet
1 hr
3 cubic ft
24
Linear Programming Example
Variables
Maximize 60X1 + 50X2
Subject to
Objective function
4X1 + 10X2 <= 100
2X1 + 1X2 <= 22
Constraints
3X1 + 3X2 <= 39
Non-negativity Constraints
X1, X2 >= 0
What is a Linear Program?
• A LP is an optimization model that has
• continuous variables
• a single linear objective function, and
• (almost always) several constraints (linear equalities or inequalities)
25
Linear Programming Model

Decision variables



Objective Function



unknowns, which is what model seeks to determine
for example, amounts of either inputs or outputs
goal, determines value of best (optimum) solution among all feasible (satisfy
constraints) values of the variables
either maximization or minimization
Constraints


restrictions, which limit variables of the model
limitations that restrict the available alternatives

Parameters: numerical values (for example, RHS of constraints)
 Feasible solution: is one particular set of values of the decision
variables that satisfies the constraints


Feasible solution space: the set of all feasible solutions
Optimal solution: is a feasible solution that maximizes or minimizes
the objective function

There could be multiple optimal solutions
26
Another Example of LP: Diet Problem

Energy requirement : 2000 kcal
 Protein requirement : 55 g
 Calcium requirement : 800 mg
Food
Energy (kcal)
Protein(g)
Calcium(mg)
Oatmeal
110
4
2
Price per
serving($)
3
Chicken
Eggs
Milk
Pie
205
160
160
420
32
13
8
4
12
54
285
22
24
13
9
24
Pork
260
14
80
13
27
Example of LP : Diet Problem

oatmeal: at most 4 servings/day
 chicken: at most 3 servings/day
 eggs: at most 2 servings/day
 milk: at most 8 servings/day
 pie: at most 2 servings/day
 pork: at most 2 servings/day
Design an optimal diet plan
which minimizes the cost per day
28
Step 1: define decision variables






x1 = # of oatmeal servings
x2 = # of chicken servings
x3 = # of eggs servings
x4 = # of milk servings
x5 = # of pie servings
x6 = # of pork servings
Step 2: formulate objective function
• In this case, minimize total cost
minimize z = 3x1 + 24x2 + 13x3 + 9x4 + 24x5 + 13x6
29
Step 3: Constraints

Meet energy requirement
110x1 + 205x2 + 160x3 + 160x4 + 420x5 + 260x6 2000

Meet protein requirement
4x1 + 32x2 + 13x3 + 8x4 + 4x5 + 14x6  55

Meet calcium requirement
2x1 + 12x2 + 54x3 + 285x4 + 22x5 + 80x6  800

Restriction on number of servings
0x14, 0x23, 0x32, 0x48, 0x52, 0x62
30
So, how does a LP look like?
minimize 3x1 + 24x2 + 13x3 + 9x4 + 24x5 + 13x6
subject to
110x1 + 205x2 + 160x3 + 160x4 + 420x5 + 260x6 2000
4x1 + 32x2 + 13x3 + 8x4 + 4x5 + 14x6  55
2x1 + 12x2 + 54x3 + 285x4 + 22x5 + 80x6  800
0x14
0x23
0x32
0x48
0x52
0x62
31
Optimal Solution – Diet Problem
Using LINDO 6.1

Food
Oatmeal
# of servings
4
Chicken
Eggs
Milk
Pie
0
0
6.5
0
Pork
2
Cost of diet = $96.50 per day
32
Optimal Solution – Diet Problem
Using Management Scientist

Food
Oatmeal
# of servings
4
Chicken
Eggs
Milk
Pie
0
0
6.5
0
Pork
2
Cost of diet = $96.50 per day
33
Guidelines for Model Formulation

Understand the problem thoroughly.
 Describe the objective.
 Describe each constraint.
 Define the decision variables.
 Write the objective in terms of the decision
variables.
 Write the constraints in terms of the decision
variables

Do not forget non-negativity constraints
34
Product Mix Problem
•
•
•
•
•
•
Floataway Tours has $420,000 that can be used to
purchase new rental boats for hire during the summer.
The boats can be purchased from two different
manufacturers.
Floataway Tours would like to purchase at least 50 boats.
They would also like to purchase the same number from
Sleekboat as from Racer to maintain goodwill.
At the same time, Floataway Tours wishes to have a total
seating capacity of at least 200.
Formulate this problem as a linear program
35
Product Mix Problem
Boat
Maximum
Builder
Cost
Speedhawk Sleekboat
Silverbird Sleekboat
Catman
Racer
Classy
Racer
$6000
$7000
$5000
$9000
Expected
Seating
3
5
2
6
Daily
Profit
$ 70
$ 80
$ 50
$110
36
Product Mix Problem

Define the decision variables
x1 = number of Speedhawks ordered
x2 = number of Silverbirds ordered
x3 = number of Catmans ordered
x4 = number of Classys ordered
 Define the objective function
Maximize total expected daily profit:
Max: (Expected daily profit per unit) x (Number of units)
Max: 70x1 + 80x2 + 50x3 + 110x4
37
Product Mix Problem

Define the constraints
(1) Spend no more than $420,000:
6000x1 + 7000x2 + 5000x3 + 9000x4 < 420,000
(2) Purchase at least 50 boats:
x1 + x2 + x3 + x4 > 50
(3) Number of boats from Sleekboat equals number
of boats from Racer:
x1 + x2 = x3 + x4 or x1 + x2 - x3 - x4 = 0
(4) Capacity at least 200:
3x1 + 5x2 + 2x3 + 6x4 > 200
Nonnegativity of variables:
xj > 0, for j = 1,2,3,4
38
Product Mix Problem - Complete Formulation
Max 70x1 + 80x2 + 50x3 + 110x4
s.t.
6000x1 + 7000x2 + 5000x3 + 9000x4 < 420,000
x1 + x2 + x3 + x4 > 50
Boat
# purchased
x1 + x2 - x3 - x4 = 0
Speedhawk
28
3x1 + 5x2 + 2x3 + 6x4 > 200
Silverbird
0
x1, x2, x3, x4 > 0
Catman
0
Classy

28
Daily profit = $5040
39
Marketing Application: Media Selection
Advertising Media
# of potential
customers reached
Cost ($) per
advertisement
Max times available
per month
Exposure Quality
Units
Day TV
1000
1500
15
65
Evening TV
2000
3000
10
90
Daily newspaper
1500
400
25
40
Sunday newspaper
2500
1000
4
60
Radio
300
100
30
20





Advertising budget for first month = $30000
At least 10 TV commercials must be used
At least 50000 customers must be reached
Spend no more than $18000 on TV adverts
Determine optimal media selection plan
40
Media Selection Formulation

Step 1: Define decision variables






Step 2: Write the objective in terms of the decision variables


DTV = # of day time TV adverts
ETV = # of evening TV adverts
DN = # of daily newspaper adverts
SN = # of Sunday newspaper adverts
R = # of radio adverts
Maximize 65DTV+90ETV+40DN+60SN+20R
Step 3: Write the constraints in terms of the decision variables
DTV
ETV
DN
SN
R
+
25
<=
4
<=
30
<=
30000
0
DN
25
SN
2
R
30
Exposure = 2370 units
Availability of
Media
Budget
+
ETV
>=
10
1500DTV
+
3000ETV
<=
18000
TV Constraints
1000DTV
+
2000ETV
>=
50000
Customers reached
+
100R
<=
ETV
DTV
2500SN
+
10
10
3000ETV
+
1000SN
<=
DTV
+
1500DN
+
15
Value
1500DTV
+
400DN
<=
Variable
300R
DTV, ETV, DN, SN, R >= 0
41
Applications of LP

Product mix planning
 Distribution networks
 Truck routing
 Staff scheduling
 Financial portfolios
 Capacity planning
 Media selection: marketing
42
Possible Outcomes of a LP

A LP is either
Infeasible – there exists no solution which satisfies
all constraints and optimizes the objective function
 or, Unbounded – increase/decrease objective
function as much as you like without violating any
constraint
 or, Has an Optimal Solution



Optimal values of decision variables
Optimal objective function value
43
Infeasible LP – An Example

minimize
4x11+7x12+7x13+x14+12x21+3x22+8x23+8x24+8x31+10x32+16
x33+5x34
Subject to
 x11+x12+x13+x14=100
 x21+x22+x23+x24=200
 x31+x32+x33+x34=150


x11+x21+x31=80
x12+x22+x32=90
x13+x23+x33=120
x14+x24+x34=170

xij>=0, i=1,2,3; j=1,2,3,4


Total demand exceeds total supply
44
Unbounded LP – An Example
maximize 2x1 + x2
subject to
-x1 +
x2  1
x1 - 2x2  2
x1 , x 2  0
x2 can be increased indefinitely without violating any
constraint
=> Objective function value can be increased indefinitely
45
Multiple Optima – An Example
maximize x1 + 0.5 x2
subject to
2x1 + x2  4
x1 + 2x2  3
x1 , x2  0
• x1= 2, x2= 0, objective function = 2
• x1= 5/3, x2= 2/3, objective function = 2
46