Impact System
Impact cylinders used for cleaning of heating surfaces
at industrial and waste incineration plants
Alexander Haug
Waste-to-Energy Plant / Impact System
Delivery
Incineration
Flue Gas Cleaning
» Pneumatic impact cylinder is used for the efficient cleaning of contaminated heating areas
in waste-to-energy plants
» Adjustable impact energy allows precise and effective cleaning
» Clean heating elements are the basic to keep the overall efficiency of the evaporator, superheater and economizer at a constant level
» Extending the OPERATING TIME of the plant and maximizing waste throughput
Alexander Haug, 21.03.2009
2
Cleaning Heating Surfaces of Incinerators
Alternative
Existing Techniques
Mechanical drop
hammer system
Alexander Haug, 21.03.2009
Electro-pneumatic impact wagon
3
Pneumatic Single Rapping
Waste-to-Energy-plant – Flowchart of burning process
reburning zone
Burning Process
steam boiler
» Delivered waste is collected in the
storage pit.
» Cranes then transport the waste to the
funnel tube.
» The waste is then evenly distributed on
the grate where it is dried, vented and
incinerated at temperatures between
850ºC and 1100ºC
funnel tube
» Resultant smoke gases collect in the
reburner zone where the waste is
complete burned
grate
» The heat produced during this process
produces stream which, in turn, is used
to generate electricity through a turbine
storage pit
Alexander Haug, 21.03.2009
4
Cleaning the Tube Bundle Heat Exchanger
hot flue gas
convective
heating surface
hopper
» High concentration of sticky particles in the flue gas
» These particles will blockage the flue gas path
Cleaning the heating surface is necessary to run the plant
and guarantees a high degree of efficiency
Alexander Haug, 21.03.2009
5
Rapping Process
» High impact force provide an efficient
cleaning
» Rapping the polluted heating tube bundles
caused an oscillation, which shake off the
build up material
tube
bundle
boiler casing
» Cleaning with air or water is no longer
required
»Extension of travel time before shut
down the plant
»Increase the overall efficiency
and waste throughput of the plant
Alexander Haug, 21.03.2009
6
plunger
sticky
particles
Demand of the customers
Optimization of the cleaning system
» Optimal cleaning of the heat exchange surfaces to
optimize the absolute efficiency
» Subsequent and Individual adjustment of the impact
force
» Reducing maintenance costs
» Reducing the construction volume
» Feedback to control room of the cleaning activity
» Check the wear and inform about failures
» Process stability
» Guarantee maximum travel time
Alexander Haug, 21.03.2009
7
Pneumatic Single Position Rapping
» Individual adaptation of impact force for each point
» Wear indicators
» Check the wear and inform about failures
» Low noise level
» High process reliability
» Low maintenance cost and just a few spare and wear parts
Alexander Haug, 21.03.2009
8
Norgren Impact System
» Elements of the Norgren Impact System - Project
» Product

Impact Cylinder
» Control Cabinet




SPS (S7) Profibus DP
S7 Touch Panel
Coupler for Profibus or Fibre Optic Cable
Valve Islands (3/2 way function)
» Software
» Engineering/Documentation
» Installation
» Commissioning
» Optional
» Mounting flanges with plungers and springs
Alexander Haug, 21.03.2009
9
Impact Cylinder SPCH/080003
Application:
cleaning of heating surfaces at industrial and incineration
plants
»
Technical data - SPCH/080003
» Temperature range: -20ºC to + 80ºC
» Pressure range: 3 – 7.5 bar
» Impact energy: 125 Joule at 7.5 bar control pressure
» Triggering via valve islands with 3/2-way double
solenoid valve (single-acting)
» Compressed air: filtered 40 um
» Junction: hose fitting PA-pipe (Ø10mm)
» Air consumption: approx 5 litres per impact
Alexander Haug, 21.03.2009
10
Adjustment of the Impact Energy
Adjusting screw
Alexander Haug, 21.03.2009
11
Force Compensation
» Force reduction in the end position leads to better vibrations on the pipes
Without compensation
With compensation
Alexander Haug, 21.03.2009
12
Wear measurement of the striking pins inside
the boiler
Dipstick (go, no-go
status) of pin wear
Dipstick
Min- Max display
Alexander Haug, 21.03.2009
Status at the flange
13
Automatic
wear-indicator – can be replaced
with electrical pressure switch
Optical Wear Indicator for SPCH/080003
Wear of the impact pin inside the boiler can be
assessed with the dipstick:
• Remove visual indicator
• Insert dipstick
• Assess whether it is within acceptable region
• Reassemble the indicator
Alexander Haug, 21.03.2009
14
When the wear is > 16 mm, the indicator
is red and the cylinder will not impact.
Remove indicator to reset.
This protects both the cylinder and the
boiler parts.
Drawing Impact Cylinder SPCH/080003
Alexander Haug, 21.03.2009
15
Benefits of the Norgren Impact System
»
»
High efficiency constantly during heat
exchange due to effective rapping of the pipes
Savings in support and operation
Picture description:
Left side: pipes due to bad rapping
Right side: pipes after good rapping (Norgren)
Alexander Haug, 21.03.2009
16
Reference List - Impact Systems
Germany
» MVA Leuna Boiler I + II
» MVA Sonne (Großräschen)
» MVA Premnitz
» MVA Hameln
» MVA Herten
» MVA Mannheim
Built
2006
2008
2008
2009
1982
2009
International
» WTE Dürnrohr Boiler I + II (Austria)
» WTE Dürnrohr Boiler III
(Austria)
» WTE Pfaffenau
(Austria)
» WTE Delfzijl Boiler I + II (NL)
» KEBAG Emmenspitz
(Switzerland)
» KVA Chevenez, Geneve (Switzerland)
» KVA Turgi Aarau
(Switzerland)
» WTE Allington*
(UK)
» WTE Moskau*
(Russia)
*Impact wagon system
Alexander Haug, 21.03.2009
17
2005
2009
2009
2009
2006
2002/2009
1996
2005
2007
Project Dürnrohr Boiler I + II + III
Impact system with 94 impact cylinders per boiler
Alexander Haug, 21.03.2009
18
Control Cabinet Impact System
Dürnrohr (Austria)
» SPS (S7 300) Profibus DP
» Signal via Profibus- or LWL coupling
» User input with S7 OP touch panel
» Solenoid valve island 48 x 3/2-way double
valves
» Push- In slot via 10 mm PA- pipe
Alexander Haug, 21.03.2009
19
Impact System
» Each impact point is
controlled with one cylinder
» Access via angle screw
coupling and a 10 mm PApipe
» Assembly of the impact
cylinder on the boiler with a
flange or welding bell
» Each side of the boiler is
controlled via control cabinet
with valve island and control
panel
Alexander Haug, 21.03.2009
20
Cleaning of heating surfaces with single
impact spots
Dürnrohr (Austria)
» Single-acting impact cylinders
(94 per boiler)
» Triggered via valve island with double 3/2-way
solenoid valves
» 5 liters / impact at 6.5 bar
» One 10mm PA tube per cylinder
Alexander Haug, 21.03.2009
21
Key Advantages of Norgren Impact System
» Optimal cleaning
» Extend the maximum travel time
of the plant
» Guarantee high overall efficient
» Maximize the waste throughput
» Keep an “Eye” into the boiler
» Check the wear and inform about failures
» Subsequent adjustment of the cleaning system to your plant
» In- / decrease the impact force
» Change the iteration of the cylinder groups
» Nearly no maintenance and no spare and wear parts
» Comfortable operation and feedback to the control room
Alexander Haug, 21.03.2009