2009 ENVIRONMENTAL SEMINAR

Download Report

Transcript 2009 ENVIRONMENTAL SEMINAR

2009 ENVIRONMENTAL SEMINAR

Boat Bottom Pressure Washing Requirements & General Permit for the Discharge of Stormwater Associated with Industrial Activity

Tuesday, August 18, 2009

Management of Vessel Pressure Washing Wastewater

Quick History of the Issue

Spring 2006: Discharge of pressure wash water to surface or ground water no longer allowed December 31, 2008: Original deadline to cease discharge May 2008: DEP publishes guidance for pressure wash water management September 30, 2009: Deadline extension March 2009: After much negotiation with DEP to extend Sept. deadline, CMTA sends letter to legislature and Consent Order is negotiated

DEP Guidance on Boat Bottom Pressure Washing

(as of May 2008)

• • Contain & collect wastewater deflected from any boat surface during boat bottom pressure washing . Wastewater cannot be discharged to ground or surface waters Handle wastewater as “process wastewater.” Process wastewater is not covered by the Stormwater General Permit and cannot be discharged to ground or surface waters

PW WASTEWATER MANAGEMENT OPTIONS

COLLECT, TREAT & PIPE TO SANITARY SEWER

Treat water in compliance with General Permit for Miscellaneous Discharges of Sewer Compatible Wastewater (“MISC General Permit”) and regulations of municipal water pollution control authority •

COLLECT, TREAT & HAUL TO SANITARY SEWER

Transport water by the marina operator, or by a contract hauler licensed under CGS Section 22a-454 for discharge to a municipal sewage treatment plant in compliance MISC GP & local regulations •

COLLECT & HAUL TO INDUSTRIAL WASTEWATER TREATMENT FACILITY

Collect wastewater in a tank and transport by licensed waste hauler to licensed industrial wastewater treatment facility

Facilities must either cease discharge of pressure wash waste water by September 30, 2009 or enter into Consent Order Agreement with CT DEP to extend deadline to December 31, 2010

YOU DON’T HAVE TO SIGN THE CONSENT ORDER

If you don’t sign the consent order, you must: 1. stop discharging pressure wash wastewater to ground or surface water; or 2. stop pressure washing boats…

BY SEPTEMBER 30, 2009

IF YOU DO SIGN THE CONSENT ORDER

If you do sign the Consent Order, you must: 1. Officially sign onto Consent Order by September 15, 2009; and 2. abide by the Terms and Conditions of the agreement and complete all enforceable milestones

BY DECEMBER 31, 2010

Implement 2002 Clean Marina BMPs for pressure washing Submit copy of Exhibit A to Ed Finger @ CT DEP’s Water Permitting & Enforcement Division, to officially enter into Consent Order Prepare & complete all plans and specifications for project File all state and local permit applications (including COP) Obtain all state and local permits, licenses & approvals File Miscellaneous General Permit registration, if required Submit Reporting & Certification Form to CT DEP describing timeline, certifying interim BMPs implemented & actions complete Cease all unpermitted discharges of pressure wash wastewater Submit Reporting & Certification Form to CT DEP certifying that all actions have been complete or certifying that PW discharges have ceased

Pad constructed of impervious material coated with a sealant

EXAMPLE ONLY-NOT FOR CONSTRUCTION

sump Stormwater discharge Process wastewater should not overflow or run off the pad at any time, nor should it accumulate and discharge to ground or surface water Lockable valve, watertight cover or plug, or dedicated power source that can be secured is required for pumps used to divert stormwater Discharge to tank or sanitary sewer NOTE: 1) Pads constructed to allow stormwater to overflow when not pressure washing are considered a point source and subject to the conditions of the Industrial Stormwater General Permit.

Secure stormwater conveyance prior to pressure washing.

Maintain equipment, including hoses, to prevent discharges. Leaks from hoses and equipment are considered process wastewater discharges.

Use a minimal amount of pressure & water Post signs outlining proper operation

EXAMPLE ONLY-NOT FOR CONSTRUCTION

sump Sweep and rinse pad prior to activating stormwater diversion Transport resulting solid waste to a permitted waste disposal facility Discharge to tank or sanitary sewer Stormwater discharge NOTE: 1) O&M for pad must be identified in SWPPP, included in weekly inspections, staff 2) training, stormwater monitoring including sample location and procedures Inspection of pad must be included in Comprehensive Site Compliance Evaluation as part of SWPPP

DEP Guidance on Managing Overspray “process wastewater” Photo credit: Thomas MaGuire, Massachusetts Department of Environmental Protection “overspray”: the incidental spray discharged from a pressure washing gun during boat bottom pressure washing activities that does not come into contact with any boat surface, including any that may drift by air current away from its point of origin * No need to contain overspray as long as water source is a potable water supply and no additional chemicals or pollutants are added *If chemicals are added (eg., treated recycled water source) , no collection necessary if the wastewater meets the target criteria for copper, lead and zinc as specified in the Stormwater GP. The discharge of recycled water from a pressure washing gun must not exceed the following concentrations : Copper 1.3 mg/l Lead 0.04 mg/l Zinc 0.50 mg/l

Facilities that do not sign on to the Consent Order will be subject to the full enforcement authority of DEP as of September 30, 2009