Transcript Document

Environmental Considerations
by
Aimee L. Kratovil, Esq.
Environmental Protection Specialist
San Francisco Airports District Office
Western Pacific Region
Federal Aviation Administration
1
Environmental
Considerations
 Pre-NEPA
 Master Plan
 Airport Layout Plan
 Introduction to NEPA
 What is it?
 What triggers it?
 Where is the guidance?
 What level of NEPA Document?
 NEPA versus CEQA
 Difference in legal thresholds
 Satisfying NEPA and CEQA
 Segmentation Considerations
 NEPA Considerations for Land Transactions
 Categorical Exclusion Form Update
2
Pre-NEPA
 Planning Document Status
 Master Plan




Project definition
Purpose and need
Alternatives
Forecasts

FAA Approved
 Airport Layout Plan
 Conditional approval
 Proposed projects included
 FAA will not program environmental grants or full design grants until the planning process is
complete
 Issuance of a full design grant prior to a NEPA determination is considered a
predetermination of the NEPA process and is contrary to law
 FAA may only issue grants for preliminary design as part of the planning grant prior to a
NEPA determination
 Preliminary design may not exceed 20% of the total planning grant
 Language to this effect will be found in FAA Order 5050.4B when it is enacted
3
Introduction to NEPA
 What is it?
 National Environmental Policy Act of 1969
 Basic national charter for protection of the environment
 Directs federal agencies to act according to the letter and spirit of the Act
 What triggers it?
 The NEPA process addresses impacts of “federal actions” on the human
environment
 What are “federal actions?”
 All airport improvement program grants
 All plans submitted to FAA that require FAA approval
 Where is the guidance?
 FAA Order 1050.1E, Environmental Impacts: Policies & Procedures
 Effective June 2004
 FAA Order 5050.4A, Airports Environmental Handbook
 Being updated
 Draft 5050.4B was released December 2004 for comments
4
Introduction to NEPA
 What level of NEPA Document is required?
 Categorical Exclusion (CatEx)
 FAA Order 1050.1E, chapter 3
 Extraordinary circumstances also found in chapter 3
 Environmental Assessment (EA)
 FAA Order 1050.1E, chapter 4
 Coordinate with FAA EPS early
 Scope of work complete
 Preliminary document sections
» Purpose and Need
» Alternatives
 Regulatory Agency Coordination
 Environmental Impact Statement (EIS)
 FAA Order 1050.1E, chapter 5
 Consult with FAA EPS prior to proceeding
5
NEPA versus CEQA
 NEPA legal thresholds
 NEPA = National Environmental Policy Act
 Requires a statement of purpose and need
 Requires the determination of impact significance to be based upon a
comparison of the No Action Alternative with the proposed development
alternatives in the same future year
 CEQA legal thresholds
 CEQA = California Environmental Quality Act
 Requires a statement of project objectives to define the boundaries of
the project and the types of alternatives to be considered
 Requires the determination of impact significance to be made against
the environmental setting at the time the Notice of Preparation is
published
6
Satisfying NEPA and CEQA
 Write clear and separate definitions of
 The project objectives for the airport sponsor
 The purpose and need for the FAA
 Identify and evaluate alternatives against both the project objectives and purpose
and need
 For each environmental category addressed in the EA/EIR or EIS/EIR
 Clearly separate and delineate the applicable federal and state criteria
 Separately present the federal and state evaluation of the potential impacts of the project
alternatives in light of those criteria
 The Master Plan Example – Timing is Everything
 A Master Plan is a “project” that triggers CEQA
 A Master Plan does not require a “federal action” that triggers NEPA
 “Federal action” would be triggered by approval of the ALP that depicts Master Plan projects
and/or federal funding for proposed projects
 NEPA is concerned only with projects proposed to go forward in the near term (i.e. 5 year window)
 The purpose and need must be adequately defined and justified
 Therefore, there is a distinct difference in the proposed action under NEPA and CEQA
from the start
7
Segmentation Considerations
 Segmentation Considerations
 Requirements of NEPA may not be avoided by segmentation of
projects
 The United States Supreme Court has established three
criteria to “prove” segmentation
The project was originally perceived as unified and
interdependent
The segments do not have independent utility
The segments are not reasonable when considered alone
 Any one of these criteria may be sufficient to prove
segmentation
8
NEPA Requirements for Sale
or Disposal of Airport Land
 A NEPA determination must be made by FAA prior to
any FAA release of grant obligations for sale or disposal
of dedicated airport property
 A release of grant obligations is a “federal action” that
triggers NEPA
 FAA Order 5190.6A, Airport Compliance Requirements,
chapter 7
 FAA Order 1050.1E, Environmental Impacts: Policies and
Procedures
Typically a land release is categorically excluded under FAA
Order 1050.1E, paragraph 307b unless an extraordinary
circumstance as described in paragraph 304 is triggered
9
NEPA Requirements for Land
Acquisitions
 A NEPA determination must be made by FAA prior to
any airport land acquisition
 The airport sponsor must update the ALP and Exhibit A
property map per 49 USC 47107 (a)(16) and the grant contract
when land is acquired for the airport even if federal funds are
not used
 FAA approval of the ALP or federal funding are
“federal actions” that trigger NEPA
 FAA Order 1050.1E, Environmental Impacts: Policies and
Procedures, paragraphs 310b and 310r
Land acquisition over 3 acres requires an Environmental
Assessment unless it is clearly associated with a categorically
excluded action
10
NEPA Requirements for Land
Acquisitions
 If the airport sponsor acquires land for the airport
without prior FAA approval, the action could prejudice
or preclude favorable decision by the FAA on proposed
changes in the ALP or development which would use
the land acquired or on requests for reimbursement for
the property
 Prior to approval of future FAA action involving the property,
the FAA will carefully consider the manner in which the
particular property was acquired and whether it was acquired
consistent with pertinent environmental policy
 FAA Order 5050..4A, Airport Environmental Handbook,
paragraph 33
11
Categorical Exclusion Form
Update
 FAA Western Pacific Region has decided to adopt and utilize an Environmental
Evaluation Form for Categorical Exclusions by March 1, 2006
 The new CatEx Form will focus on analyzing extraordinary
circumstances as defined in FAA Orders 1050.1E and 5050.4A.
 Impact categories to be analyzed include:
 Air Quality
 Coastal Resources
 Department of Transportation Section 303 Lands
 Fish, Wildlife, and Plants
 Hazardous Materials, Pollution Prevention, and Solid Waste
 Historic, Architectural, Archeological, and Cultural Resources
 Noise
 Secondary (Induced) Impacts
 Socioeconomic Impacts, Environmental Justice, and Children’s Environmental




Health and Safety Risks
Water Quality
Wetlands
Other Considerations
Cumulative Impacts
12
Contact List
 If and when in doubt call an EPS:
 The San Francisco Airports District Office
Camille Garibaldi (650) 876-2778, extension 613
 Barry Franklin (650) 876-2778, extension 614
Aimee Kratovil (650) 876-2778, extension 612
 The Western Pacific Region
Michelle Simmons (310) 725-3614
Pete Ciesla (310) 725-3633
Dave Kessler (310) 725-3615
Jennifer Mendelsohn (310) 725-3637
13
The End
Questions?