Transcript Chapter 6

6-0

McGraw-Hill/Irwin Corporate Finance, 7/e

CHAPTER

6

Some Alternative Investment Rules

© 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-1

Chapter Outline

6.1 Why Use Net Present Value?

6.2 The Payback Period Rule 6.3 The Discounted Payback Period Rule 6.4 The Average Accounting Return 6.5 The Internal Rate of Return 6.6 Problems with the IRR Approach 6.7 The Profitability Index 6.8 The Practice of Capital Budgeting 6.9 Summary and Conclusions

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-2

6.1 Why Use Net Present Value?

Accepting positive NPV projects benefits shareholders.

 NPV uses cash flows  NPV uses all the cash flows of the project  NPV discounts the cash flows properly

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-3

The Net Present Value (NPV) Rule

Net Present Value (NPV) = Total PV of future CF’s + Initial Investment Estimating NPV: 1. Estimate future cash flows: how much? and when?

2. Estimate discount rate 3. Estimate initial costs Minimum Acceptance Criteria: Accept if NPV > 0 Ranking Criteria: Choose the highest NPV

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-4

Good Attributes of the NPV Rule

1. Uses cash flows 2. Uses ALL cash flows of the project 3. Discounts ALL cash flows properly Reinvestment assumption: the NPV rule assumes that all cash flows can be reinvested at the discount rate.

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-5

6.2 The Payback Period Rule

How long does it take the project to “pay back” its initial investment?

Payback Period = number of years to recover initial costs Minimum Acceptance Criteria: set by management Ranking Criteria: set by management

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-6

The Payback Period Rule (continued)

Disadvantages: Ignores the time value of money Ignores cash flows after the payback period Biased against long-term projects Requires an arbitrary acceptance criteria A project accepted based on the payback criteria may not have a positive NPV Advantages: Easy to understand Biased toward liquidity

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-7

6.3 The Discounted Payback Period Rule

How long does it take the project to “pay back” its initial investment taking the time value of money into account?

By the time you have discounted the cash flows, you might as well calculate the NPV.

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-8

6.4 The Average Accounting Return Rule

AAR  Average Net Income Average Book Value of Investent Another attractive but fatally flawed approach.

Ranking Criteria and Minimum Acceptance Criteria set by management Disadvantages: Ignores the time value of money Uses an arbitrary benchmark cutoff rate Based on book values, not cash flows and market values Advantages: The accounting information is usually available Easy to calculate

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-9

6.5 The Internal Rate of Return (IRR) Rule

IRR: the discount that sets NPV to zero Minimum Acceptance Criteria: Accept if the IRR exceeds the required return.

Ranking Criteria: Select alternative with the highest IRR Reinvestment assumption: All future cash flows assumed reinvested at the IRR.

Disadvantages: Does not distinguish between investing and borrowing.

IRR may not exist or there may be multiple IRR Problems with mutually exclusive investments Advantages: Easy to understand and communicate

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-10

The Internal Rate of Return: Example

Consider the following project:

$50 $100 $150

McGraw-Hill/Irwin Corporate Finance, 7/e

0 -$200 1 2 3

The internal rate of return for this project is 19.44%

NPV

 0  $ 50 ( 1 

IRR

)  $ 100 ( 1 

IRR

) 2  $ 150 ( 1 

IRR

) 3

© 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-11

The NPV Payoff Profile for This Example

If we graph NPV versus discount rate, we can see the IRR as the x-axis intercept.

Discount Rate

0% 4% 8% 12% 16% 20% 24% 28% 32% 36% 40%

NPV

$100.00

$71.04

$47.32

$27.79

$11.65

($1.74) ($12.88) ($22.17) ($29.93) ($36.43) ($41.86) $120.00

$100.00

$80.00

$60.00

$40.00

$20.00

$0.00

($40.00) ($60.00) 9% 19% IRR = 19.44% 29% 39% Discount rate

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-12

6.6 Problems with the IRR Approach

Multiple IRRs.

Are We Borrowing or Lending?

The Scale Problem The Timing Problem

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-13

Multiple IRRs

There are two IRRs for this project:

$200 $800

0

-$200

$100.00

1 $50.00

$0.00

-50% ($50.00) 0% ($100.00) ($150.00) 2

3 - $800

Which one should we use? 50% 100%

0% = IRR 1 100% = IRR 2

150% 200%

Discount rate

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-14

The Scale Problem

Would you rather make 100% or 50% on your investments?

What if the 100% return is on a $1 investment while the 50% return is on a $1,000 investment?

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-15

The Timing Problem

$10,000 $1,000 $1,000

Project A 0

-$10,000

1 2

3 $1,000 $1,000 $12,000

Project B 0 1 2

3 -$10,000

The preferred project in this case depends on the discount rate, not the IRR.

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-16

McGraw-Hill/Irwin Corporate Finance, 7/e

The Timing Problem

$5,000.00

$4,000.00

$3,000.00

$2,000.00

$1,000.00

$0.00

($1,000.00) 0% ($2,000.00) ($3,000.00) ($4,000.00) 10% 20% Project A Project B

10.55% = crossover rate

30% 40%

12.94% = IRR

B

16.04% = IRR

A

Discount rate

© 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-17

Calculating the Crossover Rate

Compute the IRR for either project “A-B” or “B-A” Year Project A Project B Project A-B Project B-A 0 ($10,000) ($10,000) $0 $0 1 $10,000 $1,000 $9,000 ($9,000) 2 3 $1,000 $1,000 $1,000 $12,000 $0 ($11,000) $0 $11,000 $3,000.00

$2,000.00

$1,000.00

$0.00

($1,000.00) 0% ($2,000.00) ($3,000.00) 5% 10%

10.55% = IRR

A-B B-A 15% 20% Discount rate

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-18

Mutually Exclusive vs.

Independent Project

Mutually Exclusive Projects: only ONE of several potential projects can be chosen, e.g. acquiring an accounting system. RANK all alternatives and select the best one.

Independent Projects: accepting or rejecting one project does not affect the decision of the other projects.

Must exceed a MINIMUM acceptance criteria.

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-19

6.7 The Profitability Index (PI) Rule

PI  Total PV of Future Cash Flows Initial Investent Minimum Acceptance Criteria: Accept if PI > 1 Ranking Criteria: Select alternative with highest PI Disadvantages: Problems with mutually exclusive investments Advantages: May be useful when available investment funds are limited Easy to understand and communicate Correct decision when evaluating independent projects

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-20

6.8 The Practice of Capital Budgeting

Varies by industry: Some firms use payback, others use accounting rate of return.

The most frequently used technique for large corporations is IRR or NPV.

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-21

Example of Investment Rules

Compute the IRR, NPV, PI, and payback period for the following two projects. Assume the required return is 10%. Year 0 1 2 3

McGraw-Hill/Irwin Corporate Finance, 7/e

Project A -$200 $200 $800 -$800 Project B -$150 $50 $100 $150

© 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-22

Example of Investment Rules

CF 0 PV 0 of CF 1-3 Project A -$200.00

$241.92

Project B -$150.00

$240.80

NPV = IRR = PI =

McGraw-Hill/Irwin Corporate Finance, 7/e

$41.92

0%, 100% 1.2096

$90.80

36.19% 1.6053

© 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-23

Example of Investment Rules

Payback Period: Time CF 0 1 2 -200 200 800

Project A

Cum. CF -200 0 800 CF -150 50 100

Project B

3 -800 0 Payback period for project B = 2 years.

150 Payback period for project A = 1 or 3 years?

Cum. CF -150 -100 0 150

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-24

Relationship Between NPV and IRR

Discount rate -10% 0% 20% 40% 60% 80% 100% 120%

McGraw-Hill/Irwin Corporate Finance, 7/e

NPV for A -87.52

0.00

59.26

59.48

42.19

20.85

0.00

-18.93

NPV for B 234.77

150.00

47.92

-8.60

-43.07

-65.64

-81.25

-92.52

© 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-25

NPV Profiles

McGraw-Hill/Irwin Corporate Finance, 7/e

$400 $300 $200 $100 $0 -15% ($100) ($200) IRR 1 (A) IRR (B) IRR 2 (A) 0% 15% 30% 45% 70% 100% 130% 160% 190% Cross-over Rate Discount rates Project A Project B

© 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.

6-26

6.9 Summary and Conclusions

This chapter evaluates the most popular alternatives to NPV: Payback period Accounting rate of return Internal rate of return Profitability index When it is all said and done, they are not the NPV rule; for those of us in finance, it makes them decidedly second-rate.

McGraw-Hill/Irwin Corporate Finance, 7/e © 2005 The McGraw-Hill Companies, Inc. All Rights Reserved.