Hamina 4.2.2015
• Managing Director Timo Toikka
• Hamina Energy Ltd
• Mobile +358 400 556 230
• [email protected]
• Operating engineer, wind power Heikki Lappalainen
• Haminan Energy Ltd
• Mobile +358 406316214
• [email protected]
HAMINA ENERGY LTD
• the company was founded 23.3.1901
• distribution of natural gas was started
3.12.1982
• incorporation: Hamina Energy LTD
1.9.1994
• District heating, own production, internet
services etc. 2000=>
• owned by the town of Hamina (100%)
• Turnover: 38 M€
• Personnel: 55
• Business areas:
– electricity
– natural gas
– district heat
– energy production services
– data sevices
TURNOVER
Other
Natural gas
Electricity
STRATEGY IN FUTURE
•
•
•
•
•
•
•
•
Saving material and services
Saving energy
Reuse of material
Energy from waste
CO2 free renewal energy
CO2 free energy
Renewal energy
Low emission energy
FUTURE INVESTMENTS
Renewable / emission-free energy
• Wind
• Biogas - agriculture/household waste
=> biogas for traffic and electricity
production, fertilizers for agriculture
• Geothermal heating
• Nuclear power
• LNG terminal and power plant
FUTURE OF DATA COMMUNICATIONS
•
•
•
•
•
•
•
•
•
Expansion of WiMAX for dispersed settlement areas
Building of optical fibre network in urban areas
Remote control of meters
Remote control of units
Camera surveillance
Wireless network in logistics
Backup services
TV services
web shop
CO-OPERATION IN HAMINA
CONCERN
•
•
•
•
•
•
Common image in Hamina area
Cooperation in marketing
New industry to the area
Competitive advantage in business
Stability in costs
Euros in our own economic area
STRATEGY FOR THE FUTURE
• Associating in capital intensive investments;
Suomen Voima (16 companies, 500M€ turnover,
800M€ balance sheet and 70M€ investments)
• Promotion of interests, development and marketing
organization Paikallisvoima (40 companies, 500 000
customers)
• Development of local industry and businesses
• Investing in self-sufficient, emission-free production
INDUSTRIAL ENERGY SOLUTIONS
•
•
•
•
steam boiler plant (natural gas)
hot oil boiler (natural gas)
hydrogen plant (electrolysis)
emergency power generator, electricity, heat
(hot oil), steam, burning of process gas,
hydrogen, natural gas, process water and
reserve power
History of wind power in
Hamina
• 30% share of Kotkas 2 MW wind park 1999-2005
• 3 MW wind power plant Kemi, Ajos 2006
– the first commercial 3MW WWD-3 wind power
plant
• 12 MW ( 4x3MW WWD-3) wind park in Hamina,
Summa 2010
• Extencion of Hamina wind park, Harbour 2015=>
(2x3MW Enercon E101)
• New projects (Myllykylä)
• Hamina Energy Ltd is involved in many projects,
both provencially and nationally.
17.7.2015
Phase I
Wind power plant, Ajos
• WWD-3 3MW
– 88 m / 90 m
• 3 MW / 7500 MWh/year
• Ready for the production
2006
• Electricity connection:
Kemi Energia Oy (20kV)
Phase II
Wind Power, Summa
• 4 x WWD-3 3 MW
• 12 MW / 30000 MWh/year
– 100 m / 100 m
• Ready for the production
2010
• Electricity connection:
Haminan Energy Oy, Hillo
110/20 kV substation
Phase III
Wind Power, Harbour
• 2 x Enercon E101 3MW
• 6 MW / 18000 MWh/year
– 101/133 m
• will be completed in the
autumn of 2015
• Electricity connection:
Haminan Energy Oy 20kV
grid
Operation
• WWD3 Wind power plants 4x3MW
– Because WinWind doesn’t exist anymore,we
have a partner, Wind Controller Oy, who
operates our wind turbines 24/7.
• Enercon E101 2x3MW
– We have a long operation and maintenance
agreement with Enercon.
Maintenance
• WWD3 wind turbines
– We have a team that consists of four persons.
• Operating and maintenance engineer
• Three special wind turbine mechanics.
– Technical support from our partner.
• Enercon E101
– Enercon takes care of the maintenance and is
responsible for it to us.
17.7.2015
HAMINA LNG
Thank you for your attention!