Transcript Watermain Rehabilitation Trenchless Technology Today
Watermain Rehabilitation
Eliminating the need for temporary bypass
Derrick Horsman, P.Eng.
Alltech Solutions INC
Overview
Watermain problems and issues
Spray Lining Overview
Same Day Return to Service ?
Eliminating Temporary Bypass
The Problem: Despite recent increases in public infrastructure investments, municipal infrastructure is decaying faster than it is being renewed.
1
1 National Guide to Sustainable Municipal Infrastructure.
Eliminating Temporary Bypass
The Cause: Internal (External) corrosion Watermain breaks Pipe surpassed useful life
Eliminating Temporary Bypass
High Rate of Leakage Inadequate Fire Protection
Eliminating Temporary Bypass
Eliminating Temporary Bypass
Eliminating Temporary Bypass
What do we do?
Eliminating Temporary Bypass
Conventional open cut replacement Low dig options Directional drilling Sliplining Pipebursting CIPP lining Traditional Cleaning and Spray Lining Cement lining process Epoxy lining process Modern Cleaning and Spray Lining Rapid cure polyurethane system Rapid cure high build system
Eliminating Temporary Bypass
Spray Lining
TRADITIONAL CLEANING AND SPRAY LINING
Cement Lining process Epoxy Lining process
• Less expensive • • No reduction in flow capacity No requirement to re-tap services • • • Some disruption Not suitable for certain water types Superseded in Europe by polyurethane lining systems.
• Requires above ground temporary water supply $$$$$$$ ??
Eliminating Temporary Bypass
Spray Lining
TRADITIONAL CLEANING AND CEMENT LINING
Eliminating Temporary Bypass
Eliminating Temporary Bypass
Eliminating Temporary Bypass
Spray Lining
MODERN CLEANING AND SPRAY LINING
Rapid Cure Polyurethane system Rapid Cure High Build system
Eliminating Temporary Bypass
Spray Lining
MODERN CLEANING AND SPRAY LINING
Rapid Cure Polyurethane system Rapid Cure High Build system
• Same day return to service • Only approved rapid cure material <15 sec • Potential for contamination effectively eliminated • No leaching • Immediate rectification of lining faults
Eliminating Temporary Bypass
Spray Lining
MODERN CLEANING AND SPRAY LINING
Rapid Cure Polyurethane system Rapid Cure High Build system
• Same day return to service • No requirement for above ground bypass • Improved customer services; multi-stage notification process • Operations carried out during working hours • Removes potential hazards (ie. Tripping hazards, random breaks, security issues)
Eliminating Temporary Bypass
Spray Lining
MODERN CLEANING AND SPRAY LINING
Rapid Cure Polyurethane system Rapid Cure High Build system
• Same day return to service • • No requirement for above ground bypass Substantially less expensive - cost of bypass 20-45% of total job (Awwarf) • Cost of temporary resources reduced • Shorter construction duration
Eliminating Temporary Bypass
Spray Lining
MODERN CLEANING AND SPRAY LINING
Rapid Cure Polyurethane system Rapid Cure High Build system
• Same day return to service • • • No requirement for above ground bypass Substantially less expensive Greatly reduced disruption • Minimal setup time • Rapid road reinstatement • Small job site footprint
Eliminating Temporary Bypass
Spray Lining Eliminating Temporary Bypass
Spray Lining
MODERN CLEANING AND SPRAY LINING
Rapid Cure Polyurethane system Rapid Cure High Build system
• Same day return to service • No requirement for above ground bypass • • • • Substantially less expensive Greatly reduced disruption Some revaluation of capital asset?
No reduction in flow capacity • Application of 1mm – 5mm
Eliminating Temporary Bypass
Spray Lining
MODERN CLEANING AND SPRAY LINING
Rapid Cure Polyurethane system Rapid Cure High Build system
• • • • • • • Same day return to service No requirement for above ground bypass Substantially less expensive Greatly reduced disruption Some revaluation of capital asset?
No reduction in flow capacity No requirement to re-tap services
Eliminating Temporary Bypass
Spray Lining High Build Structural System
Performance Requirements for Lining Material
1. Tough enough to survive dynamic loading at failure 2. Ductile enough to accommodate movement after failure 3. Sufficient shear strength to maintain longitudinal continuity 4. Sufficient flexural strength to provide long term corrosion void spanning capability
Eliminating Temporary Bypass
Spray Lining High Build Structural System Semi-Structural Lining 6 5 4 1 0 3 2 2 4 6
1 Bar = 14.5 psi @3mm 145psi @5mm 348 psi
8 10 12 14 16 Operating Pressure (Bar) 18 20 22 24 Eliminating Temporary Bypass
Spray Lining – Rapid Cure Polyurethane
Rapid Cure Polyurethane North American Experience • City of Saint John, NB • City of Moncton, NB • Atlantic Health Sciences Corporation, Saint John, NB • Millstone Nuclear Power Plant, Niantic, CT, USA • Region of Niagara, ON • New York Department of Environmental Protection Rapid Cure Polyurethane International Experience • United Kingdom, Russia, India, Switzerland and Malaysia • More than 8,000 km in the UK by our partner affiliates
Eliminating Temporary Bypass
QUESTIONS ???
Eliminating Temporary Bypass