SEMINAR ON ENERGY: ELECTRICITY
TRANSMISSION
A presentation to the
KENYA – SPAIN MULTILATERAL PARTNERSHIP
MEETING
By
Dr. (Eng.) John M. Mativo
Chief Manager (Planning & Development) - KETRACO
9th December 2013
Crowne Plaza Hotel, Nairobi
Vision
“To be a world-class electricity transmission
company and the leading inter-connector in Africa.”
The objectives of our projects are to:
i.
ii.
Evacuate electricity from generating stations
Reinforce the grid network for increased
capacity, reliability and provide redundancy
iii. Interconnect with neighbouring countries
Currently undertaking construction of 3,793km and
53 substations. Feasibility study 20lines
• Engineering, Procurement & Construction (EPC)
contracts
• Engineering, Procurement & Construction +
Financing (EPC+F) contracts
• Consultancy Services
• As IPP Generators with KETRACO evacuating
power
• Capacity Building
3
LOIYANGALANI – SUSWA LINE
Scope: 428km, 400kV double circuit line and
400/220kV substations at Loiyangalani and Suswa
Contractor: Isolux
Estimated Cost: Euro 143million (Transmission Line)
Financier: Spain and GoK
Commencement: Jan 2014 and Completion: Dec 2015
Purpose: To evacuate 300 MW from Lake Turkana Wind
Plant
4
220kV Nairobi Ring & Associated Substation
Scope: 100km, 400kV double circuit line and
substations at Ngong, Isinya, Athi River and Koma
Rock
Contractor: Iberdrola
Estimated Cost: Euro 45million (Substations)
Financier: AFD, EIB & GOK
Commencement: Mar 2013 and Completion: Sep 2014
Purpose: To Increase transfer capacity and increase
5
power
reliability
LESSOS – TORORO LINE
Scope: 132km, 400kV double circuit line and
substation works at Lessos
Contractor: Inabensa
Estimated Cost: Euro 33million
Financier: AfDB & GOK
Commencement: Sep 2013 and Completion: June 2015
Purpose: The project will increase the power
transfer capacity between Kenya and Uganda.
6
Olkaria – Lessos - Kisumu
Scope: 300km, 400/220kV double circuit line and
substation works at Olkaria, Lessos, New Kisumu and
Mamba Leo
Financier: JICA & GOK
Prequalification Commencement: Jan/Feb 2014
7
Kenya – Tanzania Interconnector
Scope: 100km, 400kV double circuit line and
substation works at Isinya (Kenya portion)
Financier: JICA & GOK
Prequalification Commencement: Jun 2014
8
Dongo Kundu – Mariakani line
Scope: 50km, 400kV double circuit line and substation
works at Dongo Kundu & Mariakani
Purpose: The line will evacuate 700-800MW from the
LNG/CNG power plant in Dongo Kundu
Time Line: June 2015
9
Lamu – Kitui – Nairobi East line
Scope: 520km, 400kV double circuit line and
substation works at Lamu, Kitui & Nairobi East
Purpose: The line will evacuate 1000MW from Lamu Coal
power plant and 1000MW Kitui coal power plant.
Time Line: Dec 2016
10
Menengai – Rongai line
Scope: 32km, 400kV double circuit line and substation
works at Menengai* & Rongai
Financier: World Bank
Purpose: The line will evacuate 400MW from Menengai
geothermal power plant.
Time Line: June 2016
11
Silali – Rongai line
Scope: 150km, 400kV double circuit line and
substation works at Silali* & Rongai
Purpose: The line will evacuate 220MW from Soilo
geothermal power plant (1st Phase).
Time Line: June 2016
12
Lamu – Kitui – Nairobi East line
Dongo Kundu – Mariakani line
Scope: 4 lots EPC Transmission line and 2 lots for EPC
Substations
Bid submission Date Time Line: 15th January 2014
13
The planned transmission
network upto 2017 is as
follows-:
• 612km 500kV HVDC Project
• 1,880 km 400kV Projects
• 2,135km 220kV Projects
• 2,587km 132kV Projects
Solar Potential Areas
Wind Potential Areas
Geothermal Potential Areas
14