Pre-Bid Public Meeting

Download Report

Transcript Pre-Bid Public Meeting

BLOCK MEETING
for the
Sanitary Sewer Rehabilitation Phase I
26402-26603 Maplewood Dr., 26611-26803 Westwood Dr.,
Westwood Ct., Eastwood Dr., Hillside Ct., & Wedgewood Ct.
November 29, 2010
City Staff:
Contractors:
Engineer:
 Frank Miller
 Philip Thomas
 Ed Shackelford, P.E.
– Public Works Director
– Reynolds Inliner, LLC
– City Engineer
 Vicky Rudy, PCED
 Juan Ramon Torres
 Steffanie DeLoss, P.E.
– City Manager
– T. Construction & Utility, LLC
– Project Engineer
DISCUSSION OVERVIEW
Above: Pipe Bursting

Construction Locations

Rehabilitation Methods

Resident & Property Impacts

Contractor’s Comments

Contact Information

Questions
CONSTRUCTION LOCATIONS
REHABILITATION METHODS

Pipe Bursting




Main Sewer Line
Service Leads
City Clean-Outs
Cured-In-Place Pipe

Also Called CIPP
Above: Sanitary Sewer Schematic
Above: Pipe Bursting
RESIDENT & PROPERTY IMPACTS

What to Expect:






Your sewer may be disconnected for part of a day.
Your driveway may be blocked for a day.
Construction will impact some landscaping and
improvements in City Rights-of-Way.
Construction will impact traffic.
You may smell an odor.
We need your cooperation.
Right:
Pipe
Bursting
RESIDENT & PROPERTY IMPACTS

Residents should:





Limit discharge to the sewer during construction.
Use extreme caution while in the construction zone.
Consider making arrangements for outdoor pets.
Make arrangements if the work limits driveway access.
Contractor will:





Place door hangers notifying residents 48-72 hours
before construction.
Excavate open trench at each lot.
Remove construction debris.
Limit work to the street Right-of-Way.
Restore sewer services the same day.
RESIDENT & PROPERTY IMPACTS

Owner/Resident Must Remove


Contractor may Remove



Private Improvements in the R.O.W. or Easement
(Sheds, Outdoor Furniture, Landscaping, etc.)
Trees & Large Bushes
Existing Improvements Damaging the Sewer
Contractor may Remove & Replace





Grass & Limited Landscaping
Mail Boxes
Utilities
Pavement
Fences
Above: Pipe Bursting Schematic
CONTRACTOR’S COMMENTS





Timeline
Construction Approach
Coordination
Recommendations
Concerns
Right:
CIPP
Left:
Pipe
Bursting
Above & Below:
Sewer Clean-Out
CONTACTS

Primary Contact
 City


of Oak Ridge North
Frank Miller – 832.458.9997 (Cell)
Secondary Contacts
 Jones
& Carter, Inc.
Left:
Pipe
Bursting
Steffanie DeLoss – 281.363.4039 ext. 1126
 Jonathan White – 281.363.4039 ext. 1202

 Contractor

Philip Thomas – 281.914.0877
QUESTIONS