OKLAHOMA CITY AIR LOGISTICS CENTER

TEAM TINKER

OC-ALC Chrome Plate Reduction

20 FEB 2002 Johnny Tsiao OC-ALC/LPARR (405)736-3481 [email protected]

I n t e g r i t y - S e r v i c e - E x c e l l e n c e

OVERVIEW

CHROME WORKLOAD AT TINKER

HVOF AS ALTERNATIVE

TF33 HVOF QUALIFICATION

TINKER HVOF CAPABILITY

FUTURE TASKS

2

• • • •

TINKER CHROME PLATE WORKLOAD

2063 total parts in CY 2001

– –

constant average of 172 parts per month 29% increase from CY 2000 F110/101 increase due to ENSIP schedule F100 increase due to organic repair qualifications TF33 decrease due to C141 a/c retirement CY 2001 3% CY2000 4% 16% 10% TF33 F100 F110 AND F101 OTHERS 39% 40% 70% 18%

3

NEED FOR CHROME REDUCTION

CURRENTLY TINKER IS A BIG USER OF HEXAVALENT CHROME FOR REPAIR OF ENGINE COMPONENTS

INCREASED RESTRICTIONS ON CHROME USAGE WILL SIGNIFICANTLY IMPACT MISSION READINESS FOR AIR FORCE PROPULSION

IDENTIFY CHROME PLATE FEATURES TO DETERMINE BEST ALTERNATIVES

– –

Review tech data for all chrome callouts Categorize by location and geometric features

4

HVOF AS ALTERNATIVE

LP HAS IDENTIFIED HIGH VELOCITY OXYGEN FUEL (HVOF) COATING AS THE LEADING TECHNOLOGY TO REPLACE CHROME PLATING AT TINKER AFB

TF33 HVOF substitutions provide the greatest initial reduction in chrome usage

F110/101 Aft Shaft is bulk of chrome usage. Chrome repair also used for #4 Seal Housing on as needed basis to support DLA shortage. HVOF alternative is currently available for Aft Shaft.

Currently few F100 components identified for HVOF substitution. However, continual efforts for repair qualifications will identify additional needs

OEMs ALSO SPECIFIES HVOF IN THEIR DESIGNS

LP HAS IDENTIFIED COMPONENTS HAVING SUBSTRATES AND GEOMETRY SUITABLE FOR HVOF APPLICATION

5

HVOF CANDIDATES

TF33 COMPONENTS :

– – – – – – –

AMS 5613, #1 Bearing Support; #2, #4, #5 and #6 Bearing Housing AMS 5616, #6 Hub AMS 5660, Rear Compressor Rear Hub AMS 6280, #2 Bearing . Housing Alternate AMS 6304, LPT Shaft; HPT Shaft AMS 6322, #4.5 Bearing . Retaining Nut AMS 6415, #2 Hub; #2.5 Bearing . Housing

F110/101 COMPONENTS :

– – –

INCO 718, HPT Aft shaft A-286, #4 Carbon Seal Seat (recent addition) SAE 8740, #5 Carbon Seal Seat (may be planned)

F100 COMPONENTS:

– –

AMS 6265, Impeller shaft AMS 6265, Gear shaft

6

TF33 HVOF QUALIFICATION

TF33 IS THE LEAD PROGRAM FOR CHROME REPLACEMENT VIA HVOF

F100 agrees to pattern qualification methodology after TF33

T56 will qualify thermal spray based on Joint Materials Test Protocol

7 COMPONENTS IDENTIFIED FOR ENGINE TEST

Remaining 5 to be qualified by similarity

FUNCTIONAL TEST PROCEEDS ENDURANCE TEST

Fit Check completed

– –

Metallurgical analysis by PW Need Wright Lab assistance for sonic testing

7

TF33 HVOF COMPONENTS FOR ENGINE TEST

#4 hub LPT shaft HPT shaft #1 brg hsg #2 hub #5 brg hsg #6 brg hsg

8

TF33 HVOF COMPONENTS FOR ENGINE TEST

ENGINE TEST PROBLEMS

– – –

Hardware installed on test engine Engine at PW test facility Significant delay due to technical and financial problems unrelated to this effort

Project completion of test by Aug 02

POST ENGINE TEST MATERIAL ANALYSIS IS REQUIRED BEFORE PARTS ARE VALIDATED

9

TF33 HVOF Functional Test #1 Bearing Housing As finished by Engelhard 2/01

10

TF33 HVOF Functional Test #5 Bearing Housing As finished by Engelhard 2/01

11

TF33 HVOF Functional Test #6 Bearing Housing & Seal Runner As finished by Engelhard 2/01

12

TF33 HVOF Functional Test #2, 2.5 and 3 Bearing Journals As finished by Engelhard 2/01

13

TF33 HVOF AMT HPC Rear Hub As received by Engelhard 2/01

14

TF33 HVOF Functional Test #4.5 Bearing & Seal Journals As finished by Engelhard 2/01

15

TF33 HVOF Functional Test #5 Bearing & Seal Journals As finished by Engelhard 2/01

16

TINKER HVOF CAPABILITY KEY PARAMETERS

Booth Installation

– – –

Purchased and installed one Sulzer-Metco DJ system Bio-environmental, safety certification Long term Oxygen supply

Training

Classroom and practical

PW, Engelhard, Metco support

LP Quality Plan

Amend LPP process order to include HVOF

Coating Parameter

– – –

Sampling method Evaluation standards Masking Tools

17

TINKER HVOF CAPABILITY KEY PARAMETERS

Finishing

– – –

Fine finish required for oil wetted parts Tinker has not developed finishing capability Engelhard support

Coating Removal

Need to determine removal method for subsequent repairs

Chemical vs mechanical

OEM Qualification

Two part PW source approval: General Process and Part Specific

– –

Working on establishing PW support for source approval Need to address GE components

18

TINKER INHOUSE HVOF ROADMAP

START HVOF Roadmap Legend:

Tinker Englehard PWA Spray Equipment Installation Jan '02 Metco Bio, Fire Safety Approval Englehard and Metco Facility Operational Training Bulk Oxygen HQ Approval Develope Training Manual Funded Fy '02 OJT Classroom Testing Bulk Oxygen Installation TIESV Met Lab RDE Contract Evaluation Standards Coating Polishing Procedures Hands on w/ MCL Lab Quality Documents Revision PWA Program Plan Quality Plan LPOI 21-166 Process Order LPP 85-11 LPA/ LPF/ LPQ Approval Coatings Parameters PWA 36206-1 Robotic Programs Tinker and Englehard Lab Samples Masking/ Tooling Coating meets Specification Requirements?

No Yes SEE PAGE 12 Preliminary Qualification Part Specific Qualification See PWA Flowsheet Proceed to the next part requiring qualification Program Plan Requirements Met?

Yes END Approval Granted

19

PW QUALIFICATION PROCESS

PRELIMINARY

Improve Process Qualification Request See Note 1 Preparation of Requested Material See Note 3 Submittal of Requested Material Rework Process Schedule Meeting to Review Qualification requirements Process Process Qualification Samples Submittal of Qualification Samples Rework Process Qualification Granted Samples Fail - Creates Replog Entry See Note 2 - Identifies Necessary Steps for Qualification Process - Notifies Requester - Submits Material For MCL Review and Approval to Specifications - Review Results and Communicate to Source Samples Pass - Review of Process Qualification Requirements and Plans See Note 4 Samples Fail Samples & Document Review Acceptable - Submits Material For MCL Review and Approval to Specifications - Review Results and Communicate to Source - MCL Prepares the Material for Review and Compares Samples to Specifications - Provide Results to MME

PARTS SPECIFIC

- MCL Prepares the Material for Review and Compares Samples to Specifications - Provide Results to MME 20

FUTURE TASKS

New part numbers and Tech Data must be introduced

Class I Engineering Changes required for configuration control

Additional funding for OEM through CIP needed

More extensive process quality control requirements

Standardized evaluation of process qualification

Process tech data incorporation to T O 2-1-111

Particle liberation in oil wet areas

Design requirements defined by OEM

JOAP trending impacts

Atomic absorption limitations with tungsten

AMT engine will define criteria

program specific issue joint issue 21