Leading a Peer Review - Association of Local Government
Download
Report
Transcript Leading a Peer Review - Association of Local Government
Roles & Responsibilities of
Peer Review Team Leaders
Instructors:
Kelly Hammond
Ruthe Holden
1
Session Objectives
Brief Overview of Peer Review
Team Leader Roles & Responsibilities
Tips and Resources to being a great
team leader
2
Purpose & Objectives of Peer
Reviews
Evaluate the Design & Operation of a
Department’s Quality Control System
Provide Reasonable Assurance that a
Department Conforms with GAGAS
3
What Does “Conforms” Imply?
Conform (def): To come to have the same
form or character.
Reasonable Assurance of Conformity
Does not Imply Perfection
Can be Form over Substance
4
Quality Control System
GAGAS 3.83 states that the formality of an
audit organization’s quality control system
will vary based on its size, people,
complexity of its work, and cost-benefit
considerations.
5
TEAM LEADER ROLES &
RESPONSIBILITIES
6
Team Leader Roles
Guide Review Team
Perform QCS review
Lead Entrance & Exit Conferences
Manage Peer Review Schedule
Responsible for Peer Review Report &
Management Letter
7
Administrative Pre-site Visit Work
Team Leader needs to:
Set-Up Binder and Dividers for Work
Use Suggested Index
Facilitates an organized approach
Road Map of documentation to be produced
8
9
Suggested Workpaper Index
30 Days From Site Visit
Review Materials and Begin “Review of QCS”
Background
Policies and Procedures
Description of QCS
Listing of Engagements
CPE Form
All team members should review the material
Discuss meeting agency officials with Audit Director
10
Collaborative Meetings
Webex meeting www.webex.com
AnyMeeting www.anymeeting.com
Join.me https://join.me
ShowDocument www.showdocument.com
GoLiveRoom www.goliveroom.com
Yugma www.yugma.com
Mikogo https://go.mikogo.com
11
10 Days From Site Visit
Sample Selection - preliminary
Logistics
Preliminary Observations
Draft Report & Management Letter
Report Cover
12
Preliminary Observations
Pre-Site Visit Review of QCS Design
“No” Answers Will Require Discussion
Benefits of Early Communication
Department has more time to consider
issues
Promotes openness
Enables quicker resolution once on-site
13
Site Visit Schedule
Monday
Tuesday
Wednesday
Thursday
Friday
Entrance Conference
CPE Review, Interviews, Work on QCS
Engagement Reviews – 25%
Finish QCS
Engagement Reviews – 75%
Assess Non-audit Work
Finish Engagement Reviews
Finish Interviews, Summary of Exceptions
Review w/ Coordinator
Exit Conference, Prepare Report
Wrap up Reporting, W/P’s
Celebrate!
14
First Day On-Site [Sunday]
Team Planning Meeting
Should be Documented
“No” answers must be covered with
responsible auditor; allow him/her to
research and explain
Emphasize Fast Start / Thursday Report
Sharing vs. Projecting
Team Discussions vs. Extemporizing
15
Forming the Opinion
Pass does not = 100% compliance
Pass with Deficiencies or Fail
Maintain Open Mind and Composure
Contact Coordinator Early
Fax / Email Summaries of Exceptions To
Coordinator
16
TIPS & RESOURCES
17
TEAM LEADER TIPS
CPE
Don’t get too mired in details. Real measure of
competence is in the actual audit work.
Delegate Non-Audit Services Form
Communicate Regularly on issues
Engage the team 2-3 times a day to see what issues
are developing
Talk to Coordinator early in week if:
Issues arise
Planning to issue a pass w/ deficiencies or fail
18
Team Leader Tips
Verify Documentation Submitted
Audit Engagements list not always accurate
Number of engagements in background does
not match Audit engagements list
Verify Staff availability
19
Team Leader Resources
Standards/Standards/Standards!
Peer Review Guide
Review Leader Checklist
Team Members
Peer Review Coordinator
20
Full Disclosure
(i.e. Stuff Happens)
Illnesses
Inflexible Team Member
Audit Director Unavailable
Outside Pressures
Travel Snags
Resistance to Results
These are rare, but if they happen, work
with the coordinator.
21
IN SUMMARY
Prepare Early
Be Organized & Have a Plan
Listen & Ask Questions
Use Your Coordinator As A Resource
Standards are the Standard
Stay Calm - Build Consensus
22
Questions?
23