New Rapid Sand Filters - Whitehead
Download
Report
Transcript New Rapid Sand Filters - Whitehead
Benjamin C. Whitehead, PE
Benjamin J. Klayman, PhD, PE
Case Study: Commissioning
New Rapid Sand Filters at
Donald K. Shine Water Treatment Plant
July 2010
July 2010
Plant Flow Schematic
July 2010
South Treatment Facility – Phase IB Expansion
July 2010
Type of Filtration
Six New Conventional Rapid Sand Filters
Roberts Leotech Underdrain w/IMS Cap
12-inches Sand
24-inches Anthracite
Water and Air Scour Backwash
1360 sq.ft. per Filter
4 gpm / sq.ft.
July 2010
New Filter Installation
Filter Underdrain
J-Tube Riser Air
Scour Manifold
July 2010
New Filter Installation
Grout Infill
July 2010
Grout Bed
New Filter Installation
July 2010
Completed Underdrain
Filter Media Installation
July 2010
Completed Filter Cell
July 2010
Filter Backwash Equipment
Air Scour Blower
Gardner-Denver
Multi-stage
300
Centrifugal
Hp
5440 scfm @ 6.2 psig
Backwash Pump
Perless
Pump Company
Vertical Turbine Mixed Flow
250 Hp
32 MGD @ 17.5-feet TDH
July 2010
Filter Backwash
Backwash Sequence
Drain filter to 6-inches above
Initiate Air Scour 2 minutes
media
Add
4 gpm/sq.ft. Low Rate BW (8 MGD) until just
below troughs
Stop Air Scour and continue Low Rate water only to
top of trough
Initiate 17 gpm/sq.ft. High Rate BW (32 MGD) 4
minutes
Low rate BW (8 MGD) for 1 minute
10 minute settling delay
Open effluent valve 2 minutes after filling starts
Backwash is reclaimed / returned to raw
water influent of the plant
July 2010
STF Filter
July 2010
Filter Backwash – Selectable Parameters
July 2010
Backwash with Air Scour
July 2010
Backwash with Air Scour
July 2010
Backwash
July 2010
Backwash
July 2010
MDNRE Requirements
2 Consecutive 15 min. NTU > 1.0
2 Consecutive NTU > 0.5 first 4 hours
2 Consecutive NTU > 1.0, 3 consecutive months
2 Consecutive NTU > 2.0, 2 consecutive months
B&V / City of Wyoming Start-up Goals
Maintain NTU < 0.3 (<0.1 normally)
< 0.1 NTU @ 7 MGD
July 2010
Commissioning Plan
How do we get there?
Careful Planning
Start Slowly
Filter to Rest
Monitor/Operate Closely
Flow
Turbidity
Headloss
July 2010
Commissioning Pre-requisites
Media Washing/Screening
VOC testing
Chlorination
Instrumentation / Alarms
Monitoring / Trending
SCADA Control
Backwash Equipment
Backwash Sequence
Transfer Pumping
July 2010
Commissioning Plan
Initial Start-up:
Initiate Filter Off-line (Filter-to-Waste)
1 MGD, Filter-to-Waste until < 0.3 NTU
Filter
On-line: 1 MGD
> 0.3 NTU, Initiate Settling-delay: 4 hours
Re-test: <0.1 NTU up to 3 MGD
Seasoning:
2 weeks up to 3 MGD
1 week off-line
July 2010
Commissioning Plan
Performance Test:
Run Filter Several minutes
Backwash
Place On-line, 1 to 3 MGD
Ramp 0.5 MGD @ 30 min intervals
>
0.2 NTU Initiates Continuous Monitoring
> 0.3 NTU Initiates Filter-to-Waste
Ramp to 7 MGD for 1 hour < 0.1NTU
July 2010
SCADA Screen – STF Filter Overview
July 2010
Filter No. 13 Start-up
0.8
Flow
Head Loss
Turbidity
Flow (MGD) / Head Loss (ft)
7
0.7
6
0.6
5
0.5
4
0.4
3
0.3
2
0.2
1
0.1
0
1/4
1/5
1/6
1/7
1/8
Time
July 2010
1/9
1/10
1/11
0
1/12
Turbidity (NTU)
8
Filter Performance (Results)
Filter Influent Turbidity: +/- 0.3 NTU
Filter Effluent Turbidity: < 0.1 NTU @ 7 MGD
Filter Effluent Turbidity: 0.02-0.07 after Initial
Commissioning & Current Conditions
Filter Headloss: 1 to 7.5-feet
Run Time: 200 hours - New and Existing
Filters
4X
longer after expansion
Previously 40-60 hours
July 2010
Filter Performance
Meurer Research Inc. Plate Settling Equipment
July 2010
Field Engineering Improvements
Reduced Washwater Quantity
Reduced High Rate
Total Wash Volume
Wash: 10 minutes to 4 minutes
= 75 gal / sq.ft. (100,000 gal)
Industry Standard = 150-180 gal / sq.ft. (250,000 gal)
Allows for 5 Consecutive Backwashes to Reclaim
Operator Adjustable Settling Delay
Washwater Launder Stabilization
Headloss Instrumentation Calibration
Air Distribution Optimization
July 2010
Questions?
- 31
July 2010