Transcript Slide 1

Resistance Seam
Cladding
September 13, 2011
David Workman
Senior Engineer, Resistance and Solid-State Welding
Email: [email protected]
Phone: 614.688.5244
Resistance Seam Cladding for
Linepipe – Background

CRA pipe
─ 316 SS or High-Ni alloys

CRA is becoming critical
─ Gas applications with CO2 and Cl ions
─ Fluid applications with H2S
─ Abrasion resistance


Very expensive as a solid pipe
Clad CRA pipe
─ Reduced cost per foot of piping system
─ Steel substrate with 2- to 3-mm clad layer

CRA cladding methods are:
─ Roll bonding
─ Metallurigical bonded
─ 50% of market
─ Mechanical bond
─ Plastic deformation of CRA
─ 30% of market

Other clad processes: explosion and arc
cladding
Dia (mm)
Wall (mm)
Clad t (mm)
Base Mat'ls
Price $/m
Price $/m
Mech Clad
Margin $/m
Price $/m
Arc Clad
Margin $/m
Price $/m
Roll Clad*
Margin $/m
150
19
3
$303
$900
$597
$1,964
$1,661
$1,742
$1,439
350
19
3
$835
$2,150
$1,315
$3,976
$3,141
$4,402
$3,567
Why Resistance Seam Clad?







Shorter turn time (reduced WIP)
Faster production rate
Simple parts configuration
Flexibility to alter pipe or CRA on the fly
Lower cost $/per foot less than other metallurgical
cladding processes (estimated $1150/foot at 150-mm
diameter)
Comparatively low capital investment
Ability to use DOM pipe
Flat Plate Trials – EWI Project No.
51549GTO







Trials between flat steel plate and
1- to 3-mm CRA clads
Thermal analyses associated with
the process evaluated
Clads showed up to 100% bonding
Surfaces were flat to within 100 μm
Improved thermal profiles seen
with thinner clad layers
Shear test failed in base metal
Proof of concept established
Weld Quality when Applying CRAs
to Steel Pipe with RSeWC





Full-face bonding observed
during testing
Shear tests failed consistently in
the clad
Adaptation to pipes showed
better than 90% bonding
No dilution seen on the
sectioned pipe samples
Tracking and surface quality
being addressed by improved
tooling
Metallographic Sections



Narrow fusion zone apparent
between CRA and Pipe
Free of voids
Fusion zones overlap to
create continuous welded
interface
Process Adaptations to Round
Pipe – EWI Project No. 52864IRD

Adaptation of deep reach seam
welding system
─ 200-kVA transformer
─ Dedicated tooling for pipe positioning
─ Flood cooling integral to the process



Steel pipe ~10-mm wall × 350-mm
diameter
Inconel 625 liner rolled from sheet
stock ~2-mm thick
Process adapted to the deep reach
welding frame
─ Lower speeds and currents
Functionality of the Welding System




Water cooling to protect wheels
Process adaptations for
specific welding system
Industrial level cleaning of pipe
for joining
Demonstrated overlays to
create continuous attachments



Minimal residual heat from the
process
Minimal disruption to clad
surface
Wheel designs to minimize
disruption of external pipe
surface
How is it Applied to Line Pipes?





DOM pipes can be used or
welded pipes
Internal pig is used to
transfer force and current
through the pipe section
without compromising pipe
wall
Normal high current
Resistance seam welder is
used to drive the system
Systems can be ganged to
run multiple heads
simultaneously
40-foot section very easily
managed in production setup
Why Does it Work?

The welding process is laid out to confine fusion
zone to the CRA –Pipe ID interface
─ Proprietary surface preparation techniques




Resistance seam welding is an established process
for joining similar material thickness parts
Solidification of fusion zone occurs under welding
force applied by wheels to create sound
microstructure
Process is self regulating
Welding force maintains fit-up between CRA and
Pipe ID
Modeling of Thermal Profile in Joint
1600
Temperature (C)
1400
1200
1-mm, 16.7-kA
1.8-mm, 16.7-kA
1000
3-mm, 16.6-kA
800
600
400
0
0.2
0.4
0.6
0.8
Fractional Distance Through the CRA
1
1.2
Speed Effect on Thermal Profile in
Joint
1600
Temperature (C)
1400
1200
1000
50-mm/min, 6.9-kA
800
100-mm/min, 9.7-kA
300-mm/min, 16.7-kA
600
400
0
0.5
1
Distance Through CRA (m m )
1.5
2
State of Technology


Shown to meet or exceed user quality specifications
for flat plate applications
Round pipe applications require significant
equipment investment to reach quality level of flat
plate trials
─ To date results are above required levels
─ Further improvements are expected with tooling enhancement

Cost analysis shows that the process is lower cost
than competitive technologies
Questions?
David Workman
Senior Engineer, Resistance and Solid-State Welding
Email: [email protected]
Phone: 614.688.5244