Transcript Slide 1

Workface Planning
APEGGA Conference
Apr 2007
Jeph Virtue
Answer these….
• Who are COAA Workface Planning Members and
Sponsors?
• What is Workface Planning?
• Why do it?
• How does it work? (including “the Rules”)
• What is your role?
• Want more info or training?
Committee Members
Jeph Virtue
Suncor
(Chair)
Simon Marshman
Frank DeLuca
Niels Frederiksen
Doug Hawkins
George Jergeas
Preston Noton
Lloyd Rankin
Raymond Rewcastle
Geoff Ryan
Pat Synnott
John Vincent
Flint
Maurice D’Aoust
Bird Construction
Ron Embury
Jacobs
Dan Garon
CLRA
Jose Herrero
UofC
Ray Johnson
Hatch
Ronald Ramsay
UofC
Randy Regan
Bantrel
Brian Roy
Jacobs
Gary Semaniuk
Jacobs Catalytic Ltd.Celina O’Neill
Colt
Bill Luxton
Jacobs Catalytic Ltd.
NOVA
Fluor Canada
Fluor Canada
Bantrel
Bantrel
Suncor
Brand Scaffold
Stantec
Suncor
SAIT
Sponsors
Alberta Building Trades Council
Bantrel
Bantrel Constructors
Bird Construction
Christian Labour Association of Canada
Construction Labour Relations – Alberta
Shell Canada Limited
Suncor Energy Inc.
TransCanada Pipelines
COAA Members
Fluor Canada
Ledcor Group
Workface Planning Definition
• Workface Planning is the process of organizing and
delivering all the elements necessary, before work is
started, to enable craft persons to perform quality
work in a safe, effective and efficient manner.
Size of the Prize
Tool Time
37%
Wait
Time
15%
Tool Time
47%
Wait
Time
~5%
• 10% more tool time is a 25% improvement in productivity
• Safety, morale and predictability improvements
One Bite at a Time
Workface
Planning
Rework
Absenteeism
Bench
marking
Supervisory
Skills

Supervisor
Mentoring


Workface planning will not solve all productivity issues … but it’s a good start
Workface Planning Works!
Project A
Same:
Owner
EPCM
Plant Type
Size
Time period
Workface Planning added later
Behind schedule
Project B
Workface Planning from start
~25 to 30% better production
On Plan
Thesis Extract: Conclusion
“There is sufficient evidence to conclude that workface planning, as developed
by the COAA steering committee, contributes to higher project performance.”
Owner Commitment
“Plan the Work”
Workface Planning
“Release the Work”
“Work the Plan”
Supervisor
Dedicated Planner
Prerequisites
Materials & Equipment
Coordinators
Field Installation
Work Package
Materials
Tools
Equipment
Trades/Specialists
Detailed Plan
Drawings
Vendor Info.
Safety Requirements
Supervisor Review
Scope
Ready
√
Team
Tools
37%
47%
1 day to 4 weeks of
defined scope.
Tool Time Improvement
A Supervisor’s Day
Meetings
QA/QC
Initiatives
+
+
Paperwork
Safety
Planning
+
-
+
+
+
-
Supervision
15%
On-site
Travel
+ always grows
-
gets squeezed
Not enough direct supervision. Planning suffers when busy.
Construction Mgr
Construction Mgr
Superintendent
General Foreman
Work
the
Plan
Plan
The Dedicated
Work Planner
Plan
the
Work
Superintendent
General Foreman
Foreman
Crew
Foreman
Crew
Foreman
Crew
Foreman
Crew
Foreman
Crew
Work
the
Plan
Foreman
Crew
Foreman
Crew
Foreman
Crew
Foreman
Crew
Foreman
Crew
Performance Improvement
Workface Planning Rules
#1: Appoint Dedicated Planners
Why do we do this?
Workface Planning Rules
#2: Planner completes Field Installation
Work Package (FIWP) and releases when
ready
Field Installation
Work Package
Materials
Tools
Equipment
Trades/Specialists
Detailed Plan
Drawings
Vendor Info.
Safety Requirements
Supervisor Review
Workface Planning Rules
#3: Complete FIWP at least 4 weeks prior to
construction start on that FIWP
Workface Planning Rules
#4: Provide Planners with latest versions of
documentation
Workface Planning Rules
#5: Track progress of each FIWP vs targets
Workface Planning Rules
#6: Develop a backlog of FIWP’s
Workface Planning Rules
#7: Assign responsibility for integration
planning
Workface Planning Rules
#8: Assign responsibility for Material,
Construction Equipment, Scaffold and
Specialty Tool Coordination to Dedicated
Coordinators
Workface Planning Rules
#9: Develop Startup sequence, then path of
construction, then Construction Work
Package Release Plan
Workface Planning Rules
#9 (Cont.):
1)
Develop Startup sequence
2)
Path of construction
Considerations
•
Start-up Sequence
•
Manhours
•
Congestion
•
Access
•
•
•
•
Levels
Complexity
Equipment Delivery
Time to complete
3) Identify Construction Work Packages (CWP) and CWP Release Plan
Workface Planning Rules
#10: Write requirement for Workface
Planning into contracts
Workface Planning Rules
#11: Audit to ensure rules are being followed
DBM
Prerequisites - Owner
• Executive declaration: “Use COAA Workface Planning!”
• Appoint Workface Planning Sponsor and Champion
EDS
• Develop Workface Planning Execution Strategy for project
• Determine systems, tools, organization
– Determine how Workface Planning Principles will be implemented
– Roles and Responsibilities specific to Workface Planning
– Align key stakeholders
EPC
• Include Workface Planning requirement in Contracts
• Define startup sequence of units
• Support and audit
• Expect Construction Indirects to be higher; but overall Total
Installed Cost to be lower
DBM
Construction Management
• Commit to Workface Planning
• Make it happen (all phases)
EDS
• Develop Workface Planning Execution Plan for project
• Develop Path of Construction (with Eng and Contractors)
– startup sequence
– construction logistics and time to complete – by area
EPC
• Include Workface Planning requirement in contracts
• Identify Construction Work Packages (CWP) and release plan
• Appoint Integrated Planner
•
•
•
•
Perform Constructability review (with Eng and Contractors)
Coordinate dedicated planners via integrated planner
Manage rub points
Roll-up overall FIWP progress
EDS
• Commit to Workface Planning
• Develop Path of Construction with Construction Management (CM)
• Identify Construction Work Packages (CWP) and develop release
plan with CM and Eng
• Appoint Dedicated Planners, Equipment Coordinators, Scaffold
Coordinators and Workface Planning Leaders
EPC
DBM
Construction Contractors
•
•
•
•
•
•
Perform Constructability review (with CM and Eng)
Break CWP into Field Installation Work Packages (FIWP)
Identify FIWP’s and FIWP release plan
Develop FIWP’s
Feed 3 week lookahead schedule with FIWP releases
Execute FIWP – track progress
EDS
DBM
Prerequisites - Engineer
• Commit to Workface Planning
• Incorporate Workface Planning into Stds, Procedures and Job
Instructions
• Establish Work Breakdown Structure
• Develop Path of Engineering
EPC
– based on Construction Work Packages and release plan
– allow 2 to 3 months between IFC and construction start
– communicate to team consequences if missed (MEET THE PLAN)
• Deliver CWP’s per the release plan
• Provide document updates to dedicated planners
Training
• ½ Day Overview ($400)
– Executive, Management, Supervision
– Owner, EPCM, Construction Contractors
• 4 Day Workface Planner Course ($2400)
– Workface Area and Integration Planners, Champions,
Coordinators (Equipment, Material, Tool, Scaffold)
– Owner, Construction Contractor, Construction Manager
• Available now
More Info
• www.coaa.ab.ca
• COAA Conference: May 15 eve, May 16
• Thankyou