Biowaste to Bioenergy through Gasification
Download
Report
Transcript Biowaste to Bioenergy through Gasification
February 1, 2011
Biomass Program Review IBR & Infrastructure
Dr. Douglas M. Goodale, PI
Executive Summary
Develop a simple approach to convert wastes to
energy.
Direct pathway to liquid fuels or combined heat and
electrical power (CHP).
Despite significant hurdles, all testing is complete
and the project is progressing to closure.
Project will be complete by Dec. 31st, 2011 and
within the original budget.
2
Quad Chart Overview
Timeline
Project Start Date
Project End Date
Mechanical turnover
Start-up planned
Commissioning
Percent complete
6/1/08
12/31/11*
N/A
6/1/11
6/1/11
90%
Project Development
Current status
on target
Cost
within budget
Schedule
within schedule
Project scope
no change
Project complete 12/31/11
* No-cost extension request in process
Budget
Total Project Funding
DOE Share
Contractor Share
Funding Received by FY
10/1/08 – 9/30/09
10/1/09 – 9/30/10
10/1/10 – 2/1/11
Project Participants
Collaborations
W2E USA, Inc.
$1,279,200 Intellectual property W2E USA, Inc.
$0
Project Management-Doug Goodale
Construction Management
N/A
$767,520
Start-up and Commissioning - W2E
$511,680
Operations -W2E & SUNY Cobleskill
$0
3
Spend Plan
$1,400,000
$1,200,000
$1,000,000
$800,000
$600,000
$ Rec'd DOE
$ Spent SUNY
$400,000
$200,000
$0
FY09 FY10
FY10 FY10
FY10 FY11
Q1 Q2
Total
Q3
Q4
Q1
4
Project Overview4
Task
21
4
6
8
10
Months
12 14
16
18
20
22
24
1
2
26
Finish installation
at SUNY
2
3
4
3
5
1 start
2
date 3-12-10
Arrival date 3-20-11
Original Target Completion
Actual Completion
Install at SUNY
3 Closing date 3/31/11
4
no cost variance
5
Major Technical Hurdle
The complexity of the bench scale gasifier requires
locating in specially designed building.
Funding was secured from the State of New York for a
new building to locate the gasifier on the SUNY
Cobleskill campus.
Center for Environmental Science and Technology
(CEST) was completed in Nov. 2010, requiring all hot
testing to be done at the point of equipment
manufacture in India.
All hot testing was completed and the equipment is
currently in transit to the SUNY Cobleskill campus.
6
No Cost Extension
Installation of the prototype gasifier in the CEST is a
deliverable.
Shipment of equipment from India was delayed until
the building was complete and available.
Two no-cost extensions were requested to fund
installation and meet deliverables.
The current request for a no-cost extension would
allow complete installation of the gasifier in the CEST
by Dec. 31, 2011.
7
Commercial Cost
This technology is ideally suited for 100 kW to 5 MW
of electrical generation capacity.
The projected cost for engineering, permitting,
construction, and commissioning of a 1 MW waste to
combined heat and power facility is estimated at 7
million USD.
A 1 MW facility converts about 15,500 tons of waste
annually into enough electrical energy to power 680
residential dwellings (85% utilization).
8
Project Approach
1. Establish & commission innovative gasification system
2. Test the system – determine system efficiency
3. Adjust system, retest and recalculate efficiency
4. Completion of each task served as a go/no-go
milestone
5. Relocate system to campus upon completion of CEST
facility
6. Prepare for system scale-up
7. Maintain synchronization with DoD grants
9
Technical Accomplishments
Milestones -chronologically by accomplishment date
(Each milestone represented a “go/no go” decision)
1. Installation of gasifier at point of origin
2. Gasifier operation
3. Data analysis
4. System install on campus (anticipated)
08/11/09
12/31/10
02/28/11
12/31/11
Project objectives
All objectives are met except on-campus installation
Technical Accomplishments (most important)
Proved system will convert biowaste into bioenergy
Bench Marks
1. Met 90% of project objectives since last report
2. Achieved all technical targets
10
Project Status
% Complete
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Task 1 - Cold Testing, Calibration, Installation at SUNY
Task 2 - Operations Plan, Data Analysis Plan, Operations
Task 3 - Model for Ag Wastes, Scale Up Criteria, Model
Validation, Process Improvements
Complete
Incomplete
Task 4 - Institutional and Farm Models
Task 5 - Project Management
Final Reporting
11
View Video of Bench Scale Gasifier to
be Installed at Cobleskill Campus
12
Summary of Test Results
Average
Hay - 30% O2
% Target of
Efficiency
% Target of
Heating Value
Hay - Air
Cow Manure - Air
Wood - Air
0.0%
25.0%
50.0%
75.0%
100.0%
13
Project Relevance
Thermochemical Conversion Platform in section
3.2.2 of the Biomass Multi-Year Program Plan.
Thermochemical Gasification Route
Processes high moisture and high ash biomass with
minimal or no preparation.
Operates on air, enriched air, or pure oxygen at
atmospheric pressure without catalysts.
Effective and simple scrubbing method.
Agricultural Residues Pathway
14
Project Relevance
Project Meets (see sections 3.2.2.3 and 3.2.2.4)
WBS 3.1 – Feedstock Thermochemical Platform Interface
3.1.1 Feedstock Variability
3.1.2 Processing Interface
WBS 3.2 – Thermochemical Processing Core R&D
3.2.1 Biomass gasification
3.2.5 Syngas clean-up and conditioning
3.2.6 Fuels Synthesis (Future)
WBS 3.3 – Thermochemical Process Integration Core R&D
3.3.1 Thermochemical Processing Integration
3.3.2 Thermochemical Platform Analysis
WBS 3.4 – Fundamentals and New Concepts.
3.4.1 Advanced Thermochemical Processing
15
Success Factors and Challenges
Critical Success Factors
Minimal feedstock preparation and management.
Chemistry of gas is sufficient for synthesis into other
energy forms.
Challenges
Hot testing had to be completed in India to avoid
unreasonable delays.
Results need to be validated in the US.
Equipment installation on the SUNY Cobleskill campus
(currently in transit from India).
16
Benefits
Wastes can be simply converted to a clean energy
form (gas, liquid, electrical, and heat).
Reduces the disposal of agricultural and municipal
wastes.
Any waste that is flammable can be used as a
feedstock.
Process produces a flammable gas, which can be for
heating and electrical generation, or synthesized into
a liquid fuel.
Gas is scrubbed prior to use, allowing for
combustion that is cleaner than natural gas.
The only byproduct from the process is ash.
17
Expected Outcomes
Numerous small waste to energy facilities can be
installed near the points of waste generation
Reduces emissions from trucking.
Reduces load on the grid (transmission losses, distributed
power, etc.)
Electrical power is fed onto the grid, waste heat can be
used for space and water heating purposes.
Syngas is rich in hydrogen and is easily separated for
use in support of a hydrogen economy.
Syngas can be synthesized into liquid biofuels either by
chemical or biological pathways (various alcohols, DME,
Fischer-Tropsch).
18
Commercial Viability
Can be very profitable since a tipping fee is charged
to receive the waste.
Suitable wastes (agricultural, cafeteria, municipal
solid, sludge, etc) are in ample supply and disposal
is costly.
Income streams include tipping fees, gaseous fuels,
liquid fuels, electrical generation, and offsetting fossil
fuel usage by using waste heat.
This technology is creditable since very little or no
feedstock preparation is required.
19
1 MW Combined Heat and Power Generating
Facility on SUNY Cobleskill Campus
1 MWe operating at 85% utilization will generate
7.45 million kW-hrs per year (54% of total campus
usage).
Partial or complete heating of the campus is
possible, depending on the generating technology
used.
Generating on-site and using waste heat offsets
emissions from large generating stations.
20
Economics of 1 MWe CHP
Electrical generation: 7450 MW-hr at 85% utilization
Electrical Savings: $335 K at $0.045 per kW-hr
Natural Gas Savings: $375 K at $7.53 per Dth
Operating Costs: ($930 K) at $125 per MW-hr
Tipping Fees for Wastes: $1,008 K at $65 per ton, 15,500
ton/year
Net Income EBITDA: $788 K per year.
Simple ROI: 8.9 years for $7 million USD plant cost.
Environmental sustainability with minimal water usage or
disposal, 1.3 MW gross to net 1 MWe.
21
Technology Transfer
New Curriculum
Title:
Degree:
Approval:
HEGIS Code:
Program code:
Environmental & Energy Technologies
Bachelor of Technology
NYS Education Department Aug 2010
0115
33972
Training Seminars - examples
Distance Learning
Short Courses
One-day training
22
Project Summary
Relevance: Project aligns with DOE’s Biomass Multi
Year Program Plan.
Approach: Project aligns with Thermochemical
Platform Objectives, but there is more R&D to be done.
Accomplishments: Proved biowastes can be
converted to bioenergy with minimal feedstock
preparation.
Success factors: Deliverables were completed despite
the challenges of installation on the campus.
Run Tests: Successfully completed in India.
23
Thank You
Douglas M. Goodale, PhD
[email protected]
Biowaste to Bioenergy through Gasification
Principal Investigator
SUNY Cobleskill
Cobleskill, New York 12043
24