Clean Water Act & Logging Roads
• The Clean Water Act (CWA) requires a National Pollution
Discharge Elimination (NPDES) permit for “point source”
discharges of pollutants to navigable waters.
• Non-point source pollution is not subject to the same permitting
requirements and generally is addressed through other CWA
programs (e.g. TMDLs).
• There are statutory exemptions from the NPDES permit
requirement, including for some agricultural operations, but not for
forest management activities.
• However, by regulation EPA has long exempted silvicultural
activities from the NPDES permit requirement of the CWA.
Stoel Rives Forest Industries Practice
3
NEDC v. Brown
• NEDC sued :
– Marvin Brown (the Oregon State Forester);
– all the members of the Oregon Board of Forestry; and
– Hampton Affiliates, Stimson Lumber, Georgia-Pacific and
Swanson Group—companies with state logging contracts that
hauled logs on the roads in question.
• NEDC alleged:
– NPDES permit required for stormwater runoff from forest roads.
• Additional parties:
– OFIC and AF&PA intervened.
Stoel Rives Forest Industries Practice
4
Alleged Facts
• NEDC presented photographs allegedly showing turbid runoff
from ditches and culverts from the Trask River Road and Sam
Downs Road in the Tillamook State Forest of Oregon.
• NEDC alleged the state owned the roads (although one is
owned by the county).
• NEDC alleged that the 4 companies haul logs on the road,
thereby “grinding up the road surface and creat[ing] much of
the sediment and other pollutants delivered to rivers and
streams.”
Stoel Rives Forest Industries Practice
5
Stoel Rives Forest Industries Practice
6
Plaintiff’s Legal Arguments
• Discharges from ditches and culverts associated
with the roads are point source discharges.
• The silviculture exemption in EPA’s rules is
invalid.
• Hauling logs is an “industrial activity” within the
meaning of § 402(p) of the CWA and, therefore,
is subject to stormwater permitting requirements.
Stoel Rives Forest Industries Practice
7
Silvicultural Rule
“Silvicultural point source means any discernible, confined and discrete
conveyance related to rock crushing, gravel washing, log sorting, or log
storage facilities which are operated in connection with silvicultural
activities and from which pollutants are discharged into waters of the
United States. The term does not include non-point source silvicultural
activities such as nursery operations, site preparation, reforestation and
subsequent cultural treatment, thinning, prescribed burning, pest and
fire control, harvesting operations, surface drainage, or road
construction and maintenance from which there is natural runoff.
However, some of these activities (such as stream crossing for roads)
may involve point source discharges of dredged or fill material which
may require a CWA section 404 permit.” 40 CFR 1222.27(b).
Stoel Rives Forest Industries Practice
8
Silvicultural Rule
• Defendants argue Silvicultural Rule clearly applies.
• Plaintiffs argue that exemption only applies to “non-point
sources” and that EPA cannot undermine the CWA by
exempting point sources (citing EPIC v. PALCO, No. C012821-MHP (ND Cal. Oct. 14, 2003)).
• Defendants argue that EPA has broad authority to interpret the
term “point source” in the Silvicultural Rule.
• Both sides cite the 9th Circuit’s Forsgren decision for support
(League of Wilderness Defenders v. Forsgren, 309 F3d 1181
(9th Cir. 2002)).
Stoel Rives Forest Industries Practice
9
Clean Water Act Section 402(p)
• Two-phase regulatory program for stormwater.
• Phase I required permits for stormwater from:
– Industrial activity;
– Municipal separate storm sewer serving population
>100,000.
• Phase II required EPA to study and identify additional sources
as necessary to mitigate impacts on water quality. EPA
identified and required permits from:
– Smaller municipal separate storm sewers;
– Construction sites >5 acres.
Stoel Rives Forest Industries Practice
10
EDC v. EPA, 344 F3d 832 (9th Cir. 2003)
• EDC challenged EPA’s phase II rules, including an
argument that EPA improperly failed to include forest
roads.
• On procedural grounds, the court remanded the rule to
EPA to reconsider, including reconsideration of whether
forest roads should require phase II stormwater permits.
• In this case, the court and EPA clearly recognized that
forest roads are not subject to phase I permitting
requirements as an industrial activity.
Stoel Rives Forest Industries Practice
11
District Court’s Decision
• Granted motion to dismiss in favor of defendants.
• Decision based entirely on interpretation of Silvicultural Rule.
– Relied heavily on Forsgren.
– Concluded that Forsgren rejected application of
Silvicultural Rule because aerial spraying of pesticides is
not natural runoff.
– Forsgren did not invalidate the Silvicultural Rule or
narrowly apply it to nonpoint sources (which don’t need an
exemption).
• Court did not reach the section 402(p) arguments.
Stoel Rives Forest Industries Practice
12
Ninth Circuit Panel
• Fletcher, Breyer and Fisher
– Fletcher, author of NEA v. EPA overturning EPA
exclusion of ballast water discharges from NPDES
permitting
– Breyer, district court judge, Northern District of
California, home of Judge Patel, who authored
EPIC v. Pacific Lumber Co.
Stoel Rives Forest Industries Practice
13
Ninth Circuit’s Opinion
NEDC v. Brown, 2010 WL 3222105 (9th Cir. Aug. 17, 2010)
• Reversed District Court
• Held:
– Silvicultural Rule cannot exclude logging road
discharges from NPDES permitting.
– Logging road discharges are industrial stormwater
discharges subject to EPA Phase I NPDES
permitting.
Stoel Rives Forest Industries Practice
14
Silvicultural Rule
• Logging road stormwater discharges fall squarely
within the statutory definition of a point source.
– Congress did not empower EPA to redefine what constitutes
a point source.
– Congress clearly wanted to regulate all point-source
discharges.
• Result: The Silvicultural Rule does not exempt
stormwater runoff from logging roads from NPDES
permitting, and has no continuing effect in 9th Circuit.
Stoel Rives Forest Industries Practice
15
Industrial Discharge
• The Panel acknowledged:
– EPA’s regulatory definition of discharges
associated with industrial activity “purports to
exclude forest road discharges”
– EPA plainly intended to exclude such discharges
• But . . .
Stoel Rives Forest Industries Practice
16
Industrial Discharge
• The Panel found EPA could not exclude such
discharges because:
– EPA conceded that logging is “industrial” when it
found that “industrial facilities” include “Lumber
and Wood Products” facilities under SIC 24.
– The discharges otherwise fit in the regulatory
definition of industrial discharges.
Stoel Rives Forest Industries Practice
17
Industrial Discharge
• In reaching this conclusion, the Panel:
– Ignored EPA’s plain explanation that its inclusion
of SIC 24 was not intended to encompass logging
activities covered by the Silvicultural Rule.
– Ignored the fact that forest road discharges do not
fit the definition of industrial discharges.
– Ignored the court’s own ruling in EDC v. EPA.
Stoel Rives Forest Industries Practice
18
Implications
• Threshold issues:
– What roads require permits?
• What construction features actually constitute point sources?
• What attributes define a logging road and distinguish from a road
not associated with industrial activities?
– Who needs the permit?
• The road owner?
• Holders of timber contracts with road maintenance requirements?
• Anyone who uses the road?
– General permit or source-specific permit?
Stoel Rives Forest Industries Practice
19
Implications
• Sweeping/uncertain permitting requirements
– Enormous number of roads and culverts potentially
subject to permitting
– No established permitting system
– No clear permitting criteria, but . . .
• May have to meet effluent limitations (water quality
standards)
• May require monitoring
Stoel Rives Forest Industries Practice
20
Implications
• Legal uncertainty and lawsuits
– Impact on federal and state timber sales
• Delay and/or lawsuits to enjoin timber sales
• Possible revisions to timber sale agreements
– Impact on private timber harvesting
• Lawsuits to enjoin harvesting and/or hauling
• Effects not only on private roads, but on county roads
that could be considered “logging roads”
Stoel Rives Forest Industries Practice
21
Response
• First step
– Petition for rehearing en banc
• Stay of the mandate pending ruling.
• Rehearing statistically unlikely.
• Second step
– Petition for certiorari to the U.S. Supreme Court
• Seek a further stay of the Ninth Circuit ruling.
• Chances to prevail are best here.
Stoel Rives Forest Industries Practice
22
Current Status
• Petition for en banc review filed
– Focus on the weaker aspect of the Panel’s ruling
that forest road stormwater is an industrial
discharge.
– Focus on the sweeping implications and
importance of the ruling.
– Court has asked for responsive briefing from
plaintiffs (good sign).
Stoel Rives Forest Industries Practice
23
What Else Are We Doing?
• Coordination with others
– State has filed a petition for en banc review as
well, focusing on similar arguments.
– EPA was unwilling to file an amicus brief but
made clear that its position has not changed.
– And . . .
Stoel Rives Forest Industries Practice
24
Amicus Briefs
• Coordination with others
– Amicus briefs filed
•
•
•
•
Pacific Legal Foundation on behalf of industry groups
County organizations
Mountain States Legal Foundation
American Forest Resource Council
– Focus of these briefs is on showing the scope and
importance of the court’s ruling
Stoel Rives Forest Industries Practice
25
What’s Next?
• Court will act
– Either deny or grant petition for rehearing.
– If granted, group of 11 judges will rehear the case.
– If denied, petition for cert. in 90 days.
• Legislative solution
– Statutory exemption for forest operations?
Stoel Rives Forest Industries Practice
26
Thank You!