Transcript Slide 1

Mahanadi Coalfields Limited
Workshop on Technology
Development for reaching
250 MT (19-20)
Trend and Coal production projection
300.00
250.00
in MT
200.00
150.00
100.00
50.00
0.00
13-14
14-15
15-16
16-17
17-18
18-19
19-20
in MT 110.44 127.00 150.00 167.00 187.00 222.00 250.00
Estimated demand & Gap
Demand of coal IN MT (at 100% satisfaction level) as per FSA/LOA
Year
15-16
16-17
17-18
18-19
19-20
Demand
199.00
242.00
242.00
242.00
242.00
Prod
150.00
167.00
187.00
222.00
250.00
Gap
49.00
75.00
55.00
20.00
-8.00
Projected Coal production upto 2019-20
300.00
in MT
200.00
100.00
0.00
14-15
15-16
16-17
17-18
18-19
19-20
On-Going
79.95
101.45
115.75
132.25
160.75
172.00
Completed+ existing
47.05
48.55
51.25
54.75
57.25
41.00
Future
0.00
0.00
0.00
0.00
4.00
37.00
TOTAL
127.00
150.00
167.00
187.00
222.00
250.00
Coal production projection Year wise upto 2019-20
Year
14-15
15-16
16-17
17-18
18-19
19-20
UG
1.50
1.50
1.50
1.50
1.50
1.50
OC
125.50
148.50
165.50
185.50
220.50
248.50
TOTAL
127.00
150.00
167.00
187.00
222.00
250.00
Coal & OB Projection
400.00
Coal-MT, OB-MCuM
350.00
300.00
250.00
200.00
150.00
100.00
50.00
0.00
14-15
15-16
16-17
17-18
18-19
19-20
Coal
127.00
150.00
167.00
187.00
222.00
250.00
OB
94.00
177.00
202.00
231.00
275.00
351.00
Additional Shovel required to achieve 250 Mty by 2019-20
Capacity
15-16
16-17
17-18
18-19
19-20
Total
34 Cum
2
1
20-22 Cum
1
4
2
4
11
03
9-10 Cum
7
27
35
5
4
78
5-6.5 Cum
3
6
8
-
-
17
2.5-4.3 Cum
-
4
2
-
-
6
Grand Total
115
Replacement
of Shovel
Total
Existi
ng
1415
1516
10 Cum
12
4.5 -6.5 Cum
40
2
2
2.5 to 4.3
Cum
37
2
4
1617
1718
18-19
1920
4
5
2
1
14
Additional Dumper required to achieve 250 Mty by 2019-20
Capacity
15-16
16-17
17-18
18-19
19-20
Total
35 T
7
8
31
-
-
46
50/60 T
48
108
139
-
-
295
85-100 T
63
229
328
55
53
728
190 T
-
6
36
20
52
114
240 T
-
20
20
-
-
40
Total
1223
Total
Replacement of
Dumper
50/60 T
Exist
ing
1415
1516
16-17
284
34
31
66
17-18
1819
19-20
17
10
-
158
Additional Dozer required to achieve 250 Mty by 19-20
Capacity
15-16
16-17
17-18
18-19
19-20
Total
770-850 HP
(with Ripper
attachment)
4
17
9
5
3
38
410 HP
15
25
41
9
9
99
Replacement
of Dozer
Total
Existi
ng
14-15
15-16
16-17
17-18
18-19
19-20
410 HP
75
9
20
1
16
2
-
48
320 HP
31
-
-
1
5
1
-
7
Additional Drill required to achieve 250 Mty by 2019-20
15-16
16-17
17-18
18-19
19-20
Total
250 mm
8
31
46
9
8
102
150-160
mm
12
26
30
4
5
77
Replacement of
Drill
Existing
250 mm
34
160 mm
55
14-15
7
15-16
16-17
17-18
1
4
1
6
1
3
18-19
19-20
Total
6
2
19
Additional Surface Miner required to achieve 250 Mty by 2019-20
30003800
mm
15-16
16-17
17-18
18-19
19-20
Total
3
8
14
3
4
32
Additional Loading machine (Pay loader) required to achieve 250 Mty by
2019-20
15-16
16-17
17-18
18-19
19-20
Total
>5 cum
5
11
13
-
-
29
>10 cum
-
1
4
3
4
12
Replacement
Loading
M/C
(Pay loader)
>5cum
Existi
ng
10
14-15
15-16
16-17
17-18
4
1
18-19
19-20
Total
5
Additional equipment required for UG upto 2019-20
Capacity
Nos
Continuous
Miner
1.4 to 4.6 M
2
SDL
1 cum
9
Low Height
SDL
0.8 cum
6
Low Height
SDL
1 cum
LHD
1.2 cum
2
LHD
2.7 cum
4
Roof Bolter
Quad bolter
2
Shuttle Car
15 Te
6
Conveyor
Belt Conveyor
11800 m
Roof Bolter
Existing
Replacement
18
18
29
20
3
15
Other P&M ( other than HEMM)
requirement to achieve 250 MT
Tube/pipe conveyor
Requirement/Capacity
Hingula
5 Km
Bhubaneswari
3.5 km
Other P&M ( other than HEMM)
requirement to achieve 250 MT
Washery
Jagannath washery
10 Mty
Hingula washery
10 Mty
Kulda washery
10 Mty
Basundhara washery
10 Mty
Siarmal washery
10 Mty X 4
Lakhanpur integrated
20 Mty & 10 Mty
Rapid Loading System including SILO
requirement to achieve 250 MT
Kaniha/Gopalji SILO
30 Mty
Lingaraj SILO
16 Mty
Bhubaneswari SILO
20 Mty
Ananta SILO
15 Mty
Bharatpur SILO
15 Mty
Hingula SILO
15 Mty
Gopalprasad SILO
15 Mty
Talabira-II &III SILO
20 Mty
Lakhanpur SILO
30 Mty
Kulda SILO
10 Mty
Siarmal SILO
40Mty
Technological Development &
Mechanization of Mines Proposed
Present technology
SDL/LHD with Bord & Pillar in UG
Man-riding system in UG
Dragline & Shovel-Dumper combination for OB removal ,
Loader-Tipper for coal production in OC
Surface miner for blast free coal production in OC
OITDS, GPS for better monitoring
Future technology
Continuous miner in UG
Higher capacity Shovels & Dumpers
Pipe conveyor for coal transportation
Ripper dozer for blast free OB removal in OC
RLS with SILO for faster loading of wagons
Production level
in 19-20
1.5 MT
248.5 MT
Award of Contracts
Sl Projects
1 Kaniha OCP
2 Siarmal OCP
Key Contracts for EPC, OB removal, Timeline
coal removal etc.
Award of contract for MDO
Sep-17
Dec-16
Award of contract for MDO
Issues with BEML
(A) Delay in supply of spare parts. Spare parts of a module is not
supplied in full rather it is supplied in piecemeal due to which
repair of particular assembly and equipment is delayed.
(B)
BE-1600 Hydraulic Excavator 9.5 cum. 06 nos. supplied to MCL
are going under frequent breakdown, due to Failure of engines,
Hydraulic pumps & Hydraulic tubes, Cooling system and other
components since its commissioning.
The performance of BEML :
Year
200809
200910
201011
201112
201213
201314
201415
% Availability
Model
Present
populat
ion
BE 1600 D
6
-
79
66
55
39
45
50
BE 1000 D
12
-
84
71
68
54
52
53
BE 1000 E
5
69
64
72
69
57
66
69
The performance of BEML :
Year
200809
200910
201011
201112
201213
201314
201415
% Breakdown
Model
Present
populat
ion
BE 1600 D
6
-
14
29
41
58
51
46
BE 1000 D
12
-
10
23
27
42
44
43
BE 1000 E
5
27
32
24
27
40
30
27
(C)
The performance of BH-100 Ton Dumpers after warranty period
is very poor due to failure of Engines, Transmission and other
components. Performance is as below :
Year
2008- 2009- 2010- 2011- 2012- 2013- 201409
10
11
12
13
14
15
% Availability
Present population 29
Model
BH-100
(100T)
-
63
76
61
55
34
38
(C)
The performance of BH-100 Ton Dumpers after warranty period
is very poor due to failure of Engines, Transmission and other
components. Performance is as below :
Year
Model
BH-100
(100T)
2008- 2009- 2010- 2011- 2012- 2013- 201409
10
11
12
13
14
15
% Breakdown
Present population
29
-
30
19
35
42
63
59
(D)
Recently, supplied BH-60 Ton Dumpers are giving problems like
Cabin Vibration, Regular failure of suspension, Air Conditioning
compressor mounting bolt loosening problem, Sensors are not
working, Camera monitoring foundation bracket failure & Transmission
pump failure etc.
(E)
Recently supplied BD-355 Dozers are also not performing to the
mark and giving troubles like :





Automatic release of blades sometimes
Misalignment of cabin
Non functioning of Air Conditioner
Fuel Injection Pumping problem
Starting problem etc.
ISSUES WITH M/S.H.E.C., RANCHI
There is general delay in supply of equipment as well as spare parts.
As HEC is facing financial constraints, they are demanding advance
payment for supply of equipment for recently ordered 10 cum. Electric Rope
Shovel
ISSUES WITH M/S. PROMTRACTOR (JSC), RUSSIA
Performance of 15 nos. 410 HP Dozers are very very poor due to abnormal failure
of engine & transmission even in warranty period. The performance is as below :
Year
2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15
Company
M/s. Promtractor (JSC), Russia
% Availability
Model
Present
Populati
on
Promtractor T25.01CB-1
15
-
-
71
53
31
24
11
67
74
88
% Breakdown
Model
Promtractor T25.01CB-1
-
-
23
43
M/s. Promtractor (JSC), Russia has no Indian service provider for supply of spare
parts and maintenance and also not supporting well for supply of spare parts and
services.
Thank you
SUGGESTIONS FOR SUPPLY AND MAINTENANCE OF EQUIPMENT
 All HEMM should be supplied with Guaranteed Spare Parts Supply
(GPS) or Maintenance and Repair Contract (MARC) for life time.
SUGGESTIONS FOR SUPPLY AND MAINTENANCE OF
EQUIPMENT
 Guarantee for initial 2-3 years is meaningless as machine will perform
initially better than when it gets older after 03 years. Hence, guarantee
for later period is more important.
 Cost of equipment quoted is very less but spare parts are very costly
which ultimately result into higher cost of production. If life cycle cost is
adopted this can be eliminated.
 Buy back system is to be incorporated in case of spare parts which are
not consumed during warranty period. Some manufacturers are reluctant
for life time guarantee due to uncertainty in foreign currency fluctuation.
This problem can be sorted out by incorporating currency escalation/deescalation clause.
Modification in Proveness criteria
 4-5 years satisfactory performance may be introduced instead
of one year as per existing standard NIT.
 At least 30-40% of the tendered quantity may be considered for
meeting the prove ness criteria instead of at least one number as
per existing standard NIT.
 Tender finalization should be 60/40 basis as per earlier system
to have a check on L-1 bidder both in price as well as
performance.
 The equipment which are not having base in India should not
be given chance for participation in open tender as there is also
problem of spare and service support because of non availability
of India Agent. There should be a provision of consignment store
having major population nearer to the project.