Project Cost Management Time is Money
Download
Report
Transcript Project Cost Management Time is Money
Project Cost Management
PMBOK 4th Edition
Agenda
Broad
Understanding of Project Cost
Management.
Understand how software estimation is
different.
PROCESS GROUPS
I
Planning
Estimate Costs
Budget Costs
E
Controlling
C
Control Costs
Estimate Costs
Cost estimating and Pricing:
Cost estimating: how much will it cost the performing
organization to provide the product or service
involved?
Pricing: how much will the performing organization
charge for the product or service? Business decision.
Estimating should be done by the person doing
the work.
Estimate Costs
Inputs
1. WBS
2. Resource
requirements
3. Resource rates.
4. Act. duration est.
5. Historical info.
6. Chart of accounts
7. Risks
Tools
1. Analogous est.
2. Parametric
modeling
3. Bottom-up est.
Outputs
1. Cost estimates
2. Cost
management plan
Based on the WBS to increase the accuracy.
Project managers should analyze the needs of
the project, to compare and reconcile any
differences with cost requirements from
management.
Estimate Costs
Cost estimates for all resources that will be
charged to the project.
Supporting detail must include:
Generally expressed in units of currency to facilitate
comparisons both within and across projects.
Generally includes appropriate risk response planning.
Reference to WBS.
How it was developed?
Assumptions made.
Range of possible results.
Cost management plan how cost variances will
be managed.
Estimate Costs
View
the Templates
Top Down
Experience Based/Analogy
Parametric
WBS
Roll up the numbers
Estimates vs. Accuracy
Estimate
Accuracy
Order of
Magnitude
(Early)
-25%
+75%
Budget
Estimate
-10%
+25
Definitive
Estimate
-5%
10%
Most difficult to estimate as very
little project info is available
Used to finalize the Request for
Authorization (RFA), and establish
commitment
Development stage estimate.
Needed to predict revised project
completion date
Tools for Estimating
Top Down
Estimating
Bottom Up
Estimating
Parametric
Modeling
Accuracy
depends on experience
Fast, but estimates are rough
Slow,
but reliable
High cost (time) / WBS needed
Buy-in from the team
Mathematical models to predict costs
Two types: REGRESSION ANALYSIS,
and LEARNING CURVE
Expert judgment
Delphi
Method
Tasks need not to be identified
(analogous) Considerable experience needed
Influencing Factors
Two
sets of factors influence the ultimate
cost of a system
Size Factors
Number, and type of functions
Project
Factors
Project parameters that influence
project costs.
Control Costs
Inputs
1. Cost Baseline
2. Performance
Reports
3. Change Requests
4. Cost
Management
Plan
Tools
1. Cost Change
Control System
2. Performance
Measurement
3. Earned Value
Management
4. Additional
Planning
5. Computerized
Tools
Outputs
1. Revised Cost
Estimates
2. Budget Updates
3. Corrective Action
4. Estimate at
Completion
5. Project Closeout
6. Lessons learned
Understand what is driving variances, good and
bad, and decide what action to take.
Case Study
Simple
Case study requires you to master
the following:
EV = Earned Value
PV = Planned Value
AC = Actual Cost
Budget Costs
The cost baseline will be used to measure and
monitor cost performance of the project.
Expected
Cash Flow
Cumulative
Values
Cost
Baseline
Time
Control Costs
To
Control / Report Costs
And to Revise Costs and provide a new
Estimate At Completion
Use Earned Value Method
Example
Painting
your four walls.
Each wall $1000.
Total Budget At Completion (BAC) =
$1000+$1000+$1000+$1000
Half way through you audit the work.
Let us consider two scenarios.
Scenario 1
One
Wall is painted
Amount Spent is $500
Scenario 2
Two
Walls painted
Amount Spent is $4000
What is the Revised EAC
For
Scenario 2.
TCPI
What
if CPI is consistently low.
Can you catch up somehow?
How will you know if it is not possible?
Read 18.6.1 about TCPI.
Case Study:
Project “Book Contract”
The
“Book Contract” Project:
10 work packages
• 10 chapters
Negotiated to be delivered 1
per month
Estimated cost of $100 each
Time to Complete Performance
Index
(BAC)
This is equal to:
Why pick TCPI?
The
TCPI focuses on the remaining
project activities.
It reflects what it will take in future
performance to recover from a
negative actual cost position.
Note: It is effectively the mirror
opposite of the cumulative CPI.
We’ve all been there.
You’re
a few months into a project
and the first few deliverables have
been completed.
You diligently calculate the CPI = 0.9.
Your customer asks you about your
plans for the cost overrun
“No problem, we’ll make it up”
BUT CAN YOU?
Back to the Case Study..
Month
1
2
3
Planned Value
$100
$100
$100
Earned Value
$100
$100
$100
Actual Cost
$110
$110
$110
Cumulative Earned Value (EV)
$100
$200
$300
Cumulative Actual Cost (AC)
$110
$220
$330
CPI = EV/AC
0.89
0.89
0.89
TCPI calculation: Work
Remaining
The work remaining is
BAC – EV = $1,000 - $300 = $700
This
is an estimate of the earned
value remaining:
The total earned value for the project is
$1,000
We have completed 3 deliverables.
Work remaining = $700.
TCPI Calculation: Funds
Remaining
funds remaining are BAC – AC =
$1,000 – $330 = $670.
This is the remaining budget if we are
to deliver as promised.
The
Project Moves on
1.04
doesn’t look too bad!
We have to achieve a CPI rate of
1.04 times of what we were
working on.
Yes, We Can!
Yes, We Can!
Yes, We Can!
So Three More Months &
Three more Chapters
Month
Planned Value
1
2
3
4
5
6
$100 $100 $100 $100 $100 $100
Earned Value
$100 $100 $100 $100 $100 $100
Actual Cost
$110 $110 $110 $110 $110 $110
Cumulative Earned
Value (EV)
Cumulative Actual
Cost (AC)
CPI = EV/AC
$100 $200 $300 $400 $500 $600
$110 $220 $330 $440 $550 $660
0.89
0.89
0.89
0.89
0.89
0.89
Three More Chapters …
Uphill…
To
complete the project within
budget, we now have to work at a rate
18% greater than we proposed.
In fact, we need a 29% improvement
in our expenditure rate from 89% to
118%!
TCPI Goes to ∞ in month 8!
Estimates of Cost to
Complete
The estimate of the final cost
at completion is called the
estimate at completion (EAC).
Next: The PM should
calculate the new EAC.
Analysis
The
TCPI has the remarkable
property that if we own up to the cost
overrun and use the TCPI with the
EAC in the denominator, then we
can proceed at our current efficiency
(defined by our current CPI) and hit
the new cost target.
Conclusion
When
BAC is no longer attainable,
the project manager should calculate
a new EAC.
This new estimate becomes the goal
we will work towards if approved by
stakeholders.
TCPI = (BAC –EV) / (EAC –AC)
Conclusion
TCPI
gives us a reality check
analysis.
PM: Our CPI is 0.9. We will
deliver on budget, don’t worry.
Auditor: I have TCPI = 1.2,
implies 30% increase in
productivity.
Auditor: Are you Sure?
References
Provides
a good overview and general
guide to the principles of EVM.
Shows the EVM role in facilitating effective
project management , Project
Management Institute, 2005
The Two Most Useful Earned Value
Metrics: the CPI and the TCPI By Quentin
W. Fleming and Joel M. Koppelman
Also Warburton and Kanabar – Several
PMI papers and Book