Transcript RUC 2
Determining the Health of a Project through Earned Value Management Determining the Health of a Project through Earned Value Management What and Why When How Outcomes Limitations EVM and RM Integration Clearing and grubbing for a new water treatment plant in Kassan, Alaska What and Why EVM is a project management technique that: – Objectively quantifies project progress and performance in terms of dollars – Measures actual performance against an assumed spending baseline – Provides indicators of future performance based on past performance When Scope Schedule Budget Earning Rules Accrued Costs Picture Here Installing a well line in Pitka’s Point, Alaska Toksook Bay, Alaska 590 residents New WTP/WST – $8.86M – Const. Comp = 8/31/13 How Scope – Work Breakdown Structure Scope Item Construction Activities OOK 07-002 - Water Treatment Plant Construction start Date Initial Material Flown/unload and transport Safety & Safety Stand Down L - Housing Set-up Site work Clear & grub/haul off, 1300CY L - Haul In NSF Place NSF/Compact/grade Grade and set connex Barge Arrival/unload/transfer to site Piling Contract Piling Contractor for WTP Piling Contractor for WST Set up for Pipe Work Raw Water from 3A and 3B L - C-143 Station 49+50 to 40+00 L - C-142 Station 49+00 to 29+00 How Scope – WBS Schedule – Critical Path Scope Item Construction Activities OOK 07-002 - Water Treatment Plant Construction start Date Initial Material Flown/unload and transport Safety & Safety Stand Down L - Housing Set-up Site work Clear & grub/haul off, 1300CY L - Haul In NSF Place NSF/Compact/grade Grade and set connexes (3) Barge Arrival/unload/transfer to site Piling Contract Piling Contractor for WTP Piling Contractor for WST Set up for Pipe Work Raw Water from 3A and 3B L - C-143 Station 49+50 to 40+00 L - C-142 Station 49+00 to 29+00 Est Start 03/12/12 Est Copm 08/31/13 03/12/12 05/02/12 08/31/13 05/02/12 05/02/12 05/03/12 05/04/12 03/12/12 05/24/12 05/31/12 05/31/12 06/14/12 05/03/12 05/04/12 05/25/12 08/27/12 05/31/12 06/14/12 06/14/12 06/16/12 06/16/12 03/12/12 03/12/12 04/07/12 06/23/12 06/26/12 06/26/12 06/30/12 06/23/12 04/21/12 04/07/12 04/21/12 06/25/12 07/21/12 06/30/12 07/10/12 How Scope – WBS Schedule – Critical Path Budget – Itemized by WBS Scope Item Construction Activities OOK 07-002 - Water Treatment Plant Construction start Date Initial Material Flown/unload and transport Safety & Safety Stand Down L - Housing Set-up Site work Clear & grub/haul off, 1300CY L - Haul In NSF Place NSF/Compact/grade Grade and set connexes (3) Barge Arrival/unload/transfer to site Piling Contract Piling Contractor for WTP Piling Contractor for WST Set up for Pipe Work Raw Water from 3A and 3B L - C-143 Station 49+50 to 40+00 L - C-142 Station 49+00 to 29+00 Est Start 03/12/12 Est Copm 08/31/13 Cost $2,664,292.90 03/12/12 05/02/12 08/31/13 05/02/12 $2,664,292.90 $0.00 05/02/12 05/03/12 05/04/12 03/12/12 05/24/12 05/31/12 05/31/12 06/14/12 05/03/12 05/04/12 05/25/12 08/27/12 05/31/12 06/14/12 06/14/12 06/16/12 $15,000.00 $3,000.00 $25,548.00 $824,916.90 $11,889.50 $20,382.00 $11,936.40 $2,984.10 06/16/12 03/12/12 03/12/12 04/07/12 06/23/12 06/26/12 06/26/12 06/30/12 06/23/12 04/21/12 04/07/12 04/21/12 06/25/12 07/21/12 06/30/12 07/10/12 $9,122.80 $581,900.00 $393,638.00 $188,262.00 $4,561.40 $50,175.40 $11,403.50 $18,245.60 How Scope – WBS Schedule – Critical Path Budget – Itemized by WBS Earning Rules – Predefined Metrics Scope Item Construction Activities OOK 07-002 - Water Treatment Plant Construction start Date Initial Material Flown/unload and transport Safety & Safety Stand Down L - Housing Set-up Site work Clear & grub/haul off, 1300CY L - Haul In NSF Place NSF/Compact/grade Grade and set connexes (3) Barge Arrival/unload/transfer to site Piling Contract Piling Contractor for WTP Piling Contractor for WST Set up for Pipe Work Raw Water from 3A and 3B L - C-143 Station 49+50 to 40+00 L - C-142 Station 49+00 to 29+00 QTY Unit 1 1 1 LS LS LS 1300 6000 15 CY CY DAY Est Start 03/12/12 Est Copm 08/31/13 Cost $2,664,292.90 % Dollars 03/12/12 05/02/12 08/31/13 05/02/12 $2,664,292.90 $0.00 05/02/12 05/03/12 05/04/12 03/12/12 05/24/12 05/31/12 05/31/12 06/14/12 05/03/12 05/04/12 05/25/12 08/27/12 05/31/12 06/14/12 06/14/12 06/16/12 $15,000.00 $3,000.00 $25,548.00 $824,916.90 $11,889.50 $20,382.00 $11,936.40 $2,984.10 75% 0% 10% $11,250.00 $0.00 $2,554.80 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 06/16/12 03/12/12 03/12/12 04/07/12 06/23/12 06/26/12 06/26/12 06/30/12 06/23/12 04/21/12 04/07/12 04/21/12 06/25/12 07/21/12 06/30/12 07/10/12 $9,122.80 0% $581,900.00 $393,638.00 100% $188,262.00 100% $4,561.40 0% $50,175.40 $11,403.50 0% $18,245.60 0% $0.00 $393,638.00 $188,262.00 $0.00 $0.00 $0.00 How Scope – WBS Schedule – Critical Path Budget – Itemized by WBS Earning Rules – Predefined Metrics Accrued Costs – Actual Cost to Date ss Estimated Cost Version 8, 5/11 Cost Tracking Updated as of: PPE 4/21/2012 5/5/2012 5/19/2012 6/2/2012 6/16/2012 6/30/2012 6/2/2012 Materials $2,501,487.50 Plan-Set Task Totals Equipment $1,167,040.00 Construction Budget $8,862,720 Costs to Date Remaining Balance To Date $1,372,700 Plan set title and plan set # OOK-07-002 Freight Community Name Notice To Proceed Date Toksook Bay Labor Travel Subcontract Material 100,886.00 66,463.79 127,431.70 58,137.57 Freight 40,907.93 0.00 676.58 67,210.06 3/15/2012 Local Labor 0.00 2,086.43 4,840.89 10,463.97 Cost To Date ANTHC Labor Equipment 81,789.63 0.00 53,093.87 42,831.01 58,421.55 1,009.21 50,568.70 17,523.88 $265,000.00 $3,196,771.50 $118,590.00 $1,613,831.00 Travel 0.00 3,000.00 560.00 560.00 Subcontract 583,532.46 141.11 348.26 215.19 Total Costs This Period 807,116.02 167,616.21 193,288.19 204,679.37 0.00 0.00 $7,490,020 Total Cumulative Percent of Costs Budget Spent 807,116.02 9.11% $974,732.23 11.00% $1,168,020.42 13.18% $1,372,699.79 15.49% $1,372,699.79 15.49% $1,372,699.79 15.49% Biweekly Report ss Estimated Cost Version 8, 5/11 Cost Updated as of: Plan set title and plan set Community Name Notice To Proceed Date 6/2/2012 OOK-07-002 Toksook Bay 3/15/2012 Materials Equipment Freight Labor Travel PPE 4/21/2012 5/5/2012 5/19/2012 6/2/2012 6/16/2012 6/30/2012 Cost to Date Material 100,886.00 66,463.79 127,431.70 58,137.57 352,919.06 Freight 40,907.93 0.00 676.58 67,210.06 108,794.57 CONSTRUCTION 17,391.29 Quantity ANTHC Labor 81,789.63 53,093.87 58,421.55 50,568.70 243,873.75 Unit Plan-Set $2,501,487.50 $1,167,040.00 $265,000.00 $3,196,771.50 $118,590.00 $1,613,831.00 Actual Cost Subcontract Local Labor 0.00 2,086.43 4,840.89 10,463.97 Cost To Date Equipment 0.00 42,831.01 1,009.21 17,523.88 61,364.10 Est. Start Travel 0.00 3,000.00 560.00 560.00 Subcontract 583,532.46 141.11 348.26 215.19 4,120.00 Est. Comp OOK 07-002 - Water Treatment Plant Toksook Bay / 07-002 / WTP WST NTP or project start date Pre-Construction Shipping Electrical Panels (subcontract) Pre-Construction Meeting Pre-Construction Completed General Conditions Insurance & CPA set-up Per Diem Construction Activities 03/02/12 03/02/12 03/02/12 04/27/12 04/27/12 04/27/12 04/27/12 04/27/12 05/02/12 05/02/12 05/02/12 03/12/12 08/31/13 03/02/12 03/02/12 08/20/12 08/20/12 06/13/12 04/27/12 04/27/12 08/30/13 08/30/13 08/30/13 08/31/13 OOK 07-002 - Water Treatment Plant Construction start Date 03/12/12 05/02/12 08/31/13 05/02/12 Initial Material Flown/unload and transport Safety & Safety Stand Down 05/02/12 05/03/12 05/03/12 05/04/12 Constructi Costs to Date Remaining Balance Total Costs This Period 807,116.02 167,616.21 193,288.19 204,679.37 0.00 0.00 584,237.02 Cost to Date Running Total Bi-Weekly Total 15.00% Planned Value 45.00% 100.00% 10.00% 4.00% 70.00% 9.00% $8,862,720 $1,372,700 $7,490,020 Total Cumulative Costs 807,116.02 $974,732.23 $1,168,020.42 $1,372,699.79 $1,372,699.79 $1,372,699.79 $1,372,699.79 Est. Task Cost $8,862,423.30 $0.00 $0.00 $404,000.00 $250,000.00 $150,000.00 $4,000.00 $0.00 $2,233,588.40 $71,291.00 $33,840.00 $2,664,292.90 Earned Value Percent of Budget Spent 9.11% 11.00% 13.18% 15.49% 15.49% 15.49% 15.49% Construction Budget W-WP W-WT W-BD Earned Valve % Earned Valve Dollars 45% $112,500.00 0% $0.00 100% $4,000.00 0% $0.00 70% $49,903.70 9% $3,045.60 95% $14,250.00 0% $0.00 $2,664,292.90 $0.00 5.00% % 95.00% $15,000.00 $3,000.00 EVM Outcomes Three-Line Diagram – Planned Value – Earned Value – Actual Cost Variances – CV and SV Performance Indices – CPI and SPI Estimate at Completion Mixing & placing concrete for a water storage tank in Pitka’s Point, Alaska EVM Outcomes Drilling helical piles for a boardwalk in Kwigillingok, Alaska Installing water distribution main and flush hydrants in Pitka’s Point, Alaska EVM Outcomes Excavating for a new lagoon in Kasigluk, Alaska Thermopile foundation for a clinic in Kaltag, Alaska EVM – Three Line Diagram Cost and Schedule Variances CPI = 0.91 EAC = $9,724,000 PlanTrax® Version 3.3b EVM Limitations Subjective measurement No consideration of quality Requires accurate accounting Looks forward based on past events The Tinker family’s new bathroom Kasigluk, Alaska Insulated flush hydrants in Galena, Alaska EVM and RM Integration Identify potential problems quantify their impact Monitor and manage more effectively Recoup value of mitigated risks Crushing rock for pipe bedding in Pitka’s Point, Alaska The new water treatment plant in Pitka’s Point, Alaska Determining the Health of a Project through Earned Value Management What and Why When How Outcomes Limitations EVM and RM Integration A boy with a newly installed arctic box and low pressure sewer in the background in Kasigluk, Alaska Questions?