Asia Pacific Partnership
United States of America
Power Generation Task Force
August 13 – 17, 2007
Yards Creek Overview
J. Geuther, Manager Yards Creek
Yards Creek Overview
400MW Pumped-Storage Station
3 Identical Units
Commissioned 1965
Three year Construction
Jointly Owned
Remotely Dispatched
Asia Pacific Partnership • Aug 13 - 17, 2007
FirstEnergy Corp. & Duke Energy Corporation
Yards Creek Overview
2
Yards Creek Overview
Upper Reservoir
– 163 Acres
– 4763 AF Power Storage
– 49’ Elevation Variation
Lower Reservoir
– 302 Acres
– 4763 AF Power Storage + Seasonal Storage
– 18’ Elevation Variation
Auxiliary Reservoir
– 380 AF Seasonal Storage
Asia Pacific Partnership • Aug 13 - 17, 2007
FirstEnergy Corp. & Duke Energy Corporation
Yards Creek Overview
3
Yards Creek Overview
3000MWH Energy Storage
Peak Load Generation
Load Regulation
Voltage Support
Black Start Capability
Asia Pacific Partnership • Aug 13 - 17, 2007
FirstEnergy Corp. & Duke Energy Corporation
Yards Creek Overview
4
Equipment Suppliers
BLH Pump-Turbines—American Hydro Runners
Pelton Governors
GE Motor-Generators—National Electric Coil Rewinds
GE EX2000 Voltage Regulators
Allis-Chalmers Spherical Valves
Siemens 3AF Vacuum 14.4kv Generator Breakers
Siemens 230kv GCB’s
Westinghouse 144MVA Step-up Transformers
Delta Star 230kv Phase Reversal Switches
375kva Emergency Generator
Asia Pacific Partnership • Aug 13 - 17, 2007
FirstEnergy Corp. & Duke Energy Corporation
Yards Creek Overview
5
Operation
Upgraded Pump-Turbines—6% Efficiency Gain
750,000+MWH Annual Generation
Equivalent Forced Outage Rate (EFOR) < 1%
High Starting Reliability
Asia Pacific Partnership • Aug 13 - 17, 2007
FirstEnergy Corp. & Duke Energy Corporation
Yards Creek Overview
6
Daily Cycling
7 hours Generation at Maximum Output
9 hours to refill Upper Reservoir
600 Generate Starts/Year per Unit
Asia Pacific Partnership • Aug 13 - 17, 2007
FirstEnergy Corp. & Duke Energy Corporation
Yards Creek Overview
7
Staffing
On-site Staffing
– 6 Hydro-Technicians
– 1 Administrative
– 2 Management
Corporate Support
–
–
–
–
–
Engineering
Environmental
Administrative
IT
Legal
Other
– Contract Labor Services
– Security Services
Asia Pacific Partnership • Aug 13 - 17, 2007
FirstEnergy Corp. & Duke Energy Corporation
Yards Creek Overview
8
Priorities
Safety
Environmental and Regulatory Compliance
– Federal Energy Regulatory Commission (FERC)
– New Jersey Department of Environmental Protection
(NJDEP)
– Delaware River Basin Commission
Reliability
Cost Effective Operations
Asia Pacific Partnership • Aug 13 - 17, 2007
FirstEnergy Corp. & Duke Energy Corporation
Yards Creek Overview
9
Operations
Remotely Dispatched from Reading, PA.
Automated with Local Operation Capability
Alarms are Remotely Telemetered
Reservoir Levels are Remotely Telemetered
5 Minute Generate Starting
10 Minute Pump Startup—Across Line Start
Asia Pacific Partnership • Aug 13 - 17, 2007
FirstEnergy Corp. & Duke Energy Corporation
Yards Creek Overview
10
P/G Cycle Efficiency
Original = 67%
New Runners = 73%
P/G Ratio
Asia Pacific Partnership • Aug 13 - 17, 2007
FirstEnergy Corp. & Duke Energy Corporation
1967
1970
1973
1976
1979
1982
1985
1988
1991
1994
1997
2000
2003
2006
1.7000
1.6000
1.5000
1.4000
1.3000
1.2000
Yards Creek Overview
11
Significant Projects
Pump-Turbine Upgrades – 70 MW increase
– Unit No. 1 1995
– Unit No. 2 1993
– Unit No. 3 1996
Motor-Generator Rewinds
– Unit No. 1 1996
– Unit No. 2 1997
– Unit No. 3 1996
230kv Gas Circuit Breaker Replacements
– Unit No. 1 2005
– Unit No. 2 2005
– Unit No. 3 2006
Asia Pacific Partnership • Aug 13 - 17, 2007
FirstEnergy Corp. & Duke Energy Corporation
Yards Creek Overview
12
Significant Projects
Voltage Regulator Replacement
– Unit No. 1 2001
– Unit No. 2 2001
– Unit No. 3 2001
Penstock Interior Inspection and Painting--1995
Asia Pacific Partnership • Aug 13 - 17, 2007
FirstEnergy Corp. & Duke Energy Corporation
Yards Creek Overview
13
Turbine Upgrades
Replacement runners
Modified/new wicket gates
Modified stayvane
Modified draft tube
New wicket gate linkage
Reinforcement of stayring bolting flange
Greaseless wicket gate bushings
Asia Pacific Partnership • Aug 13 - 17, 2007
FirstEnergy Corp. & Duke Energy Corporation
Yards Creek Overview
13
Stator Rewinds
Unplanned Outages after
20yrs Service
Achieved Increased
Capability
Asia Pacific Partnership • Aug 13 - 17, 2007
FirstEnergy Corp. & Duke Energy Corporation
Yards Creek Overview
14
230kv GCB Replacement
Unplanned Outages after 20yrs Service
Achieved Increased Capability
Asia Pacific Partnership • Aug 13 - 17, 2007
FirstEnergy Corp. & Duke Energy Corporation
Yards Creek Overview