Unit 12
Foundation Plans
page 123
Learning Objectives
Identify footings on foundation
plan
Identify various components of a
foundation system
Recognize reinforcing steel on
prints
Footings
Unit 12
page 123
are the “feet” upon which the
entire building rests
shown on the foundation plans
footing sizes are determined by
loads from building
type of soil
Footings
column footings
Unit 12
page 123
usually wider & thicker due to
concentrated loads
column located in the center of
the footing
reinforcing
steel
Plan View
footing
column
Footings
column footings
column
centerline
column footings
Footings
column footings
Unit 12
page 124
Figure 12 -2
Footings
wall footings
Unit 12
page 124
support concrete foundation
walls
footings typically have a keyway
plans will indicate T/F (top of
footing elevation)
Footings
wall footings
reinforcing
steel
T/F 96’-6”
A
sometimes dashed
sometimes solid
Foundation Walls
Unit 12
page 124
are the base of the building
transfer the loads to the
footings
poured in-place concrete
used on commercial buildings
where extreme loads are present
masonry block
usually reinforced with steel
Footings
wall footings
Unit 12
page 125
Figure 12 - 5
Slabs
Unit 12
page 125
slab-on-grade or (ground) new
ACI term
unreinforced
reinforced - when subjected to
settling or heavy loads
mesh
reinforcing steel
post tensioned
steel fiber
floating slab or monolithic slab
one continuous unit
Slab-on-Grade - Plan View
no joints
saw cut pattern
Slabs
slabs on metal deck
structural slabs
flat slabs
waffle or dome
pan
beam & joist
Waterproofing
Foundations
Unit 12
page 125
protection against underground
water
consist of mopping the outside of
the wall with a tar or asphalt like
material
a layer of stone is laid against
wall to allow the foundation to
drain of water
Foundations
Unit 12
page 126
Figure 12 -6
Foundations
Unit 12
page 126
Figure 12 - 7
Test Your Knowledge
take 10 minutes to complete the
test on page 127
Concrete Foundation for an
Office
Unit 12
Take 10 minutes & complete the
questions for Activity 12-1 on
page 129 refer to large prints 12-1
Concrete Foundation for a
Residence
Unit 12
Take 10 minutes & complete the
questions for Activity 12-2 on
page 130 refer to large prints 12-2
END OF UNIT 12