Economic Evaluation - Massachusetts Institute of Technology

Download Report

Transcript Economic Evaluation - Massachusetts Institute of Technology

Economic Evaluation

Objective of Analysis

Criteria

Nature

Peculiarities

Comparison of Criteria

Recommended Approach Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 1 of 22

Objectives of Economic Evaluation Analysis

Is individual project worthwhile? Above minimum standards?

This is a “choice”, is it better or not?

This is easier

Is it best? Is it at top of ranking list?

This is a “judgment” about details

This is more difficult

Note difference between “choice” and “judgement” -- a key consideration in selection of method to be used in real options analysis Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 2 of 22

Principal Evaluation Criteria

Net Present Value

Benefit - Cost Ratio

Internal Rate of Return

Cost-Effectiveness Ratio

Pay-Back Period Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 3 of 22

Net Present Value

NPV = B - C (stated in present values)

Objective: To Maximize

Advantage: Focus on Result

Disadvantages

Interpretation of NPV

No account for scale, thus difficult to use for ranking Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 4 of 22

Activity: Years:

Present Value and Net Present Value: Example Calculations

Initial 0 1 2 3 4 5 6 7 8 Rehab 9 10 11 12 Cash Flow -100 5 10 20 40 50 40 30 20 -40 35

Use NPV function in Excel. Note carefully that it assumes you mean that all cash flows occur at the end of the relevant period, not at beginning.

25 15

Present Value of cash flows at end of year 1, 2,etc, at rate = NPV (rate,c9:n9) Discount rate expressed either in percent or decimal: 10% or 0.1

$143.58

Net Present Value is above plus cash flow at time zero= NPV(0.1,c9:n9) +b9

$43.58

Note: c9:n9 => range of years 1 to 12; b9 => year 0 Thus formula = NPV of cash flows to start of year 1 + cost investment Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 5 of 22

Difficulty in Interpreting Meaning of NPV

Suppose for example that a project

costs 1000

sells 4 years later for 1500

The obvious profit is 500 = 1500 - 1000

From an NPV perspective, however, we get

– –

NPV = 1500 / (1+r) exp 4 - 1000 This amount depends on discount rate, r

– –

If r = 10%, NPV ~ 1500 / 1.47 - 1000 ~ 20 Try telling that to tax authorities -- or others!

Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 6 of 22

Evaluation of Projects S and T

Project S T Benefit $ Cost $ Net Value $ 2,002,000 2,000,000 2,000 1,000 Which project has the highest Net Present Value?

Which would you choose?

When might NPV be a good method?

NPV as % of Cost 0.1

100 Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 7 of 22

Benefit - Cost

Ratio =

B /

C (Present Values)

Objective:

To Maximize

Advantage:

Common Scale, Useful in Ranking

Disadvantages:

Treatment of Recurring Costs

B /

C or Net Benefits/Investment = > Bias against operating projects

Ranking sensitive to r low r = > higher rank for long-term projects Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 8 of 22

A Comparison of a Capital Intensive and Operations Project

(Benefits in Present Values) Project Investment, C Annual Cost, C k r Annual Benefits Annual Return Useful Life T otal Benefits T otal Cost, C k + C r Benefit/Cost Ratio Annual Return Net Value Present K $1,000,000 $50,000 $200,000 $150,000 10 Years $2,000,000 $1,500,000 1.34 better than 15% worse than $500,000 worse than R $1,000,000 $500,000 $700,000 $200,000 10 Years $7,000,000 $6,000,000 1.17

20% $1,000,000 Note: Because B/C counts recurring costs as part of total costs, It disadvantages projects with operating costs (ex: factories), And favors capital intensive projects (hydropower dams) Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 9 of 22

The Ranking of Projects by Benefit-Cost Criterion Can Depend on DR

Project A Investment C k ,$ 1000 Annual Benefits R, $ 200 B 1000 125 Project Life N Years Benefit - cost at discount rate of 3% 10% 10 20 1.73 1.23

(best) 1.86 1.05

(best) Note: Varying the DR changes the Relative value of projects Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 10 of 22

Internal Rate of Return

IRR = r such that NPV = 0

Objective:

Maximize IRR

Advantages:

– –

No need to choose r Manipulation by r impossible

Disadvantages:

Calculations complex -- but easy in spreadsheet

Ambiguous

Note: ranking by IRR and B/C ratio may differ Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 11 of 22

Data for calculation of IRR

Repeat of Example in Present Value/DCF lecture Example:

Year 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 Investment Net Income Cash Flow 15 -15 2 2 3 3 3 4 1 5 5 5 5 5 3 -2 4 4 5 5 NPV at 12% $0.79

Formula: NPV(12%, B9:K9)

Note: b9:k9 => range of years from 2001 to 2010 This NPV calculation assumes cash flows all at end of year Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 12 of 22

6 6

Spreadsheet Determination of IRR

Year Investment Net Income 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 15 2 3 3 4 5 5 5 3 4 5 6 Cash Flow IRR -15 13.33% 2 3 1 5 5 Formula: IRR(b9:k9) -2 4 5 6

Note: b9:k9 => range of years from 2001 to 2010 This NPV calculation assumes cash flows all at end of year Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 13 of 22

Graphical Determination of IRR

Determination of IRR

15.0

10.0

5.0

0.0

-5.0

1 4 7 10 13 16

Discount rate Engineering Systems Analysis Massachusetts Institute of Technology

Series1

Richard de Neufville © Economic Evaluation Slide 14 of 22

Projects can Lead to Ambiguous Solutions for the Internal Rate of Return

Project P Q Investment, $ C k 200 Annual Benefits $ R 100 Project Life Years N 5

Cash flow 500 200 t NPV 310

Closure cost at Year N-1 $ C c > RN - C k 310

5 % DR

Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 15 of 22

Ranking of Projects by Internal Rate of Return and Benefit-Cost Ratio Can Differ

Project A B Investment, C k , $ 1000 1000 Annual Benefits R, $ 200 125 Project Life N Years 10 20 Benefit - Internal Rate Cost of Return, 0% r = 3% 1.71 15.10

(best) 1.86 10.93

(best) Why is this? Because Relative value of project in B/C depends on DR Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 16 of 22

Pay-Back Period

PBP = Cost/Annual Benefits

Note: undiscounted

Objective:

To minimize

Advantages:

Really simple

No choice of r

Disadvantages

Difficult to rank correctly projects with different useful lives or uneven cash flows Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 17 of 22

Evaluation of Projects V and W

Project Investment, C k , $ V W 2000 2000 1 2 3 4 5 6 1000 800 1000 1000 800 800 800 800 800 Payback Period Years NPV at 10% IRR 2 2.5

487 1484 23.4% 32.7% Note: Although Pay-back period gives "wrong" results, many Managers prefer it, because they do not trust forecasts!

Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 18 of 22

Cost- Effectiveness Ratio

Ratio = (Units of Benefit) / Cost

example: “lives saved/million dollars”

Objective: To Maximize

Advantage: Avoids problem of trying to assign $ values to “intangibles” such as a “life”, “ton of pollution”, etc.

Disadvantage: No sense for minimum standard or limits Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 19 of 22

Data for of Cost-Effectiveness Analysis

Screening X-Rays Lab Tests MRIs Operations Lives Saved Project Cost, Millions Cost-Effectiveness Cumulative Project Cumulative Project Cumulative 20 40 60 75 100 20 60 100 135 175 0.5

2 7 12 25 0.5

2.5

9 19 37 40.0

20.0

8.6

6.3

4.0

40.0

13.3

4.0

3.0

1.9

Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 20 of 22

120 100 80 60 40 20 0 0

Cost-Effectiveness Analysis

Lives Saved by Projects

10 20

Currency, Millions

30

Cumulative Lives Saved for Budget

200 180 160 140 120 100 80 60 40 20 0 0 10 20

Currency, Millions

30 40

What is value of life? How much budget should we spend on this?

Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 21 of 22

Recommended Procedure (if you have discretion to choose)

Examine Nature of projects

Easy to put into $ terms? Steady cash flows? or with closure costs? Or various project lifetimes?

An operating or a straight capital investment?

Choose Method Accordingly

No method is perfect -- ultimately a judgment

Current “best practice” uses several criteria; uses judgment to decide on project Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 22 of 22

A Note for Optimal Plant Exercise Part 1 Average Costs of Production vary

Total Cost Average Cost 1 5.2

5.2

2 3 5.4

5.6

2.7 1.867

4 5.8

1.45

5 6 1.2

6 7 8 9 6.2

6.4

6.6

6.8

1.03 0.914 0.825 0.756

10 7 0.7

Capital cost =5 Labor and Materials =0.2/part Maximum Capacity= 10

Total Cost vs Average Cost

8 2 0 6 4 1 2 3 4 5 6 7 8 9 10

Number of Parts

Total Cost Average Cost

Engineering Systems Analysis Massachusetts Institute of Technology Richard de Neufville © Economic Evaluation Slide 23 of 22