Software Development Methods

Download Report

Transcript Software Development Methods

SPPMG Event
18th February 2010
Why (IT) Projects Fail
Malcolm Bronte-Stewart
School of Computing
University of the West of Scotland
Objectives
This presentation will:
• Discuss some of the costs and causes of
technology project failure
• Challenge the way in which project failure
is judged
• Suggest pre and post project evaluation
techniques that may be useful to SMEs
M B-S
2
Cobb’s Paradox
“We know why projects fail, we
know how to prevent their failure
– so why do they still fail?”
Martin Cobb, Treasury Board of Canada Secretariat in Unfinished
Voyages, a follow to the CHAOS report, The Standish Group
M B-S
3
Lyytinen and Robey (2000)
“Organisations fail to learn from their experience
in systems development because of limits of
organisational intelligence, disincentives for
learning, organisational designs and
educational barriers. Not only have many
organisations failed to learn they also have
learned to fail. Over time they accept and
expect poor performance while creating
organisational myths that perpetuate short-term
optimisation.”
M B-S
4
Project Failure
IT projects tend to go over budget and / or over time
schedule and / or do not meet expectations
• Research by the BCS, Royal Academy of Engineering,
OASIG, Oxford University and others suggest that
only about 15% to 30% are successful
• Conservative estimates put the cost of IT project
failure at tens of billions of Euros across the EU Jaques,
2004 (142 billion euros in 2004 McManus & Wood-Harper, 2008) and
around $500 billion wasted on IT purchases that fail to
reach their objectives worldwide Feld & Stoddard, 2004
• We go on making expensive mistakes
M B-S
5
M B-S
6
M B-S
7
M B-S
8
M B-S
9
M B-S
10
M B-S
11
M B-S
12
M B-S
13
M B-S
14
M B-S
15
IT Development Project Costs
• $55 billion wasted on cancelled and over-run IT
projects in the USA in 2002 (Standish, March 2003)
• “Public sector IT expenditure over past 12 months
is in excess of £12.4 billion with a significant
proportion at risk of being wasted” according to a
House of Commons select committee (published July
2004)
• “This year (2006) organisations and governments
will spend and estimated $1 trillion on IT hardware,
software and services worldwide”. (Charette, IEEE)
M B-S
16
IT project success statistics
• 75% of IT projects are challenged and 10% are
abandoned (Oxford University, August 2003)
• Only 7% of the 1000 firms Critical Research
surveyed thought they were using IT effectively and
75% of these firms think that their IT systems are not
providing a return on investment
• Of 3,682 projects in 365 firms – 31% were cancelled,
53% had cost overruns and poor functionality and
only 12% were on-time and budget (Johnson)
• Three quarters of large systems may be considered
failures (Laudon & Laudon)
M B-S
17
For example - some Headlines
• 2010 New HMRC inland revenue tax system producing
wrong codes “ we’ve heard it all before”.
• 2010 Labour accused of wasting 26bn on failed IT projects
“stupendous incompetence”.
• 2009 Rural payments scheme put out to grass “a display of
scant regard for protecting public money”.
• 2009 C-nomis offender management system
sloppy project management”
“a master class in
• 2008 Edinburgh Fringe Box-office system
“weak”, “fundamentally
flawed” “insufficient planning, lack of risk management, inadequate
communications and no authorised business case”.
• 2005 Strathclyde Police Computer System “a complete disaster”
• 2003 Libra the IT system for magistrates courts “One of the
worst projects I have ever seen”.
M B-S
18
“Prison IT system guilty of 'basic'
project management failures” (2009)
• The £234m C-Nomis IT system for Prisons failed
in almost every possible way .
• The NAO concluded that the technical complexity had been
“significantly underestimated”. C-Nomis was treated as an IT project
and not a business-change programme, project management was
poor, and contracts with suppliers were weak.
• Edward Leigh, chairman of the Public Accounts Committee, said of CNomis that “kindergarten mistakes” had been repeated: “This
Committee hears of troubled government projects all too frequently.
But the litany of failings in this case are in a class of their own. All of
this mess could have been avoided if good practice in project
management had been followed.”
M B-S
19
IT project failures
• The Defence Information Infrastructure project to
incorporate 150,000 terminals for 300,000 users at
over 2000 defence sites is 18 months late and
running more than £180m over budget.
• The official cost of the controversial national identity
system has soared to over £5bn.
• The NHS IT scheme [NPfIT] was initially estimated
to cost around £2.3bn. The most recent estimate is
£12.7bn.
M B-S
20
IT Project Failure
• Sainsbury’s, the supermarket giant,
installed an automated fulfilment
system to increase efficiency and
streamline operations in 2003.
• The system ran into "horrendous"
barcode-reading errors. Yet in 2005
the company claimed the system was
operating as intended.
• Two years later, the entire project was
scrapped, and Sainsbury's wrote off
£150 million* in IT costs.
* (One report claims it was a $526m investment)
M B-S
21
Avon County Council installed a new computer
program to pay staff wages.
•
•
•
•
The spree started in a small way paying a caretaker £75 an hour.
Then it didn’t pay canteen workers at all for 7 weeks.
Next it paid a janitor £2,600 for a week’s work.
A deputy headmistress received her year’s annual salary once a
month.
• Heads of department earned less than their assistants.
• Some people had more tax deducted in a week than they earned
all year.
• By February 280 council employees were out on strike.
(Stephen Pile)
M B-S
22
The misguided torpedo assumption
• To prevent the possibility of a torpedo
returning and exploding against the ship it was
fired from
• a safety system built so that it would selfdestruct if it turned 180 degrees
• Unfortunately, during trials, a torpedo jammed
in its tube on board the ship, the test was
abandoned and the ship turned round to go
home …. BANG!
M B-S
23
London Ambulance System
New Software “Put Lives At Risk!”
• Main Findings of investigation
– Inexperienced procurement team
– Staff mistrust and opposition
– Over-ambitious timetable
– Price put before quality
– Incomplete and untested software
– Andersen Consulting report suppressed
– Management failed to identify and solve problems
– Users “did things wrong”
“...a faulty system implemented with undue haste, by a management
determined to impose its will...”
M B-S
24
IT Project Research
• Jones, in a study of 250 large software projects at
or above 10,000 function points* between 1995
and 2004 found that about 25 were successful,
50 had minor delays and 175 had major delays
and overruns or had been terminated without
completion.
• He notes that the main problems were not
technical but were due to aspects of poor project
management.
*(equivalent to around1,250,000 statements in the C programming language)
M B-S
25
Wider effects of IT project failure
• Perceptions of poor success rates and wasted
resources affect decision making
• The more IT projects are seen to go wrong the more:
– the public become cynical
– staff learn to expect problems and delays
– Developers wonder if a lot of their work is likely to be
wasted effort
– business people become nervous of technology change
– those holding the purse strings may view IT as a worry and
a poor return on investment
M B-S
26
What are the main causes of failure?
• 6 major research studies reach remarkably
similar conclusions about the significant
causes that threaten project success:
– OASIG
– Standish (CHAOS)
– Select Committee
– OGC / NAO
– Schmidt, Lyytinen, Keil & Cule,
– Fortune and White
M B-S
27
OASIG Report (Clegg et al,1996)
• Outcomes from IT investment :
– 80% to 90% do not meet goals
– 80% delivered late and over budget
– 40% fail or are abandoned
– Under 40% address training and skills enough
– Less than 25% integrate business and
technological objectives properly
– Only 10% - 20% meet all success criteria
M B-S
28
IT Project Failure (OASIG)
• Main reasons why IT projects fail
– Management agenda is too limited
• most IT investments are technology led
• main investment motive is to only cut costs
– This narrow focus on technical capabilities and efficiency goals means
that inadequate attention is given to the human and organisational
issues that can determine a project’s ultimate success.
– Users don’t influence development enough
– Senior managers don’t understand the links between technical and
organisational change
– Project management techniques and IT approaches are too technical
– Companies fail to organise work or design jobs/roles properly
M B-S
29
The Standish Group (1995)
Of the $250 billion spent each year on IT application development
• 31.1% of projects cancelled before completion (failed).
• 52.7% of projects were challenged: over-budget, over the time
estimate, and offers fewer features and functions than originally
specified.
• 16.2% of software projects were successful - completed on
time, on-budget and to specification, (but some of the largest of
which have only approximately 42% of the originally-proposed
features and functions).
• Recently these results have improved somewhat but remain
disappointing.
M B-S
30
Standish Group CHAOS Survey Results
M B-S
31
M B-S
32
CHAOS Project Success Factors
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
User involvement
Executive management support
Clear and firm statement of requirements
Proper planning and formal methodology
Realistic expectations
Minimised scope and smaller project milestones
Competent, skilled staff
Ownership
Clear vision and business objectives
Hard-working, focussed staff
Experienced project managers
Reliable estimates
M B-S
33
Select Committee on Public Accounts
Report on Improving the delivery of Government IT
projects (Study of 25 projects 1990 to 2000)
• “Implementing IT systems has proved difficult”
• Frequent cases of delay, confusion and
inconvenience for the citizen and poor value for
money for the tax payer.
M B-S
34
Select Committee Report conclusions
1. Decisions about IT are Business not technical, they have profound effects on
customer service and must involve senior management.
2. End users and their business needs must be identified before the project
commences so that clear objectives are taken into account fully during design and
development
3. Scale and complexity – how ambitious? Can it be undertaken in one go?
4. Skilled Project Managers are essential
5. Sound methodologies and well conceived risk management are called for
6. Need for a high degree of professionalism in the definition, negotiation and
management of IT contracts
7. Training can take up considerable resources but must address the needs of the
users and of those maintaining the systems if the anticipated benefits are to be
realised
8. Contingency plans should be in place
9. Organisations should learn lessons from project undertaken. A post implementation
review should establish the extent to which they secured the proposed business
benefits, user expectations and technical requirements.
M B-S
35
OGC and NAO Best Practice 2005
Common causes of project failure
•
•
•
•
•
•
•
•
•
1. Lack of clear links between the project and the organisation's key strategic
priorities, including agreed measures of success.
2. Lack of clear senior management and Ministerial ownership and leadership.
3. Lack of effective engagement with stakeholders.
4. Lack of skills and proven approach to project management and risk
management.
5. Too little attention to breaking development and implementation into
manageable steps.
6. Evaluation of proposals driven by initial price rather than long-term value for
money (especially securing delivery of business benefits).
7. Lack of understanding of, and contact with the supply industry at senior levels
in the organisation.
8. Lack of effective project team integration between clients, the supplier team
and the supply chain.
M B-S
36
Keil, Cule, Lyytinen & Schmidt (1998)
These researchers recruited 3 panels of experienced project
managers in different places – Finland, Hong Kong & U.S.A. –
and asked them to identify and rank specific risk factors.
–
–
–
–
–
–
–
–
–
–
Lack of top management commitment to the project
Failure to gain user commitment
Misunderstanding the requirements
Lack of adequate user involvement
Failure to manage end user expectations
Changing scope / objections
Lack of required knowledge / skills in project personnel
Lack of frozen requirements
Introduction of new technology
Conflict between user departments
M B-S
37
Fortune and White (2006)
Fortune and White reviewed 63 publications that focus
on project Critical Success Factors
• The top ten (in order of count of citations) of the 27 they quote are:
–
–
–
–
–
–
–
–
–
–
Support from senior management
Clear realistic objectives
Strong / detailed plan kept up to date
Good communications / feed back
User / client involvement
Skilled / suitably qualified / sufficient staff / team
Effective change management
Competent project manager
Strong business case / sound basis for project
Sufficient / well allocated resources
M B-S
38
OASIG
Select Committee
IT projects are
business
(not
decisions
NAO / OGC
Keil et al
CHAOS
(Top Fortune
Requirements:)
(CSFs)
Evaluation of proposals driven by
Misunderstanding
driven by Many IT investments are
initial price rather than long term
requirements
technical) seen only as technology led
value, especially securing delivery of
and aimed at cost cutting
business benefits
and
White
user Clear business objectives Strong business case /
and
Realistic sound basis for project
expectations
Lack of user involvement
Insufficient involvement from Users do not influence Lack of effective engagement with or commitment
User involvement
users
development enough
stakeholders
User / client involvement
Lack of clear link between the project
Unclear and changing
Clear realistic objectives
Need to set and review
Clear objectives should be set
and the organisation’s key strategic
Clear and firm statement
scope and objectives
strategic
objectives
for
from the start
priorities, including agreed measures
of requirements
change
of success
Lack of commitment
senior management
Large
projects
overambitious
may
from Management agenda is Lack of clear senior management Lack of top management Executive
commitment
often too limited or narrow
ownership and leadership
support
be
Skilled project managers are
essential to keep to time and
budget
and
appropriate
deliverables
from
management Support
management
senior
Project size, complexity,
Inadequate
attention
is Too little attention to breaking Number of organisational Minimised scope and number
of
people
given
to
human
and development and implementation units involved
smaller
project involved, and duration
organisational issues
into manageable steps
milestones
Competent
project
manager and effective
project
change management
Senior managers do not
of
required
Lack of skills and proven approach to Lack
understand the link between
Experienced
project management and risk knowledge and effective
technical and organisational
managers
project
management
management
change
skills
Correct choice / past
Lack of effective project
experience of project
Proper planning and
management
management
formal methodology
methodology
methodology / tools
Some project management
Success depends on good risk
techniques
and
IT
analysis
and
sound
approaches
are
too
methodologies
technical
Contingency plans should be Must work to detailed
in place
implementation plans
Not managing
properly
change Reliable estimates
Strong / detailed plans
kept up to date
Inappropriate staffing and
Skilled / suitably qualified
User and operator training Failure to organise changes Inadequate resources and skills to ill defined responsibilities Competent, skilled and and sufficient staff / team
must be planned and designed in work and roles properly
deliver the total delivery portfolio
focussed staff
There should be a
implementation review
post-
Need professionalism in the
definition, negotiation and
management of IT contracts
Introduction
technology
Lack of understanding of , and
B-S at
contact with, the supplyMindustry
senior levels in the organisation
of
new Standard
infrastructure
Ownership
Planned close down /
software review, acceptance of
possible failure
Good communication /
39
feedback
Are IT Projects Different?
• IT and software-based projects have certain
characteristics which make them different
–
–
–
–
–
–
–
–
–
–
–
specification
requirements creep
invisibility
complexity
flexibility
estimation
training / churn
changing technologies
communication and conflict
resistance to change
testing
M B-S
40
Risk Analysis
• Consideration of these recognised common
causes of project failure, taken with reports, case
studies, project management experience and
previous research, build a picture of the variety
and scope of important risk factors.
• Instead of expecting individuals to guess the likely
risks for each project we can specify a standard,
comprehensive collection of a variety of aspects
and issues that threaten successful IT project
outcomes.
M B-S
41
Risk Analysis Technique
A technique has been developed that is intended
to help project managers and others to gauge
and take account of these risk factors.
It requires little training and gives a structured list
of relevant questions that invite the user to
consider the extent to which each element
threatens the project under review .
These can be separated into 3 (or 4) groups:
Some concern the firm itself and are slow to change
Some concern the project in question
Some concern the details of the options being
assessed and compared
(This Environment)
This Organisation
This Project
This Option
To create a series of Risk Tables
M B-S
42
M B-S
43
M B-S
44
M B-S
45
Risk or Threat Level
• Each factor may be awarded its own weighting (or ignored)
according to its perceived significance
• Multiplying the weights by the scores gives a total value for
each factor and these can be summed to arrive at the overall
value
• Comparing your risk analysis values with those of others
provides a focus and common language to bring out
concerns, specific issues, enlightened evaluation and
assessment of likely dangers and potential problems
• The technique may become more valuable the more it is used
as experience of the results and the model’s inadequacies
develops
M B-S
46
Other issues
There are at least two other aspects that might usefully be
taken into account:
1. The wider environment, trends and market conditions, ie
the level above the first table that is outside the control of
the organisation in question but influences project choice
2. The degree of uncertainty in the estimates of risk factors
So these tables provide an IT project risk analysis readyreckoner in a standardised and quantifiable form that can
be applied before the project begins, or during a
feasibility study
But how do we judge the finished project?
M B-S
47
Measuring Success
• Three factors are used to decide if a project
is a success or a failure soon after its
closure:
– Time / on schedule?
– Money / within budget?
– Delivered product / to specification?
}
Yes
or
No
• Fail any one of these tests and it may be
labelled a failed project (even though it passes the other two)
M B-S
48
Three factors – “The Iron Triangle”
Good?
Quality / Scope / Functionality
Did the
project
come in on
or under
budget and
schedule?
AND did the
project meet
customer
requirements?
Time
Quick?
Cost
M B-S
Cheap?
49
Failures?
What about the extent and type of the failure?
• Some are abandoned, some are incomplete but in use
• Some just overrun budget or time, others are total
disasters
• The project management process may be a mess
AND / OR
• The delivered product may be useless or unwanted
• How do we differentiate and categorise the relative
success / failure of IT projects?
M B-S
50
Maybe graphics would help?
Budget
Time
Scope
400%
Over
300%
200%
Original
estimate
100%
50%
Under
25%
10%
M B-S
51
Failure?
• Was failure an event or a process – did it suddenly
appear or take time to become evident?
• Was / Were there:
– Undisclosed needs and requirements creep?
– Over-optimistic budget and timescale?
– Weak methodology, changing team and power struggles?
• Does blame lie more with the clients who expected too
much, or the planner who set the parameters, or the
project manager who had to please the clients and abide
by the parameters?
• How can we tell?
M B-S
52
So What is Project Failure?
• Should a project be regarded as a failure if it
1. overruns budget or timescale slightly but the customer is happy with
the results?
2. Comes in under budget and time but gains little acceptance
• Judging overall success by using just the three factors is
arguably too short-sighted and simplistic
• “the operation was a success but the patient died”
• We may be ignoring many of the richer outcomes and
avoiding a more systemic view
• Perceptions change over time
• Project success may not mean Product success
M B-S
53
Famous Project Failures?
Sydney Opera house
• 18 times over budget
• yet world renown icon of Australia
Titanic Movie 1997
• one of the most expensive films
ever made at the time, lots of
problems during shooting, went
well over schedule and budget and
the producers wanted to cut it by 1
hour yet it was the highest grossing
movie ever (till Avatar) won critical
acclaim and 11 Oscars.
M B-S
54
Famous Project Failures?
Millennium Dome hit financial difficulties and found itself
needing an additional £179 million of National Lottery
funding during 2000 but it attracted 5.5 million paying
visitors: twice as many as any other UK visitor attraction in
the previous year.
The vast majority of
visitors (87%) were
satisfied with their day
out and it opened its
doors on time.
But what now?
M B-S
55
Empire State Building
• Objectives: in 1929, to be the highest building in New
York (to beat the Chrysler Building)
• It achieved that objective, was completed well ahead
of schedule and well below budget. ... So a Success!
• But for the same reason that anticipated costs had
been halved - the great depression - rental rates were
low and it was called the “Empty State Building”
• It did not turn a profit until 1947 .. So a Failure!
• Today it is 97% occupied, world famous and tallest
M B-S
56
Famous Project Failures?
• The channel tunnel was initially budgeted at $7 billion but it
entered service in 1994 with a price tag of over $13 billion.
• In 2002 it was still burdened by $9.3 billion in debt
• By 2004 it was £10billion....
• But now carries millions of passengers...
M B-S
57
Famous Project Failures?
• Thames Barrier
begun in 1974, opened in
1984 way over budget
(£55m estimate / £435m
actual) and time schedule
• But what if it had not been
built?
M B-S
58
Passport Agency IT system
• Initial assessments were
unflattering, long delays and costs
over £12m (which included
£16,000 on umbrellas for those
waiting in queues)
• Yet 4 years later the systems was
working well with 99.5% of
straightforward applications turned
around within 10 days.
M B-S
59
Sauer (1988) comments:
• “Some systems never work.
• Some are never made operational because they will be
unacceptable to the user.
• Some work but come in cripplingly over budget, very late or both.
• Others are pared down while still others are literally forced into
place in their host organisation, despite their being either
inappropriate or unacceptable.
• Some perform to specification but turn out to be so inflexible that
maintenance and enhancement assume nightmarish proportions.
• Others are thought to work but turn out not to.”
M B-S
60
Who says it is a failure?
• Views may differ
• Did it produce unwelcome outputs for some?
• “A human system fails if it does not succeed
in doing what it was designed to do; or if it
succeeds but leaves everyone wishing it had
never tried.” (Vickers, 1981)
• Unintended impacts and consequences may
emerge
M B-S
61
Perceptions of Failure
• Lyytinen and Herscheim (1987) view IS failures
simply as problems that stakeholders perceive
– But how many stakeholders do we ask and when is any
problem too trivial to count?
• Robinson (1994) suggests that a project’s success
or failure is often determined by particular groups in
the context of a political and social environment.
M B-S
62
Short and long term objectives
Peterson and Kim, 2000, suggest a 4 way classification:
System
User
Short-term Reliable (bug- Satisfying
Objectives free) system user needs
Organisational
Improving the
effectiveness of
business
operations
Strategic
Improving
customer
service
Long-term Easily
Objectives maintainable
system
Generating
operational
benefits
Enabling
cooperative
partnership
Improving
productivity
of managers
M B-S
63
Awkward balances and compromises
“The management of IS projects is a difficult and complex task
and there are no magic bullet solutions. IS projects are
intrinsically uncertain. The management complexity arises
from the necessity to deal simultaneously with several
tensions:
– Innovation versus risk
– Learning versus control
– The need for organisational change to deliver business benefit versus
stakeholder resistance to change
– Multiple stakeholder perceptions of the purpose of the project
– The need to deliver value to the organisation versus managing effectively to
satisfy time, quality and cost objectives
– Managing detail and the big picture”.
Roger Elvin
M B-S
64
Balanced Scorecard Performance Measurement
Financial
Customer
Vision
and
strategy
Internal
Business
Process
Learning and
Growth
(Based on Norton and Kaplan original model)
M B-S
65
Failure - Success Continuums
• We need to extend and amplify our evaluation
to include impressions of:
1. Long-term effects, benefits and drawbacks, ROI,
process improvements, efficiencies, cost
reductions, income generated, money well spent?
2. Stakeholder acceptance, to what extent are the
customers and sponsors pleased with results?
3. How successful was the team and the
methodology that was used, lessons on approach
and structure
M B-S
66
1 Long-term effects –
The investment
How has it changed the business?
• Business and organisational benefits may not
be realised quickly
• It will often take time for the IT system to
produce improvements
• Unexpected drawbacks and advantages may
appear once the system is in operation
• Failed projects provide useful lessons
M B-S
67
Financial Services Firm BPR
• A New Zealand firm instigated a consultancy led BPR project
to improve customer service, reduce costs and improve the
quality of work performed.
• They implemented a standard ERP system (SAP)
• Initially the project was regarded as a success, with 64%
reduction in staff and projected savings of $2million per
annum.
• Two months later however the unintended consequence of
the BPR project was that all in-house expertise had
disappeared from the accounting group and no one could
operate the SAP system properly.
M B-S
68
2 Stakeholders The Requirements
• There are normally several parties interested in,
dependant upon and maybe hostile to the implications
and outcomes of any IT project.
• It will often cause change and disrupt the status quo
• Different stakeholders may hold differing views about
what they want from (and fear about) the project.
• Each group of stakeholders may judge the success of
the project according to different feelings, beliefs and
M B-S
69
measures.
M B-S
70
Stakeholder analysis and management
High
Level of
concern
and
interest
in project
Keep informed,
Key players,
Show consideration,
Manage closely,
Consult
Partner & collaborate
Keep channels open,
Keep satisfied,
Minimal effort,
Meet their needs,
Monitor
Involve
Low
High
Low
Power, influence, importance
Based on Gardener et al (1986)
M B-S
71
3 Team and Approach The Performance
• Review effectiveness and productivity of techniques
• Team performance – group size and composition, abilities, technical
strengths and weaknesses, training, leadership, team work
• Organisational structure
• Project management procedures and methods
• Administration – collecting, recording, monitoring and controlling
• Problems, errors and correction effort
• Appropriateness of methodology - Over 300 (Avison & Fitzgerald) maybe
1,000 (Jayaratna) different approaches identified
Commercial World
Academic World
M B-S
72
Methodology selection & starting point
Unclear and
undefined
Interpret
Messy
requirements
Terms
of
Reference
Decided and
Appreciate
views
Clear,
Static
defined
Known, understood,
agreed view of needs,
limited scope
M B-S
Situation
or
Context
Complex – a variety of
attitudes and opinions on
nature and size of
problems
73
The Singer or the Song?
Who/what is to blame when the methodology seems to
go wrong?
Perceptions of IT development success depends on a
number of interdependent issues
– The chosen approach / methodology - appropriateness, strengths
and weaknesses, application and tailoring (the Play or concert)
– The project manager and the team’s knowledge, experience,
training, personalities, attitude and ability to use the methodology
properly (the Interpreters – actors or orchestra)
– The client and user, values, involvement from the start,
requirements well defined, realistic expectations? (the Audience)
– The context, appreciation of the richness of the project situation
(the venue, background, economic climate, culture, history,
politics, market conditions)
M B-S
74
Maybe graphics would help?
Budget Time Scope
Business Stakeholder Method
Benefits
Views
&Team
Short-term
Long-term
400%
Over
300%
200%
Original
estimate
100%
50%
Under
25%
10%
M B-S
75
Conclusions
• This presentation looked at some costs,
causes and examples of IT project failure.
• It introduced a set of risk analysis tables
intended for SME IT projects.
• Having criticised current either/or fail/success
measurement models it described a broader
approach that may help to differentiate among,
reach a richer appreciation of, and assist
learning about projects.
M B-S
76
Questions?
M B-S
77