ACARP Roadway Development Operators Workshop March 2008 Roadway Development at Crinum Mine Gregory Crinum Introduction Development at Crinum Mine has undergone massive changes over the last 2 years. Changed from panel development off mains to punch longwall system. After 13 years of utilising Joy continuous miners introduced an ABM 25S continuous miner. 01.01.01 Gregory Crinum 2 Crinum Mine - Technical Data 01.01.01 Roof strength UCS 6 to 22 MPa Floor strength UCS 6 MPa Roadway width 4.8m Pillar dimensions 30m wide x 130m centres Coal Seam height 3.2m Cutting height 3.2 to 3.3m leaving 0.3m coal on the floor Stone cut 0.2 to 0.3m Gregory Crinum 3 Crinum Mine - Equipment 01.01.01 Joy 12CM32 continuous miner Joy 15SC32 shuttle car Joy Mobile boot end Track mounted auxiliary fan (18m3) with 720mm diameter ventilation tubes Panel belts 1400 belt and structure with 2 x 375kw drivehead and 300m loop take up Coal cleared via mains belts Pipes installed utilising pipe pods on MPV’s Stone dusting utilised stone dust pods on MPV’s Gregory Crinum 4 Crinum Mine - Development Rates Averaged 140m per week in MG15 MG15 Weekly Development Metres 250 206 200 185 Metres 164 186 181 212 177 166 159 150 120 107 159 128 136 136 109 107 103 92 100 156 147 125 115 100 145 142 143 136 118 184 221 213 205 201 105 106 80 74 70 65 40 50 08 Oct 24 Sep 10 Sep 27 Aug 13 Aug 30 Jul 16 Jul 02 Jul 18 Jun 04 Jun 21 May 07 May 23 Apr 09 Apr 26 Mar 12 Mar 26 Feb 12 Feb 29 Jan 15 Jan 01 Jan 0 Week Ending (Date) 01.01.01 Gregory Crinum 5 Crinum Mine - Development Rates Averaged 3.0m per op hr for 46.6 op hrs per week in MG15 MG15 Weekly Metres per Hour 4.50 3.91 Matres per Hour 4.00 3.69 3.49 3.09 3.003.23 2.882.96 2.84 3.50 3.00 3.43 3.33 2.67 2.40 2.19 2.50 3.223.09 2.68 3.82 3.47 3.38 3.44 3.24 3.20 3.03 2.953.01 2.86 2.96 2.862.902.97 2.66 3.69 2.842.76 2.84 2.50 2.36 2.31 1.91 1.79 2.00 1.50 1.00 0.50 08 Oct 24 Sep 10 Sep 27 Aug 13 Aug 30 Jul 16 Jul 02 Jul 18 Jun 04 Jun 21 May 07 May 23 Apr 09 Apr 26 Mar 12 Mar 26 Feb 12 Feb 29 Jan 15 Jan 01 Jan 0.00 Week Ending (Date) 01.01.01 Gregory Crinum 6 Decision Behind Crinum East Moved from Crinum to Crinum East in October 2006. Change from mains drivage to punch longwall system. Increase in productivity due to U/G panel belts only. No outbye mains areas to maintain. Trench conveyors simpler because they do not require gas monitoring and surface conveyors easier to maintain. Quicker travel time from surface to U/G – have Toyotas that can go from surface to crib room. 01.01.01 Gregory Crinum 7 Decision Behind Crinum East Less infrastructure to maintain – no complex gas monitoring system, u/g dewatering system, road maintenance. Longwall moves easier as there is no mains to deal with. Ventilation of panels simple. 01.01.01 Gregory Crinum 8 Crinum East Mine Plan 01.01.01 Gregory Crinum 9 Crinum East Trench 01.01.01 Gregory Crinum 10 Crinum East - Changes to Development Panel belts changed to 1050 belt with 1400 structure and 2 x 75 kw combi drives with a 7m loop take up. Coal stockpiled outside portal and trucked out of trench to surface stockpile. No MPV’s used at Crinum East as part of the BHPB FRCP’s. Pipe trailer and Eimco utilised for installing pipes. Quick duster utilised for stone dusting. Seam height 3.1m at Crinum East requiring additional stone to be cut 01.01.01 Gregory Crinum 11 Crinum East - Production with Joy CM Initially commenced development at Crinum East with Joy continuous miner. Small decrease in weekly development metres due to reduced operating hours. Mineworkers unfamiliar with pipe trailer. Lost time with stone dusting due to issues with the quick duster. 01.01.01 Gregory Crinum 12 Crinum East - Production with Joy CM Averaged 135m per week in MG17 with Joy miner. MG17 Weekly Development Metres - Joy Continuous Miner 300 244 Metres 250 200 169 157 186 171 167 119 114 119 158 100 62 52 40 50 119 111 104 91 202 200 179 141 134 131 150 191 188 52 31 29 Apr 22 Apr 15 Apr 08 Apr 01 Apr 25 Mar 18 Mar 11 Mar 04 Mar 25 Feb 18 Feb 11 Feb 04 Feb 28 Jan 21 Jan 14 Jan 07 Jan 31 Dec 24 Dec 17 Dec 10 Dec 03 Dec 26 Nov 19 Nov 12 Nov 05 Nov 29 Oct 0 Week Ending (Date) 01.01.01 Gregory Crinum 13 Crinum East - Production with Joy CM Averaged 3.2m per op hr for 42.4 op hrs per week in MG17 with Joy miner. MG17 Weekly Metres per Hour - Joy Continuous Miner Metres per Hour 4.50 3.85 3.70 4.00 3.74 3.44 3.50 2.96 3.00 2.50 3.24 2.67 2.592.61 2.84 2.77 3.72 3.40 3.13 3.35 3.03 3.11 3.25 3.25 3.44 3.13 3.29 3.11 3.00 2.38 3.50 2.38 2.00 1.50 1.00 0.50 29 Apr 22 Apr 15 Apr 08 Apr 01 Apr 25 Mar 18 Mar 11 Mar 04 Mar 25 Feb 18 Feb 11 Feb 04 Feb 28 Jan 21 Jan 14 Jan 07 Jan 31 Dec 24 Dec 17 Dec 10 Dec 03 Dec 26 Nov 19 Nov 12 Nov 05 Nov 29 Oct 0.00 Week Ending (Date) 01.01.01 Gregory Crinum 14 Introduction of the ABM The ABM continuous miner was introduced to Crinum due to a number of key factors: Continuous bolting and cutting cycle. The canopy suits poor ground conditions. The ABM was justified on a 15% productivity increase over the Joy miners. Expectation was 183m per week. Improved ergonomics at the bolter controls and elevating working platform for mineworkers and improved ergonomics for tradespersons. Roof mesh holder on the tail. 01.01.01 Gregory Crinum 15 Introduction of the ABM Monorail and flexiduct ventilation system to improve cutting rate and reduce manual handling of ventilation tubes. 01.01.01 Gregory Crinum 16 Introduction of the ABM The introduction of the ABM introduced significant changes to the mining cycle: The monorail and flexiduct ventilation system needed to be developed to suit Crinum. Supplies for the ABM required smaller cassettes and rackers. The cassettes for the Joy held 35m on 6 bolt pattern where the ABM cassettes could only hold 25m. Joy CM requires 5 person crews, ABM requires 6 person crews for continuous bolting and cutting. The majority of mineworkers in the department had not previously worked with ABM’s before. 01.01.01 Gregory Crinum 17 Crinum East - Production with ABM CM Drastic reduction in cutting time and rate leading to overall reduced metres per week. Identified a number of issues within the ABM system. The positive indicator is that cutting rate was improving toward the end of the panel. We know the system can produce metres with one shift achieving 38m. 01.01.01 Gregory Crinum 18 Crinum East - Production with ABM CM Averaged 84m per week in MG17 with ABM miner. MG17 Weekly Development Metres - ABM Continuous Miner 171 180 Metres 140 120 100 156 148 160 119 95 87 66 80 60 40 96 54 52 121 110 109 107 93 81 60 57 50 38 91 89 100 85 70 62 64 54 47 44 38 20 02-Dec 18-Nov 04-Nov 21-Oct 07-Oct 23-Sep 09-Sep 26-Aug 12-Aug 29-Jul 15-Jul 01-Jul 17-Jun 03-Jun 20-May 06-May 0 Week Ending (Date) 01.01.01 Gregory Crinum 19 Crinum East - Production with ABM CM Averaged 2.45m per op hr for 35 op hrs per week in MG17 with ABM miner. MG17 Weekly Metres per Hour - ABM Continuous Miner 4.00 3.56 3.13 3.13 Metres 3.50 3.38 2.85 2.58 2.53 2.22 3.00 2.562.642.70 2.36 2.50 2.00 2.71 2.692.812.682.74 2.38 2.25 2.17 2.82 2.61 2.202.25 2.19 2.00 3.27 2.7 2.56 1.46 1.50 1.09 1.00 0.50 02-Dec 18-Nov 04-Nov 21-Oct 07-Oct 23-Sep 09-Sep 26-Aug 12-Aug 29-Jul 15-Jul 01-Jul 17-Jun 03-Jun 20-May 06-May 0.00 Week Ending (Date) 01.01.01 Gregory Crinum 20 Crinum East - Issues with the ABM System There were a number of issues associated with the ABM and the system supporting it: 01.01.01 Issues with the ABM. Issues with shuttle car haulage. Issues with the flexiduct ventilation system. Issues associated with the conveyor system. Gregory Crinum 21 Crinum East - Issues with the ABM System Issues associated with the ABM: Cutting height had to be increased from 3.3m to 3.5m to allow flitting underneath the flexiduct in A heading. The cutting cycle was shuttle car constrained – gone from 2 cars per metre to 2.5 cars per metre. The tail on the ABM was shorter than the Joy miner. Large amount of road works required prior to flitting the miner. Issues with the pick lacing causing an arched profile. Excessive water usage creating a face water issue. Number of electrical faults. 01.01.01 Gregory Crinum 22 Crinum East - Issues with the ABM System Issues associated with the shuttle car: Shuttle car constrained - stubs had increased from 20m to 30m in A heading and 40m in B heading to accommodate monorail and flexiduct. Slow loading onto belts due to 1050 belt and jiffy drives. 01.01.01 Gregory Crinum 23 Crinum East - Issues with the ABM System Issues associated with the monorail and flexiduct: Flexiduct smaller in diameter by 20mm with higher resistance resulting in reduced quantity at face. Build up of fines in the throat. Flexiduct twists and collapses reducing ventilation to face near fan. Has added an additional shift to the panel extensions. 01.01.01 Gregory Crinum 24 Crinum East - Issues with the ABM System Issues associated with the conveyors / boot end: Utilising 1050 belt on boot end and structure designed for 1400 belt. Belt speed for 1050 belt is 2 m/s vs 4 m/s for 1400 belt requiring slow loading. Jiffy drives were too far apart causing belt slip and tensioning issues. Combi drive had only a 7m loop take up requiring a belt clipping station. Panel extensions taking 5 shifts on average. 01.01.01 Gregory Crinum 25 Crinum East - Improving the ABM System We have identified a number of problems that need to be resolved if we are going to be successful with the ABM mining system. We have commenced a Productivity Optimisation Process with Mining Consultancy Services. 01.01.01 Gregory Crinum 26 Crinum East - Improving the ABM System Improving the ABM: Reduced to height of the ABM to allow us to flit under the monorail and flexiduct in a 3.3m heading. Extended the tail to enable 2 cars per metre. Improved the panel standards (horizon control) to reduce the amount of road works required prior to flitting. Modified the pick lacing so we cut a square profile. Made changes to the water circuit to reduce water usage. Made a lot of changes to the electrical system. 01.01.01 Gregory Crinum 27 Crinum East - Improving the ABM System Improving shuttle car efficiency: Improved horizon control to reduce tramming time. Currently evaluating the use of a Stamler feeder breaker to allow unloading of the car on fast tram. 01.01.01 Gregory Crinum 28 Crinum East - Improving the ABM System Improving the monorail and flexiduct system: Trial of a monorail mule to assist packing up of monorail. Reducing the height of the trolly brackets to allow a 3.3m heading height. Tighten flexiduct rings to prevent twisting. Adding additional trolleys and rings near vent fan. Purpose built T pieces for the flexiduct. A new inline removable monorail section instead of the points currently utilised. 01.01.01 Gregory Crinum 29 Crinum East - Improving the ABM System Improving the conveyor system: Add additional jiffy drives to improve belt reliability and resolve belt slip issues. Looking at improving the belt clipping station. Reducing panel extension times. 01.01.01 Gregory Crinum 30 Crinum East - Improving the ABM System MCS POP project: Mining Consultancy Services have a large amount of experience and expertise in business analysis, mine design, mining operations and people, productivity optimisation and equipment design and selection. Currently responsible for the performance and monitoring of 60 continuous miner units world wide. Currently 2 months into the 9 month POP project. 01.01.01 Gregory Crinum 31 Crinum East - Improving the ABM System The 9 month process can be broken up into 2 phases and 4 modules: Phase 1: Evaluate to current system and mining process to establish production objectives and functional KPI’s (9 weeks). Phase 2: Implementation of the POP process, implementation of initiatives and coaching and mentoring role (25 weeks). Crucial to the success of the project is onboard monitoring on the miner to allow monitoring and evaluation of initiatives. 01.01.01 Gregory Crinum 32 Crinum East - Improving the ABM System The POP process. 01.01.01 Gregory Crinum 33 01.01.01 COM016 0% COM017 COM018 Cutter Roof Bolter Power Distribution Delay Type Electrical Control Wait on Tradesman No Labour Hydraulics/Pneumatics COM019 Ventilation Conveying Flitting Break Offs/Turns Belts - Panel Section Prep Service Extn / Retn Crib Travel Safety/Training Meeting Delay % Crinum East - Improving the ABM System Analysis of downtime for each miner. Comparison Of Continuous Miners 30% 25% 20% 15% 10% 5% Gregory Crinum 34 Crinum East - Improving the ABM System After 2 months of the POP project, a number of areas of opportunity have been identified: 01.01.01 Reducing process delays. Optimising cycle times. Changing mining dimensions. Modify 6/2 bolting pattern to a 4/4 bolting pattern. Evaluate use of Stamler feeder breaker on front of boot end. Reducing panel extension times. Planning process. Panel standards. Gregory Crinum 35 Crinum East - Improving the ABM System Presentations have been made to every crew detailing the development data over the last year. A workshop involving the development workforce has been held to provide involvement and ownership of the process. Currently designing Crinum specific reports that will be automatically generated from the onboard monitoring. This will use traffic light colour system and benchmark their performance against specific targets. 01.01.01 Gregory Crinum 36 Crinum East - Targets for the next Year We have completed MG17 and due to commence MG19. Our Goals over the following year are: Develop MG19 with high panel standards. Achieve a minimum of 10% production improvement through the POP project with MCS. Consistently achieve 4.0m per op hour. Achieve a minimum of 46 op hours per week and work towards achieving 67 op hours per week. 01.01.01 Gregory Crinum 37