Transcript LRFD Now!

LRFD Now!
Andy Zickler
VDOT Structure and Bridge
Division
Central Office
April 10, 2006
[email protected]
Status Update on LRFD
Implementation
•
•
•
•
•
General Review of Implementation plan
Training Plan
Implementation Dates to Remember
Review of Frequently Asked Questions
Information Exchange
LRFD –
Implementation Review
LRFD transition is historic
– LRFD 1st mandatory change in design
philosophy in bridge design in USA
– ASD has been around since 1st AASHO
Specification (1931)
– LFD introduced in 1970’s but never
mandatory for design across nation
– LRFD mandated by FHWA for new bridge
design beginning October 1, 2007
LRFD –
Implementation Review
Prepare!
– Prepare for
Training
– Prepare for
Design
– Prepare for
Construction
Train!
– Train for design
– Train for
Specifications
– Train for
Construction
Implement!
– Issue new AASHTO
Documentation
– Issue new VDOT
Documentation
DESIGN!!!!
Follow UP!
– Provide Lessons
Learned
– Check for other support
needs
LRFD Implementation
PREPARE!
An LRFD Team has been named to
design 2 complete bridges using
LRFD
Team Members
–
–
–
–
–
Andy Zickler (Contact Person)
Tony Barati
Prasad Nallapaneni
John Schuler
Bryan Silvis
LRFD Implementation
PREPARE!
LRFD team will be generating
complete design computations
on 2 bridges
– One continuous steel bridge
– One continuous P/S bulb tee Bridge
During the design process, team
members will be reviewing all
parts of the puzzle that make
up the contract drawings and
specifications
LRFD Implementation
PREPARE!
VDOT contract elements will be
reviewed for conformance with
LRFD
– Review will be 3 parts
• Not impacted
• Review complete with final recommendation
for action
• Review incomplete with preliminary
assessment for action PLUS recommendation
for further review.
LRFD Implementation
TRAIN!
Train for Design
– 3 Introductory 1 day training sessions
• Structural Steel – Complete!
• P/S Concrete Design – Complete!
• Foundations – July, 2007
– 3 week long training Sessions
(VDOT Only)
• Superstructure Design – Taught by NHI
• Software training – Taught by VDOT personnel
• Substructure and Retaining Structures – Taught by NHI
LRFD Implementation
TRAIN!
Train for Specifications
– Structure of this training not
determined, because extent of impact
has not been determined.
– Minimum will be self study. Changes
to specifications will highlighted, and
points of contact for questions will be
distributed
– Consultants will be advised of any
VDOT Guidelines, preferences, etc.
LRFD Implementation
TRAIN!
Train for Construction
– Structure of this training not determined,
because extent of impact has not been
determined.
– New specifications explicitly place
responsibility for some items on contractor
and outline specific requirements for
submittal it is likely that we will see more
P.E. stamped submittals for things like
erection, deck placement, shipping.
Learning what is required will be part of
training at some point.
– Consultants, Contractors, VTCA, etc. will be
kept abreast of developments
LRFD Implementation
IMPLEMENT!
Issue:
– VDOT Modifications to LRFD Spec and/or
Design Guidelines
– Sample Problems and Design Aids
– Revisions to VDOT Road and Bridge Standard
Specifications
(as necessary, if necessary)
– Revised Standards, S&B Standard Drawings
(as necessary, if necessary)
LRFD Implementation
DESIGN!!!!
April 2, 2007
– Begin “all” designs using LRFD
• Some widenings/rehabs may be excluded.
* Definition of “all” to be determined based on
what team finds and LRFD plans may change
LRFD Implementation
Follow Up!
LRFD Team will not be
disbanded on April 2, 2007
– LRFD Team will continue on for at
least several months maybe until
October, 2008
– LRFD team will help evaluate whether
follow up class training will be
required and will help establish
parameters
LRFD Training
in Detail
3 days of Introductory Training
(19.5 contact hours total)
– Structural Steel – Complete!
– P/S Concrete – Complete!
– Foundations (July 11, July 12)
Classes will be lecture format
Classes will include consultant participants
Classes will only be offered on the dates shown, no
repeats.
Classes will be in Richmond
LRFD Training
in Detail -- Software
Examples to be developed (FIRM)
–
–
–
–
–
–
–
3 span straight steel plate girder
4 span bulb-tee, continuous for LL
Concrete Multi-column pier (Rigid Frame Pier)
Concrete Hammerhead pier
Stub Abutment
Full Height Abutment
Wingwalls
Substructures will include piles and spread
footings
LRFD Training
in Detail -- Software
Additional Examples (TENTATIVE)
– Superstructure
• Rolled beam
• Continuous Conc. Slab
– LAMPAD, Tooth
– Substructure
• Integral Abutment
• MSE walls
• Pile Bent
LRFD Training
in Detail -- Software
Additional Examples (TENTATIVE)
– Others under consideration
• Timber deck
• Timber superstructure
• Timber bents (pier and abutment)
– Suggestions?
LRFD -Dates to Remember
Dates through June, 2006
– March, 2006 Two one day seminars for steel
superstructures
– April, 2006 Two one day seminars for concrete
super
– 5/26 Issue preliminary report on LRFD Impacts
to VDOT Modifications to AASHTO
– 6/30 Complete 2 design projects
– 6/30 Issue final report on LRFD Impacts to
VDOT Modifications to AASHTO
– 6/30 Issue preliminary report on LRFD Impacts
to other VDOT Documents
LRFD -Dates to Remember
Dates in July, 2006
– Issue LRFD Specs and Interims to engineers
– 7/11 NHI one day seminar for
substructure/foundations – Session 1
– 7/12 NHI one day seminar for
substructure/foundations – Session 2
– 7/28 Issue final report on LRFD impacts to
VDOT documents
LRFD -Dates to Remember
Dates in August thru December, 2006
– 8/1 Issue preliminary Design Documentation on 2 design
projects
– 8/1-10/1 Release/review VDOT AASHTO Design Guides
– 12/1 release 1st Ed. VDOT AASHTO LRFD Guides
– Determine if additional training is required
LRFD -Dates to Remember
Dates in January thru April, 2007
– 3/19 Planned LRFD Training complete. Evaluate whether
additional training required. Develop plan if required
– 3/30 Final reports on Standards/Office Practice
– 4/2 Implement LRFD on all new bridge projects
LRFD -Dates to Remember
Dates in May, 2007 and BEYOND
– 5/25 Final report on VDOT specifications/special
provisions
– Support Software…
– Provide support for implementation hiccups
LRFD -Frequently Asked Questions
• When is VDOT switching to LRFD?
• What happens after the LRFD training?
• When will I get my VDOT documents modified for
LRFD Spec?
• Will I have to design my next bridge in LRFD?
• After the VDOT training, then what?
Written Answers will be posted on Structure and Bridge LRFD page
LRFD -Frequently Asked Questions (Con’t)
• Who will answer LRFD questions when we start
designing?
• Where can I go to get more information on LRFD?
Written Answers will be posted on Structure and Bridge LRFD page
LRFD –
Information Exchange
Keeping you informed – 3 ways
– Structure and Bridge Division’s LRFD page at
www.virginiadot.org
– Handouts from training, supplemental documentation
• Have you tried it, does the LRFD site meet your needs?
– Emails
• Too many?, not enough?, right info?, wrong info?
– VTCA
• Updates to Executive Leadership
• Coordination of consultant NHI Courses
LRFD –
Information Exchange
Getting information to the LRFD Team
– Do you know how to get to us?
• Phone (George Clendenin, Julius Volgyi, Andy Zickler)
• Email (George Clendenin, Julius Volgyi, Andy Zickler)
• Thru VTCA
– Does this work for you?
• Do you need a better way?
• Do you have a better way?
LRFD –
Open Questions
What else do you want to know?
– If we don’t know today when do you have to
have an answer?
– What did we leave out?
What information do you need to plan
for your business?
– When do you need it?
– What form should it be in?
Anything else?
LRFD Now!
THANKS!
Andy Zickler (804) 371-2776
VDOT Structure and Bridge Division
Central Office
April 10, 2006
[email protected]