Report on EU Commission on Measures to achieve Compliance

Download Report

Transcript Report on EU Commission on Measures to achieve Compliance

Individual County Reports to
EU Commission
on measures to achieve compliance with
the
Drinking Water Directive
Presentation to:
Seminar on Progress of Rural Water Programme 2006
Shamrock Lodge Hotel Athlone
8h June 2006
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY REPORTS
 Sources & Ownership
– Taken over by Local Authority
– Metered supply from public scheme
– Private source
 Microbiological Compliance of Schemes
 Treatment Solutions Identified by L.A.
 Realisation of Identified Treatment Solutions
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CARLOW REPORT
Sources & Ownership
County Carlow
Sources and Ownership (11 Schemes)
6
5
5
No of Schemes
5
4
3
2
1
1
0
PWS
Public GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CARLOW REPORT
Microbiological Results in Compliance
County Carlow
Microbiological Results in Com pliance (All Schem es: 11)
Yes
36% (4)
No
64% (7)
Yes
No
County Carlow
Microbiological Results in Compliance (All Schemes: Domestic
Connections = 854)
Yes
26% (226)
No
74% (628)
Yes
No
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CARLOW REPORT
Upgrade Solutions Identified
County Carlow
Upgrade Solutions Identified (All Schemes:11)
DBO Treatment
27% (3)
Connect to PWS
9% (1)
Public Source
55% (6)
Disinfection/
Sterilisation
9% (1)
DBO Treatment
Disinfection/ Sterilisation
Connect to Public Supply
Public Source
County Carlow
Upgrade Solutions Identified (Domestic Connections = 854)
Public Source
35% (295)
Disinfection/
Sterilisation
1% (8)
Connect to Public
Supply
4% (38)
DBO Treatment
Disinfection/ Sterilisation
DBO Treatment
60% (513)
Connect to Public Supply
Public Source
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CARLOW REPORT
Status of Identified Solutions
County Carlow
Current Project Status (All 11 Schemes)
Underway
36% (4)
Complete
46% (5)
Planning
18% (2)
Complete
Planning
Underway
County Carlow
Current Project Status (All Schemes: Domestic Connections =
854)
Complete
31% (265)
Underw ay
64% (543)
Complete
Planning
5% (46)
Planning
GALWAY DBO STEERING GROUP – 21rd February 2006
Underway
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CAVAN REPORT
Sources & Ownership
County Cavan
Sources and Ownership (28 Schemes)
30
28
No of Schemes
25
20
15
10
5
0
Private GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CAVAN REPORT
Microbiological Results in Compliance
County Cavan
Microbiological Results in Compliance (All Schemes:28)
Yes
43% (12)
No
57% (16)
County Cavan
Microbiological Results in Compliance (All Schemes: 9,160
Domestic Connections)
Yes
36% (3,276)
No
64% (5,884)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CAVAN REPORT
Upgrade Solutions Identified (Schemes/Domestic Connections)
County Cavan
Upgrade Solutions Identified (All Schemes:28)
(9,160 Domestic Connections)
DBO Treatment
100% (28)
DBO Treatment
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CAVAN REPORT
Status of Identified Solutions
County Cavan
Current Project Status (All Schemes:28)
Underway
46% (13)
Complete
54% (15)
Complete
Underway
County Cavan
Current Project Status (All Schemes: 9,160 Domestic Connections)
Complete
37% (3,413)
Underway
63% (5,747)
Complete
Underway
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CLARE REPORT
Sources & Ownership
County Clare
Sources and Ow nershi (13 Schem es)
14
12
No of Schemes
12
10
8
6
4
2
1
0
Public GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CLARE REPORT
Microbiological Results in Compliance
County Clare
Microbiological Results in Compliance (All Schemes:13)
Yes
15% (2)
No
85% (11)
County Clare
Microbiological Results in Compliance (All Schemes: 3,516
Domestic Connections)
Yes
49%(1,725)
No
51%(1,791)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CLARE REPORT
Upgrade Solutions Identified
County Clare
Upgrade Solutions Identified (All Schem es, 13)
Public Source
8% (1)
Disinfection/
Sterilisation
23% (3)
DBO Treatment
54% (7)
Connect to Public
Supply
15% (2)
DBO Treatment
Connect to Public Supply
Disinfection/ Sterilisation
Public Source
County Clare
Upgrade Solutions Identified (All Schem es: No. of Dom estic
Connections: 3,516)
Disinfection/
Sterilisation
2% (83)
Connect to Public
Supply
9% (315)
Public Source
5% (170)
DBO Treatment
84% (2,948)
DBO Treatment
Connect to Public Supply
Disinfection/ Sterilisation
Public Source
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CLARE REPORT
Status of Identified Solutions
County Clare
Current Project Status (All Schem es: 13)
Complete
8% (1)
Underw ay
38% (5)
Planning
54% (7)
Complete
Planning
Underw ay
County Clare
Current Project Status (All Schem es: 3,516 Dom estic
Connections)
Complete
5% (170)
Planning
9% (323)
Underw ay
86% (3,023)
Complete
Planning
GALWAY DBO STEERING GROUP – 21rd February 2006
Underw ay
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CORK REPORT
Sources & Ownership
County Cork
Sources and Ownership (33 Schemes)
28
30
No of Schemes
25
20
15
10
4
5
1
0
PWS
Public GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CORK REPORT
Microbiological Results in Compliance
County Cork
Microbiological Results in Compliance (All Schemes, 33)
No
42% (14)
Yes
58% (19)
County Cork
Microbiological Results in Compliance (All Schemes: 1,237 Domestic
Connections)
No
48% (593)
Yes
52% (644)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CORK REPORT
Upgrade Solutions Identified
County Cork
Upgrade Solutions Identified (All Schemes, 33)
Non-DBO
Treatment
27% (9)
Connect to
public supply
6% (2)
Disinfection/
Sterilisation
31% (10)
Takeover
21% (7)
Public Source
15% (5)
Non-DBO Treatment
Takeover
Disinfection/ Sterilisation
Connect to public supply
Public Source
County Cork
Upgrade Solutions Identified (All Schemes: 1,237 Domestic
Connections)
Disinfection/
Sterilisation
12% (154)
Non-DBO
Treatment
32% (389)
Connect to
public supply
3% (36)
Takeover
26% (320)
Public Source
27% (338)
Non-DBO Treatment
Takeover
Disinfection/ Sterilisation
Connect to public supply
Public Source
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY CORK REPORT
Status of Identified Solutions
County Cork
Current Project Status (All Schemes, 33)
Complete
21% (7)
Underw ay
58% (19)
Planning
21% (7)
Complete
Planning
Underway
County Cork
Current Project Status (All Schemes: 1,237 Domestic Connections)
Complete
18% (218)
Planning
12% (146)
Underw ay
70% (873)
Complete
Planning
Underway
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY DONEGAL REPORT
Sources & Ownership
County Donegal
Sources and Ownership (36 Schemes)
25
20
No of Schemes
20
15
10
9
7
5
0
PWS
Public GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY DONEGAL REPORT
Microbiological Results in Compliance
County Donegal
Microbiological Results in Compliance (All Schemes,36)
Yes
44% (16)
No
56% (20)
County Donegal
Microbiological Results in Com pliance (All Schem es: 2,726
Dom estic Connections)
No
31% (854)
Yes
69% (1,872)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY DONEGAL REPORT
Upgrade Solutions Identified
County Donegal
Upgrade Solutions Identified (All Schem es, 36)
Non-DBO
Treatment
6% (2)
Disinfection/
Sterilisation
3% (1)
Connect to Public
Supply
47% (17)
Public Source
44% (16)
Non-DBO Treatment
Public Source
Connect to Public Supply
Disinfection/Sterilisation
County Donegal
Upgrade Solutions Identified (All Schemes: 2,726 Domestic
Connections)
Disinfection/
Sterilisation
3% (83)
Non-DBO
Treatment
8% (222)
Connect to
Public Supply
28% (759)
Public Source
61% (1662)
Non-DBO Treatment
Public Source
Connect to Public Supply
Disinfection/Sterilisation
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY DONEGAL REPORT
Status of Identified Solutions (Schemes)
County Donegal
Current Project Status (All Schemes, 26)
Underw ay
6% (2)
Complete
28% (10)
Planning
66% (24)
Complete
Planning
Underway
County Donegal
Current Project Status (All Schemes: 2,726 Domestic Connections)
Underw ay
6% (169)
Complete
30% (817)
Planning
64% (1,740)
Complete
Planning
Underway
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY GALWAY REPORT
Sources & Ownership
No of Schemes
County Galw ay
Sources and Ow nership
All Schemes (178)
140
120
100
80
60
40
20
0
127
39
12
PWS
Public GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY GALWAY REPORT
Microbiological Results in Compliance (Schemes)
County Galway
Microbiological Results in Compliance (All 178 Schemes)
No
33% (59)
Yes
67% (119)
County Galway
Microbiological Results in Com pliance (Dom estic Connections =
21,007)
No
19% (4,018)
Yes
81% (16,989)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY GALWAY REPORT
Upgrade Solutions Identified
County Galway
Upgrade Solutions Identified (All Schemes: 178)
Connect to Public
Supply
14% (25)
Takeover by Local
Authority
13% (23)
Non DBO Treatment
1% (2)
Disinfection/
Sterilisation
4% (7)
DBO Treatment
39% (70)
Public Source
29% (51)
DBO Treatment
Connect to Public Supply
Disinfection/Sterilisation
Non DBO Treatment
Takeover by Local Authority
Public Source
County Galway
Upgrade Solutions Identified (Domestic Connections = 21,007)
Connect to Public
Supply
8% (1,576)
Takeover by Local
Authority
10% (2,167)
Disinfection/
Sterilisation
4% (472)
Non DBO Treatment
1% (109)
Public Source
40% (8,541)
DBO Treatment
39% (8,142)
DBO Treatment
Connect to Public Supply
Disinfection/Sterilisation
Non DBO Treatment
Takeover by Local Authority
Public Source
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY GALWAY REPORT
Status of Identified Solutions
County Galway
Current Project Status (All 178 Schemes)
Underway
43% (76)
Complete
24% (43)
Planning
33% (59)
Complete
Planning
Underway
County Galway
Current Project Status (Domestic Connections = 21,007)
Underway
39% (8,285)
Complete
42% (8,631)
Planning
19% (4,091)
Complete
Planning
Underway
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY KERRY REPORT
Sources & Ownership
County Kerry
Sources and Ownership (12 Schemes)
12
11
No of Schemes
10
8
6
4
2
1
0
Public GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY KERRY REPORT
Microbiological Results (Schemes/Domestic Connections)
County Kerry
Microbiological Results in Compliance (All Schemes,12)
(707 Domestic Connections)
No
0%
Yes
100%
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY KERRY REPORT
Upgrade Solutions Identified
County Kerry
Upgrade Solutions Identified (All Schemes, 12)
Non-DBO Treatment
42% (5)
Public Source
8% (1)
Disinfection/
Sterilisation
10% (2)
Connect to public
supply
33% (4)
Non-DBO Treatment
Disinfection/Sterilisation
Connect to public supply
Public Source
County Kerry
Upgrade Solutions Identified (Domestic Connections = 707))
Public Source
16% (111)
Non-DBO
Treatment
17% (122)
Connect to public
supply
47% (331)
Disinfection/
Sterilisation
10% (143)
Non-DBO Treatment
Disinfection/Sterilisation
Connect to public supply
Public Source
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY KERRY REPORT
Status of Identified Solutions
County Kerry
Current Project Status (All Schemes, 12)
Complete
17% (2)
Underw ay
33% (4)
Planning
50% (6)
Complete
Planning
Underway
County Kerry
Current Project Status (All Schemes: Domestic Connections = 707)
Underw ay
26% (184)
Complete
17% (117)
Planning
57% (406)
Complete
Planning
Underway
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY KILDARE REPORT
Sources & Ownership
County Kildare
Sources and Ownership (5 Schemes)
6
5
No of Schemes
5
4
3
2
1
0
Private GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY KILDARE REPORT
Microbiological Results (Schemes/Domestic Connections)
County Kildare
Microbiological Results in Com pliance (All Schem es,5)
(607 Dom estic Connections)
No
0%
Yes
100%
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY KILDARE REPORT
Upgrade Solutions Identified
County Kildare
Upgrade Solutions Identified (All Schemes, 5)
DBO Treatment
20% (1)
Disinfection/
Sterilisation
40% (2)
Connect to Public
Supply
40% (2)
DBO Treatment
Connect to Public Supply
Disinfection/Sterilisation
County Kildare
Upgrade Solutions Identified (Domestic Connections = 607)
DBO Treatment
26% (160)
Disinfection/
Sterilisation
14% (84)
DBO Treatment
Connect to Public Supply
Connect to Public
Supply
60% (363)
Disinfection/ Sterilisation
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY KILDARE REPORT
Status of Identified Solutions
County Kildare
Current Project Status (All Schemes,5)
Complete
40% (2)
Underw ay
20% (1)
Planning
40% (2)
Complete
Planning
Underw ay
County Kildare
Current Project Status (Domestic Connections = 607)
Complete
62% (376)
Underway
4% (23)
Planning
34% (208)
Complete
Planning
GALWAY DBO STEERING GROUP – 21rd February 2006
Underw ay
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY KILKENNY REPORT
Sources & Ownership
County Kilkenny
Sources and Ownership (25 Schemes)
25
21
No of Schemes
20
15
10
5
2
2
0
Public GWS
Private GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
PWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY KILKENNY REPORT
Microbiological Results in Compliance
County Kilkenny
Microbiologicall Results in Compliance (All Schemes:25)
No
8% (2)
Yes
92% (23)
County Kilkenny
Microbiological Results in Compliance (Domestic Connections =
3,385)
No
3% (91)
Yes
97% (3,294)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY KILKENNY REPORT
Upgrade Solutions Identified
County Kilkenny
Upgrade Solutions Identified (All Schemes:25)
Public Source
16% (4)
DBO Treatment
16% (4)
Disinfection/
Sterilisation
60% (15)
Takeover by
Local Authority
8% (2)
DBO Treatment
Disinfection/Sterilisation
Takeover by Local Authority
Public Source
County Kilkenny
Upgrade Solutions Identified (Domestic Connections = 3,385)
DBO Treatment
5% (177)
Takeover by Local
Authority
1% (45)
Public Source
72% (2,420)
Disinfection/
Sterilisation
22% (743)
DBO Treatment
Disinfection/ Sterilisation
Takeover by Local Authority
Public Source
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY KILKENNY REPORT
Status of Identified Solutions
County Kilkenny
Current Project Status (All Schemes:25)
Underw ay
20% (5)
Complete
80% (20)
Complete
Underway
County Kilkenny
Current Project Status (Domestic Connections = 3,385)
Underway
4% (183)
Complete
95% (3,202)
Complete
Underway
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LAOIS REPORT
Sources & Ownership
County Laois
Sources and Ow nership (13 Schem es)
12
11
No of Schemes
10
8
6
4
2
1
1
PWS
Public GWS
0
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LAOIS REPORT
Microbiological Results in Compliance
County Laois
Microbiological Results in Com pliance (All Schem es:13)
No
54% (7)
Yes
46% (6)
County Laois
Microbiological Results in Compliance (Domestic Connections = 1,846)
No
43% (796)
Yes
57% (1,050)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LAOIS REPORT
Upgrade Solutions Identified
County Laois
Upgrade Solutions Identified (All Schemes:13)
Public Source
15% (2)
DBO Treatment
24% (3)
Disinfection/
Sterilisation
23% (3)
Connect to Public
Supply
23% (3)
Takeover by Local
Authority
15% (2)
DBO Treatment
Connect to Public Supply
Disinfection/ Sterilisation
Public Source
Takeover by Local Authority
County Laois
Upgrade Solutions Identified (All Schemes:Domestic Connections =1,846 )
Public Source
4% (75)
Disinfection/
Sterilisation
30% (562)
DBO Treatment
33% (612)
Takeover by Local
Authority
26% (476)
Connect to Public
Supply
7% (121)
DBO Treatment
Connect to Public Supply
Disinfection/ Sterilisation
Public Source
GALWAY DBO STEERING GROUP – 21rd February 2006
Takeover by Local Authority
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LAOIS REPORT
Status of Identified Solutions
County Laois
Current Project Status (All Schemes:13)
Underw ay
38% (5)
Planning
31% (4)
Complete
31% (4)
Complete
Planning
Underw ay
County Laois
Current Project Status (All Schemes: Domestic Connections = 1,846 )
Underw ay
59% (1,085)
Complete
32% (587)
Planning
9% (174)
Complete
Planning
GALWAY DBO STEERING GROUP – 21rd February 2006
Underw ay
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LEITRIM REPORT
Sources & Ownership
County Leitrim
Sources and Ownership
15
16
13
No of Schemes
14
12
10
8
6
4
2
1
0
PWS
Public GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LEITRIM REPORT
Microbiological Results in Compliance
County Leitrim
Microbiological Results in Com pliance (All Schem es: 29)
No
76% (22)
Yes
24% (7)
County Leitrim
Microbiological Results in Com pliance (Dom estic Connections = 2,488)
No
79% (1,956)
Yes
21% (532)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LEITRIM REPORT
Upgrade Solutions Identified
County Leitrim
Upgrade Solutions Identified (All 29 Schemes)
Non DBO
Treatment
3% (1)
Connect to
Public Supply
28% (8)
DBO Treatment
7% (2)
Takeover by
Local Authority
10% (3)
Disinfection/
Sterilisation
3% (1)
Public Source
49% (14)
DBO Treatment
Connect to Public Supply
Disinfection/Sterilisation
Non DBO Treatment
Takeover by Local Authority
Public Source
County Leitrim
Upgrade Solutions Identified (Domestic Connections = 2,488)
Non DBO
Treatment
3% (67)
Connect to Public
Supply
36% (905)
DBO Treatment
5% (132)
Takeover by
Local Authority
3% (65)
Disinfection/
Sterilisation
3% (250)
Public Source
43% (1,069)
DBO Treatment
Connect to Public Supply
Disinfection/Sterilisation
Non DBO Treatment
Takeover by Local Authority
Public Source
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LEITRIM REPORT
Status of Identified Solutions
County Leitrim
Current Project Status (All Schemes:29)
Planning
34% (10)
Underw ay
28% (8)
Complete
38% (11)
Complete
Planning
Underw ay
County Leitrim
Current Project Status (Domestic Connections = 2,488)
Planning
37% (930)
Underw ay
29% (723)
Complete
34% (835)
Complete
Planning
GALWAY DBO STEERING GROUP – 21rd February 2006
Underw ay
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LIMERICK REPORT
Sources & Ownership
County Limerick
Sources and Ownership (57 Schemes)
50
43
45
No of Schemes
40
35
30
25
20
15
10
6
8
5
0
PWS
Public GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LIMERICK REPORT
Microbiological Results in Compliance
County Limerick
Microbiological Reults in Com pliance (All Schem es:57)
No
60% (34)
Yes
40% (23)
County Limerick
Microbiological Reults in Com pliance (Dom estic
Connections: 5,019 )
No
50% (2498)
Yes
50% (2521)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LIMERICK REPORT
Upgrade Solutions Identified
County Limerick
Upgrade Solutions Identified (All Schem es:57)
Disinfection/
Sterilisation
11% (6)
Public Source
25% (14)
Takeover by Local
Authority
14% (8)
Connect to Public
Supply
18% (10)
DBO Treatment
Takeover by Local Authority
Public Source
DBO Treatment
32% (19)
Connect to Public Supply
Disinfection/Sterilisation
County Limerick
Upgrade Solutions Identified (Domestic Connections: 5,019)
Takeover by Local
Authority
9% (442)
Disinfection/
Sterilisation
11% (472)
Public Source
23% (1168)
Connect to Public
Supply
6% (303)
DBO Treatment
53% (2634)
DBO Treatment
Takeover by Local Authority
Public Source
Connect to Public Supply
Disinfection/Sterilisation
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LIMERICK REPORT
Status of Identified Solutions
County Limerick
Current Project Status (All Schemes: 57)
Underw ay
42% (24)
Complete
30% (17)
Planning
28% (16)
Complete
Planning
Underw ay
County Limerick
Current Project Status (Domestic Connections (5,019))
Underw ay
61% (3061)
Complete
26% (1294)
Planning
13% (664)
Complete
Planning
Underw ay
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LONGFORD REPORT
Sources & Ownership
County Longford
Sources and Ownership (6 Schemes )
6
5
No of Schemes
5
4
3
2
1
1
0
Public GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LONGFORD REPORT
Microbiological Results (Schemes/Domestic Connections)
County Longford
Microbiological Results in Compliance (All Schemes: 6)
(332 Domestic Connections)
Yes
0%
No
100%
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LONGFORD REPORT
Upgrade Solutions Identified
County Longford
Upgrade Solutions Identified (All Schemes: 6)
Public Source
17% (1)
Connect to
Public Supply
50% (3)
Disinfection/
Sterilisation
33% (2)
Connect to Public Supply
Disinfection/Sterilisation
Public Source
County Longford
Upgrade Solutions Identified (Domestic Connections = 332)
Public Source
5% (15)
Disinfection/
Sterilisation
26% (87)
Connect to
Public Supply
69% (230)
Connect to Public Supply
Disinfection/ Sterilisation
GALWAY DBO STEERING GROUP – 21rd February 2006
Public Source
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LONGFORD REPORT
Status of Identified Solutions
County Longford
Current Project Status (All Schemes: 6)
Complete
17% (1)
Planning
17% (1)
Underway
66% (4)
Complete
Planning
Underw ay
County Longford
Current Project Status (Domestic Connections = 332)
Complete
14% (47)
Planning
12% (40)
Underway
74% (245)
Complete
Planning
Underw ay
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LOUTH REPORT
Sources & Ownership
County Louth
Sources and Ow nership (9 Schem es)
9
8
8
No of Schemes
7
6
5
4
3
2
1
1
0
0
PWS
Public GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LOUTH REPORT
Microbiological Results in Compliance
County Louth
Microbiological Results in Compliance (All Schemes: 9)
No
22% (2)
Yes
78% (7)
County Louth
Microbiological Results in Compliance (Domestic Connections = 890)
No
7% (58)
Yes
93% (832)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LOUTH REPORT
Upgrade Solutions Identified
County Louth
Upgrade Solutions Identified (All Schemes: 9)
Connect to PWS
9% (1)
Disinfection/
Sterilisation
89% (8)
Disinfection/ Sterilisation
Public Source
County Louth
Upgrade Solutions Identified (Domestic Connections = 890)
Public Source
5% (46)
Disinfection/
Sterilisation
95% (844)
Disinfection/ Sterilisation
GALWAY DBO STEERING GROUP – 21rd February 2006
Public Source
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY LOUTH REPORT
Status of Identified Solutions
County Louth
Current Project Status (All Schemes: 9)
Underway
11% (1)
Planning
11% (1)
Complete
78% (7)
Complete
Planning
Underway
County Louth
Current Project Status (Domestic Connections = 890)
Underway
5% (44)
Planning
2% (14)
Complete
93% (832)
Complete
Planning
Underway
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY MAYO REPORT
Sources & Ownership
County Mayo
Sources and Ownership (111 Schemes)
120
96
No of Schemes
100
80
60
40
20
5
10
0
PWS
Public GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY MAYO REPORT
Microbiological Results in Compliance
County Mayo
Microbiological Results in Com pliance (All Schem es: 111)
Yes
23% (25)
No
77% (86)
County Mayo
Microbiological Results in Compliance (All Schemes: Domestic
Connections = 14,035)
Yes
26% (3,618)
No
74% (10,417)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY MAYO REPORT
Upgrade Solutions Identified
County Mayo
Upgrade Solutions Identified (All Schem es: 111)
Public Source
14% (15)
Disinfection/
Sterilisation
DBO Treatment
8% (9)
37% (42)
Takeover by Local
Authority
4% (4)
Connect to Public
Supply
37% (41)
DBO Treatment
Takeover by Local Authority
Public Source
Connect to Public Supply
Disinfection/ Sterilisation
County Mayo
Upgrade Solutions Identified (All schemes: Domestic Connections
= 14,035)
Connect to
Public Supply
22% (3,080)
Takeover by
Local Authority
3% (396)
Disinfection/
Sterilisation
12% (1,656)
Public Source
12% (1,749)
DBO Treatment
51% (7,154)
DBO Treatment
Takeover by Local Authority
Public Source
Connect to Public Supply
Disinfection/ Sterilisation
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY MAYO REPORT
Status of Identified Solutions
County Mayo
Current Project Status (All Schemes:111)
Complete
17% (19)
Planning
32% (35)
Underway
51% (57)
Complete
Planning
Underw ay
County Mayo
Current Project Status (All schemes: Domestic Connections =
14,035)
Complete
20% (2,812)
Planning
19% (2,615)
Underway
61% (8,608)
Complete
Planning
GALWAY DBO STEERING GROUP – 21rd February 2006
Underw ay
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY MEATH REPORT
Sources & Ownership
County Meath
Sources and Ownership (5 Schemes)
3.5
3
No of Schemes
3
2.5
2
2
1.5
1
0.5
0
PWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY MEATH REPORT
Microbiological Results in Compliance
County Meath
Microbiological Results in Com pliance (All
Schem es: 5)
No
20% (1)
Yes
80% (4)
County Meath
Microbiologicall Results in Com pliance (Dom estic
Connections: 684)
No
26%
(180)
Yes
74%
(504)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY MEATH REPORT
Upgrade Solutions Identified
County Meath
Upgrade Solutions Identified (All Schemes: 5)
DBO Treatment
20% (1)
Disinfection/
Sterilisation
20% (1)
Public Source
60% (3)
DBO Treatment
Disinfection/Sterilisation
Public Source
County Meath
Upgrade Solutions Identified (Domestic Connections: 684)
DBO Treatment
26% (180)
Public Source
40% (271)
Disinfection/
Sterilisation
20% (233)
DBO Treatment
Disinfection/Sterilisation
GALWAY DBO STEERING GROUP – 21rd February 2006
Public Source
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY MEATH REPORT
Status of Identified Solutions
County Meath
Current Project Status (All Schemes: 5)
(684 Domestic Connections)
Complete
100%
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY MONAGHAN REPORT
Sources & Ownership
County Monaghan
Sources and Ow nership (13 Schem es)
14
12
No of Schemes
12
10
8
6
4
2
1
0
PWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY MONAGHAN REPORT
Microbiological Results in Compliance
County Monaghan
Microbiological Results in Compliance (All Schemes: 13)
Yes
54% (7)
No
46% (6)
County Monaghan
Microbiological Results in Compliance (Domestic Connections: 7,500)
Yes
36% (2697)
No
64% (4803)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY MONAGHAN REPORT
Upgrade Solutions Identified
County Monaghan
Upgrade Solutions Identified (All Schem es: 13)
Public Source
8% (1)
Non DBO
Treatment
8% (1)
DBO
Treatment
84% (11)
DBO Treatment
Non DBO Treatment
Public Source
County Monaghan
Upgrade Solutions Identified (Dom estic Connections: 7,500)
Public Source
1% (100)
Non DBO
Treatment
9% (694)
DBO Treatment
90% (6,706)
DBO Treatment
Non DBO Treatment
GALWAY DBO STEERING GROUP – 21rd February 2006
Public Source
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY MONAGHAN REPORT
Status of Identified Solutions
County Monaghan
Current Project Status (All Schemes: 13)
Underway
8% (1)
Complete
92% (12)
Complete
Underway
County Monaghan
Current Project Status (Domestic Connections: 7,500)
Underway
16% (1,185)
Complete
84% (6,315)
Complete
Underway
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
NORTH TIPPERARY REPORT
Sources & Ownership
North Tipperary
Sources and Ow nership (41 Schem es)
45
40
40
No of Schemes
35
30
25
20
15
10
5
1
0
PWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
NORTH TIPPERARY REPORT
Microbiological Results in Compliance
North Tipperary
Microbiological Results in Com pliance (All Schem es: 41)
No
2% (1)
Yes
98% (40)
North Tipperary
Microbiological Results in Com pliance (Dom estic
Connections: 1,995)
No
1% (16)
Yes
99% (1979)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
NORTH TIPPERARY REPORT
Upgrade Solutions Identified
North Tipperary
Upgrade Solutions Identified (All Schem es: 41)
Public Source
2% (1)
Takeover by
Local Authority
2% (1)
Disinfection/
Sterilisation
96% (39)
Takeover by Local Authority
Public Source
Disinfection/Sterilisation
North Tipperary
Upgrade Solutions Identified (Dom estic Connections: 1,995)
Public Source
1% (16)
Takeover by
Local Authority
1% (15)
Disinfection/
Sterilisation
98% (1,964)
Takeover by Local Authority
Public Source
GALWAY DBO STEERING GROUP – 21rd February 2006
Disinfection/Sterilisation
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
NORTH TIPPERARY REPORT
Status of Identified Solutions
North Tipperary
Current Project Status (All Schemes: 41)
Planning
2% (1)
Underway
2% (1)
Complete
96% (39)
Complete
Planning
Underway
North Tipperary
Current Project Status (Domestic Connections: 1,995)
Planning
1% (18)
Underway
1% (15)
Complete
98% (1,962)
Complete
Planning
Underway
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY OFFALY REPORT
Sources & Ownership
County Offaly
Sources and Ownership (All Schemes: 19)
17
18
16
No of Schemes
14
12
10
8
6
4
2
1
1
PWS
Public GWS
0
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY OFFALY REPORT
Microbiological Results in Compliance
County Offaly
Microbiological Results in Compliance (All Schemes: 19)
No
11% (2)
Yes
89% (17)
County Offaly
Microbiological Results in Compliance (All Schemes: 3,905
Domestic Connections)
Yes
99% (3,867)
GALWAY DBO STEERING GROUP – 21rd February 2006
No
1% (38)
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY OFFALY REPORT
Upgrade Solutions Identified
County Offaly
Upgrade Solutions Identified (All Schemes: 19)
Connect to
Public Supply
5% (1)
Disinfection/
Sterilisation
5% (1)
DBO Treatment
79% (15)
Public Source
11% (2)
DBO Treatment
Connect to Public Supply
Disinfection/ Sterilisation
Public Source
County Offaly
Upgrade Solutions Identified (All Schemes: 3,905 Domestic
Connections)
Connect to
Public Supply
1% (44)
DBO Treatment
91% (3,561)
Disinfection/
Sterilisation
1% (20)
Public Source
7% (280)
DBO Treatment
Connect to Public Supply
Disinfection/ Sterilisation
Public Source
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY OFFALY REPORT
Status of Identified Solutions
County Offaly
Current Project Status (All Schemes: 19)
Planning
89% (17)
Complete
11% (2)
Complete
Planning
County Offaly
Current Project Status (Nr of Domestic Connections: 3,905)
Planning
93% (3,625)
Complete
7% (280)
Complete
Planning
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY ROSCOMMON REPORT
Sources & Ownership
County Roscommon
Sources and Ownership (34 Schemes)
35
29
30
No of Schemes
25
20
15
10
5
5
0
PWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY ROSCOMMON REPORT
Microbiological Results in Compliance
County Roscommon
Microbiological Results in Compliance (All Schemes: 34)
Yes
65% (22)
No
35% (12)
County Roscommon
Microbiological Results in Compliance (All Schemes; 2,668 Domestic
Connections)
No
35% (943)
Yes
65% (1,725)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY ROSCOMMON REPORT
Upgrade Solutions Identified
County Roscommon
Upgrade Solutions Identified (All Schemes: 34)
Public Source
15% (5)
DBO Treatment
85% (29)
DBO Treatment
Public Source
County Roscommon
Upgrade Solutions Identified (All Schemes; 2,668 Domestic
Connections)
Public Source
10% (256)
DBO Treatment
90% (2,412)
DBO Treatment
Public Source
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY ROSCOMMON REPORT
Status of Identified Solutions
County Roscommon
Current Project Status (All Schemes: 34)
Complete
21% (7)
Underway
79% (27)
Complete
Underway
County Roscommon
Current Project Status (All Schemes; 2,688 Domestic Connections)
Complete
27% (718)
Underway
73% (1,950)
Complete
Underway
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY SLIGO REPORT
Sources & Ownership
County Sligo
Sources and Ow nership (16)
14
13
No of Schemes
12
10
8
6
4
2
2
1
0
PWS
Public GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Private GWS
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY SLIGO REPORT
Microbiological Results in Compliance
County Sligo
Microbiological Results in Compliance (All Schemes: 16)
Yes
19% (3)
No
81% (13)
County Sligo
Microbiological Results in Compliance (All Schemes: 2,437
Domestic Connections)
Yes
11% (273)
No
89% (2,164)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY SLIGO REPORT
Upgrade Solutions Identified
County Sligo
Upgrade Solutions Identified (All Schemes: 16)
Public Source
19% (3)
DBO Treatment
81% (13)
DBO Treatment
Public Source
County Sligo
Upgrade Solutions Identified (All Schemes: 2,437 Domestic
Connections)
Public
Source
17% (418)
DBO
Treatment
83% (2,019)
DBO Treatment
Public Source
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY SLIGO REPORT
Status of Identified Solutions
County Sligo
Current Project Status (All Schemes: 16)
Complete
19% (3)
Underway
81% (13)
Complete
Underway
County Sligo
Current Project Status (All Schemes: 2,437 Domestic Connections)
Complete
17% (418)
Underw ay
83% (2,019)
Complete
Underway
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
SOUTH TIPPERARY REPORT
Sources & Ownership
South Tipperary
Sources and Ownership (3 Schemes)
3.5
3
No of Schemes
3
2.5
2
1.5
1
0.5
0
Private GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
SOUTH TIPPERARY REPORT
Microbiological Results in Compliance
South Tipperary
Microbiological Results in Com pliance (All Schem es: 3)
No
33% (1)
Yes
67% (2)
South Tipperary
Microbiological Results in Com pliance (All Schem es, 214 Dom estic
Connections)
No
15% (32)
Yes
85% (182)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
SOUTH TIPPERARY REPORT
Upgrade Solutions Identified
South Tippe rary
Upgrade Solutions Ide ntifie d (All Sche m e s : 3)
Disinf ection/
Sterilisation
67% (2)
Takeover
33% (1)
Disinfection/Sterilisation
Takeover
South Tipperary
Upgrade Solutions Identified (All Schemes, 214 Domestic
Connections)
Takeover
15% (32)
Disinfection/
Sterilisation
67% (182)
Disinfection/Sterilisation
GALWAY DBO STEERING GROUP – 21rd February 2006
Takeover
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
SOUTH TIPPERARY REPORT
Status of Identified Solutions
South Tipperary
Current Project Status (All Schemes: 3)
Underw ay
33% (1)
Planning
67% (2)
Planning
Underway
South Tipperary
Current Project Status (All Schemes, 214 Domestic Connections)
Underw ay
43% (92)
Planning
57% (122)
Planning
Underway
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WATERFORD REPORT
Sources & Ownership
County Waterford
Sources and Ow nership (4 Schem es)
4.5
4
4
No of Schemes
3.5
3
2.5
2
1.5
1
0.5
0
Private GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WATERFORD REPORT
Microbiological Results in Compliance
County Waterford
Microbiological Results in Com pliance (All Schem es: 4)
Yes
25% (1)
No
75% (3)
County Waterford
Microbiological Results in Com pliance (All Schem es, 94
Dom estic Connections)
Yes
21% (20)
No
79% (74)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WATERFORD REPORT
Upgrade Solutions Identified
County Waterford
Upgrade Solutions Identified (All Schemes: 4)
Connect to public
main
25% (1)
Takeover
25% (1)
Disinfection/
Sterilisation
50% (2)
Connect to public main
Takeover
Disinfection/Sterilisation
County Waterford
Upgrade Solutions Identified (All Schemes, 94 Domestic
Connections
Connect to
public main
21% (20)
Disinfection/
Sterilisation
38% (36)
Takeover
41% (38)
Connect to public main
Takeover
Disinfection/Sterilisation
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WATERFORD REPORT
Status of Identified Solutions
County Waterford
Current Project Status (All Schemes: 4)
Planning
25% (1)
Underw ay
75% (3)
Planning
Underway
County Waterford
Current Project Status (All Schemes, 94 Domestic Connections)
Planning
17% (16)
Underw ay
83% (78)
Planning
Underway
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WESTMEATH REPORT
Sources & Ownership
County Westm eath
Sources and Ow nership (2)
2.5
2
No of Schemes
2
1.5
1
0.5
0
Private GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WESTMEATH REPORT
Microbiological Results in Compliance
County Westmeath
Bacteriological Results in Com pliance (All Schem es (2))
No
50% (1)
Yes
50% (1)
County Westmeath
Microbiological Results in Com pliance (All Schem es, 246
Dom estic Connections)
No
10% (25)
Yes
90% (221)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WESTMEATH REPORT
Upgrade Solutions Identified (Schemes/Domestic Connections)
County Westmeath
Upgrade Solutions Identified (All Schemes: 2)
(246 Domestic Connections)
Disinfection/
Sterilisation
100% (2)
Disinfection/Sterilisation
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WESTMEATH REPORT
Status of Identified Solutions (Schemes/Domestic Connections)
County Westmeath
Current Project Status (All Schemes: 2)
(246 Domestic Connections)
Complete
100%
Complete
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WEXFORD REPORT
Sources & Ownership
County Wexford
Sources and Ow nership (10)
12
10
No of Schemes
10
8
6
4
2
0
Private GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WEXFORD REPORT
Microbiological Results in Compliance
County Wexford
Bacteriological Results in Compliance (All Schemes: 10)
Yes
40% (4)
No
60% (6)
County Wexford
Bacteriological Results in Compliance (All Schemes; 1,367 Domestic
Connections)
Yes
19% (261)
No
81% (1,106)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WEXFORD REPORT
Upgrade Solutions Identified
County Wexford
Upgrade Solutions Identified (All Schemes: 10)
Takeover
20% (2)
Disinfection/
Sterilisation
20% (2)
Non-DBO
Treatment
10% (1)
DBO Treatment
50% (5)
DBO Treatment
Non-DBO Treatment
Takeover
Disinfection/Sterilisation
County We xford
Upgrade Solutions Identified (All Schem es: 1,367 Dom estic
Connections)
Disinfection/
Sterilisation
20% (257)
Takeover
8% (115)
DBO Treatment
72% (993)
Non-DBO
Treatment
0.1% (2 )
DBO Treatment
Takeover
Non-DBO Treatment
Disinfection/Sterilisation
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WEXFORD REPORT
Status of Identified Solutions
County Wexford
Current Project Status (All Schemes: 10)
Planning
9% (1)
Complete
27% (3)
Underway
64% (7)
Complete
Underway
Planning
County Wexford
Current Project Status (All Schemes: 1,367Domestic Connections)
Planning
2% (22)
Complete
4% (54)
Underway
94% (1306)
Complete
Underway
GALWAY DBO STEERING GROUP – 21rd February 2006
Planning
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WICKLOW REPORT
Sources & Ownership
County Wicklow
Sources and Ow nership (14)
16
14
14
No of Schemes
12
10
8
6
4
2
0
Private GWS
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WICKLOW REPORT
Microbiological Results in Compliance
County Wicklow
Microbiological Results in Com pliance (All Schem es: 14)
Yes
7% (1)
No
93% (13)
County Wicklow
Microbiological Results in Com pliance (Dom estic Connections =
671)
Yes
4% (25)
No
96% (646)
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WICKLOW REPORT
Upgrade Solutions Identified
County Wick low
Upgrade Solutions Ide ntifie d (All Sche m e s : 14)
Public Source
14%(2)
DBO
Treatment
43% (6)
Takeover
43% (6)
DBO Treatment
Takeover
Public Source
County Wicklow
Upgrade Solutions Identified (Domestic Connections = 671)
DBO Treatment
44% (292)
Takeover
48% (325)
DBO Treatment
Public Source
8% (54)
Public Source
GALWAY DBO STEERING GROUP – 21rd February 2006
Takeover
Sherwood House
Sherwood Ave
Taylors Hill
Galway
Presentation to
Seminar on Progress
of Rural Water
Programme 2006
8th June 2006
COUNTY WICKLOW REPORT
Status of Identified Solutions
County Wicklow
Current Project Status (All Schemes: 14)
Underw ay
50% (7)
Planning
50% (7)
Planning
Underway
County Wicklow
Current Project Status (Domestic Connections = 671)
Underw ay
49% (327)
Planning
Planning
51% (344)
Underway
GALWAY DBO STEERING GROUP – 21rd February 2006
Sherwood House
Sherwood Ave
Taylors Hill
Galway