Transcript Document
An initiative of Nodal Agency Power Finance Corporation Ltd. Ministry of Power Government of India Restructured Accelerated Power Development and Reforms Programme R-APDRP Implementation in Karnataka Restructured-APDRP 0 Issues and Intervention required - Karnataka Scheduled date for Go live / integration of DC with pilot town : Dec 2011 Scheduled date for Go live / integration of all towns : Sep 2014 Town Integration Energy Audit Schedule Up Up Up to to to Month Jan’ Feb’ Mar 13 13 ’ 13 Up Up Up Up to to to to Apr’ May’ Jun’ Jul’ 13 13 13 13 Up to Aug’ 13 Up Up Up Up to to to to Sep’ Oct’ Nov’ Dec’ 13 13 13 13 Up Up Up Up Up to to to to to Jan’ Feb’ Mar’ Apr’ May’ 14 14 14 14 14 Up to Jun’ 14 Up Up Up Up to to to to Jul’ Aug’ Sep’ Oct’ 14 14 14 14 Up Up to to Nov’ Dec’ 14 14 Up Up to to Jan’ Feb’ 15 15 Target 10 18 40 40 50 50 50 50 53 55 75 91 98 98 98 98 98 98 98 98 98 98 98 98 98 98 Achie ved 6 10 31 31 46 46 46 46 46 46 46 51 51 60 60 60 60 60 60 60 60 60 60 60 60 60 Full Stack could not be rolled out as modem installation was pending from ITIA ESCOM BESCOM CESC Towns declared full stack live with EA 16 6 GESCOM 11 HESCOM 26 MESCOM 1 Restructured-APDRP 1 Issues and Intervention required - Karnataka Activity DC Data centre commissioning along with all hardware, OS, NMS, EMS & availability of network connectivity. Updating delta changes of Assets Updating delta changes of Consumers GIS Updating data on continuous basis Issues /Status •DC Commissioned, in production phase since Dec 2011. •Only state to successfully demonstrate DC/DR drill as on date. The same was done in in July 2013. •Planning for the completed operation of DR as primary and DC as secondary from 15th March 2015 for 30 days as per the SRS requirement. • LOI issued to NSG India by BESCOM for "Updating incremental data of Network Assets into GIS application under RAPDRP in 92 towns across all five ESCOMs of Karnataka“. • Updating activity to commence from March 2015. Marking of GIS maps is in progress. The data of floating consumers to be tagged with assets in GIS is being shared by ESCOMs with ITIA for migrating the same from back end. So far 1,22,000 floating consumers of 24 towns in BESCOM are updated in GIS. Business flow ensures the assets and consumers are updated in GIS. Since GIS is a heavy application consuming lot of user time, the following changes are made for speedy disposal of new connections: • Bypass GIS online for all cases where updating Assets is not required. (Deployed in April-2014 for <10HP loads and in Jan-2015 for >10HP loads) NA Deployment of GIS integrated Network Analysis Software Restructured-APDRP • Updating assets in GIS to be made post-operation i.e., after work execution. (This change is planned to be deployed by end of April-2015) •Planning a centralized GIS updation team. • Software is deployed and integrated with GIS • User operations to begin after implementing GIS post-operation and training by ITIA. 2 Issues and Intervention required - Karnataka Activity Issues /Status Meter & Modems at all • DTs, Feeders, HT consumers etc. • MDAS • CCC Customer Care Centre • Network connectivity Town Level Restructured-APDRP • • • Tender for meter replacement is under progress since it is joint work of KPTCL and ESCOMs For the Quantity Modems except HT installations, tender work is under progress(07/02/2015 Tech bid was opened) for TWO lots of BESCOM and due to poor participation ,it is retendered for (MESCOM& CESC) and (GESCOM&HESCOM) on 18/02/2015 and Technical bid opened on 26th feb and evaluation is under progress. M/s Infosys has requested ESCOMs to take up the procurement and installation of modems by ESCOMs. ESCOMs have agreed to take up the same and tender is called by BESCOM (all ESCOMs tender) for original BOQ along with 3 years incremental quantity. All the ERL modems fixed earlier will be replaced with new modems, Cost of total modems will be deducted from tender amount. Integrated with Data Centre in all 5 Discoms. Due to application slowness like GIS and WAMS ,based on the recommendation, BESCOM has upgraded primary network to 4 mbps at all locations with last mile OFC connectivity. But quality of network connectivity is very poor with frequent fibre cuts and outages Secondary network provider has failed to deliver more than 109 links, out of 330 links in BESCOM. There are huge latency issues and present VSAT equipment is incompatible to increase the Bandwidth BESCOM has decided to call a Tender for the Alternate connectivity under RAPDRP 3 Implementation Status in Karnataka Eligible Sanctioned towns Cost Rs. Cr Part-A (IT) Sanction date GoI Loan CP Fund Rs. Cr Rs. Cr Disburse Rs.Cr. 98 391.2 Feb 09 & Sep 09 391.2 - 81 786.6 Mar 10 196.6 590 Part-A (SCADA) Part-B ITC : Reliance Infrastructure Ltd (May’09) ITIA : Infosys (Dec’09) SDC : N/A SIA : N/A TPIEA-EA : CPRI (May’10) DC/DR : Bangalore/Chennai Pilot Towns : Bangalore, Mandya, Dharwad, Shikaripura and Gulbarga Ring Fencing : All 98 Towns completed & verified by TPIEA Baseline AT&C : All 98 Towns established Restructured-APDRP 4 Implementation status –Karnataka Consumer Indexing DISCOM Total Towns Total Consumer as per RFP (Lakh) Work In Progress/ Taken up Towns Consumers (Lakh) Survey Completed Towns Submitted by ITIA Consumers (Lakh) Towns Approved by Utility Consumers (Lakh) Towns Consumers (Lakh) % BESCOM 25 38.73 25 43.27 25 43.27 25 43.27 25 43.27 112.00% HESCOM 29 7.98 29 8.87 29 8.87 29 8.87 29 8.87 110.00% GESCOM 21 5.55 21 5.55 21 5.55 21 5.55 21 5.55 108.00% MESCOM 11* 4.18 11* 4.2 11* 4.2 11* 4.2 10* 4.0 96.00% CESC 12 4.98 12 5.14 12 5.14 12 5.14 12 5.14 103.00% Total 98 61.33 98 67.03 98 67.03 98 67.03 97 66.83 109.00% Asset Mapping DISCOM Total Towns Total Fdrs Total SS Work In Progress/ Taken up Survey Completed Approved by Utility Submitted by ITIA Fdrs 1327 SS 124 Towns 25 Fdrs 1327 SS 124 Towns 25 Fdrs 1327 SS 124 Towns 25 SS Fdrs 1327 124 BESCOM 25 1327 124 Towns 25 % 100% HESCOM 29 262 65 29 262 65 29 262 65 29 262 65 29 262 65 100% GESCOM 21 154 36 21 154 36 21 154 36 21 154 36 21 154 36 100% MESCOM 11* 18 5 5 18 5 5 18 5 5 18 5 5 18 5 100% CESC 12 143 29 12 143 29 12 143 29 12 143 29 12 143 29 100% Total 98 1904 259 92 1904 259 92 1904 259 92 1904 259 92 1904 259 100% * Initially it was proposed to migrate the legacy GIS data available with MESCOM for 6 towns. As the data was found to be not compatible by ITIA and MESCOM, a fresh tender is invited by MESCOM for DGPS survey, Validation, Asset mapping and Consumer indexing in respect of 6 towns with contract period of one year. Date of opening of the said tender is 3rd March 2015 . 5 Restructured-APDRP Implementation status in Karnataka Schedule for Installation of DTC DLMS Compliant Meters ESCOM Quantity BESCOM 49020 CESC GESCOM HESCOM MESCOM 6072 8303 14506 7350 Pending for installation 3354 Schedule committed on 31.1.2015 Progress ESCOMs committed during the meeting ITIA Committed to fix the New modems Budget requested from divisions to complete the balance work which are not completed by RC work, since RC period is closed. 45666 Budget is requested from the divisions to complete the balance work which is not completed by RC work, since RC period is closed. Requested ESCOMs to take up modem procurement and installation scope and old ERL modems in the field and at store are not used for DTCs and HTs in all ESCOMs --------do-----------------do-----------------do-----------------do---------- 15th Feb15 Nil Feb-15 Nil 657 Nil 1282 Nil. 15th Feb15 Nil Nil Nil 5415 8303 13224 7350 Boundary Meters & Modems: ESCOM Quantity in Nos. meters Progress of meter installation ESCOMs committed date for metering Modem Pending quantity Progress In modem installation ITIA Committed to fix the New modems Before Feb 15th all modems be installed and integrated in the system 7th Feb15 BESCOM(24) BMAZ 43 40 100% 40 pending Nil Feb-15 17 40 26 Nil CESC 21 100% Nil 14 7 GESCOM 10 100% Nil 10 NIL HESCOM 26 100% Nil 26 Nil Work will be taken up after HESCOM & CESCOM 28th Feb15 MESCOM 26 100% Nil 26 NIL Plan will be submitted Restructured-APDRP 6 Implementation status in Karnataka Schedule for Installation of HT DLMS Compliant Meters &Modems ( responsibility of ITIA) ESCOM Quantity BESCOM(24) BMAZ Pending quantity 550 Nil 7439 1756 CESC 803 Nil GESCOM 670 625 HESCOM MESCOM Restructured-APDRP 1130 Nil 861 Nil. Schedule committed on 14/01/15 Progress in metering Nil 28thFEB 15 Completed Nil 20th Feb15, the meters will be changed by 3P3W only Nil Nil 5683 Completed 45l ESCOMs committ ed during the meeting Nil 28thFEB 15 Nil 20th Modem Pending quantity Progress In modem installatio n 48 7439 502 Nil 597 206 625 NIL ITIA Committed to fix the New modems Will Complete after resolving SIM issues of KGF Plan will be submitted 7th Feb 15 Based on metering schedule. Modems shall be installed simultaneously. Feb15 Completed Nil 1101 29 Completed Nil 861 NIL 28th Feb 2015 Plan to be submitted by ITIA 7 Restructured-APDRP 8