Project Charter

Download Report

Transcript Project Charter

PROJECT PLANNING
Apex Information Systems
Anuja Jahagirdar
Jason Miller
Amol Kakade
Priyanka Akella
Bhaumik Shah
Project
 Title: Medical Insurance Management System
 Start Date: 07 Feb,2011
 Finish Date: 25 April,2011
 Manager: Anuja Jahagirdar.
Project Objective
The main objective of the project is to create a
unique and convenient software solution for
handling insurance related issues medical
professionals have to deal with.
To create an Information system that can
handle the details of multiple insurance
companies at the same time.
Scope Statement
 Research of the entire insurance market.
 Feasibility Study about the time, scope and cost.
 System is design which includes Data flow
Diagram, Table structure and entity relationship
Diagram.
 Feedback needs to be taken from medical
professional.
 Applications are available 24*7
 Regular updating of the database.
Scope Statement Contd.
 Project Success Criteria: The goal is to complete the
project within 12 weeks for budget no more than
$200,000. The project sponsor, Dr. Rob Mohammad, has
emphasized the needs and details which are to be taken
care of. To meet this goal, it is crucial to identify the
bottle-neck in the operation processing, then analyze the
code and check the product. These two methods will
save processing times and also save resources and times.
If the project takes a little longer time to complete and a
little higher cost than what we have planned, this project
still is still considered as a success project, if it allows the
company to save money and times in business
operations and at the same time is utilized in providing
services to its customers.
Work Breakdown Structure





INITIATING
PLANNING
EXECUTING
CONTROLLING
CLOSING
Project Organizational
Structure
Responsibility Assignment
Matrix
Schedule – GANTT Chart
Resource Listing
 Hardware:
1. 5 Dell workstations
2. 1 HP all-in-one printer
 Software:
1. Microsoft Office Suite
2. Microsoft Project
3. Microsoft Visio
4. Adobe Creative Suite
5. Microsoft Visual Studio 2011
Resource Listing
 Personnel:
1.
2.
3.
4.
5.
Project Manager
Systems Analyst
Database Architect
Web Developer
Technical Writer
 Miscellaneous:
Office suite
2. Internet Access
1.
Cost Estimation
 Labor: 5 employees X Avg. $60 per hour X 40
hours per week X 12 weeks = $144,000
 Computer Hardware: 5 Workstations at $1,400




per unit = $7,000
Software costs: $3,000
Workplace costs: $20,000
Additional resources (Reserves): $26,000
Total: $200,000
Cost Estimation
Labor Cost
Workstation costs
Software cost
Workplace cost
Additional resources
Risks
1. Due to time constraints, getting the project
2.
3.
4.
5.
done on time might be difficult
Lack of input from the stakeholders
Difficulty working with different insurance
companies
Stakeholders lack experience to implement
the project
Security risks dealing with patient data
Data Flow Diagrams
Context Level Diagram
Data Flow Diagrams
Data Flow Diagrams
Data Flow Diagrams
Table Structures
 PATIENT: Pat_num , Ins_num , Pat_fname ,






Pat_lname,Pat_addr,Pat_Phone,Pat_InsAmt
DOCTOR: Doc_num, Doc_fname, Doc_lname,
Doc_hosp, Doc_Phone
DOC-PAT: Pat_num , Doc_num
INSURANCE: Ins_num, Ins_policy, Ins_amt,
Ins_disount, Ins_start,Ins_end.
PAT-INS: Pat_num , Ins_num
PHARMA: Phm_num, Phm_name, Phm_addr,
Phm_phone
PAT-PHARMA : : Pat_num , Phm_num
Entity Relationship Diagram