Transcript Case Study

Approaches to Historic Bridge Rehabilitation
Case Study #1
Stenton Avenue Masonry Arch Rehabilitation
Michael J. Cuddy, P.E.
Principal
Kara Russell
Cultural Resource Specialist – Central Office
Monica Harrower
1
Cultural Resource Specialist – District 6-0
Stenton Avenue Bridge (S.R. 3003)
over Wissahickon Creek
Case study #1
 Whitemarsh Township, Montgomery County
 Bridge Description
 Built in 1914
 Total length of 168 feet as measured from end to end of wingwalls
 2-Span Masonry Arch Bridge (clear spans of 30’ and 26’)
comprised of rubble-coursed field stone spandrel walls and
parapets with concrete capstones that continue across the
wingwalls. The voussoirs of the arch rings are partially parged.
The intrados are parged, and concrete toe walls have been placed.
2
Case Study #
Aerial View Showing Project Setting
• Erdenheim Farm
• Washington Valley Park
3
• Wissahickon Trail
Case study #1
Stenton Avenue Masonry Arch Rehabilitation
 Completion Date: 2010
 Cost: $1,050,000
 Designer: TranSystems
 Owner: PennDOT Dist. 6-0
 Contractor: J.D. Eckman Company
4
Case study #1
Significant Issues Associated With Project
 Overwhelming inventory of structurally deficient bridges.
 Increasing number of structural failures to its masonry arch
population.
 Identified the need to develop a repair program that provided for
expedited design process and cost effective repair methodology as
well as one that preserved and renewed the cultural legacy of
masonry arch bridges.
5
Case Study #
Existing Structure
 Average daily traffic: 9,774 vehicles per day.
 Important transportation link.
6
 Critical Condition due to masonry superstructure condition with several Priority “0”
and “1” recommendations requiring timely repairs.
Case Study #
Structure Was in Critical Condition
 Sections of the masonry walls exhibited cracks, bulges and missing or displaced
7
stones. The structure was classified as Structurally Deficient.
 Overall, the barrels were in good condition and suitable for reuse in the rehabilitated
structure.
Substandard Bridge Railings
 Existing roadway width (20’-10”) was determined to be adequate for traffic volumes.
 Masonry barriers inadequate height and strength.
8
 Substandard guiderail connections.
How Significant Issues were Resolved
 Replace earth fill with lightweight concrete fill.
 Reconstruct stone masonry parapets with reinforced concrete cores and full
9
width moment slab.
 Repoint masonry as needed.
 Scour repair and protection.
Temporary Support of Arches
 Arch “centering”, constructed of a timber and pipe scaffolding system, installed to
10
stabilize the arches during rehabilitation.
 The existing bituminous pavement, earth fill, masonry parapets and deteriorated
sections of the spandrel walls were removed.
Case Study #
Replaced Earth Fill with Lightweight Concrete Fill
 Since the utilities would ultimately be encased in the concrete fill, carrier pipes were
11
installed that would permit the smaller diameter utility pipes to be installed after the
bridge rehabilitation.
 Concrete fill was placed over pier and abutments to stabilize the structure during
masonry reconstruction.
Replaced Earth Fill With Lightweight Concrete Fill
Deteriorated sections of the spandrel walls were reconstructed and concrete fill
was placed up to sub-grade level of the new reinforced concrete moment slab.
12
Case Study #
Finished Concrete Moment Slab
 Full width reinforced concrete moment slab with integral concrete barriers was
13
constructed on the concrete fill.
 The barriers were faced with stone and finished with an integral concrete capstone for
aesthetics.
Concrete Core Barrier
 Stone facing was also provided on the fascia.
 Repointing was performed in accordance with the PennDOT Stone Arch Bridge
14
Maintenance Manual and NPS Standards.
Case Study #
Finished Roadway Section
 A bituminous wearing surface was added to the concrete moment slab to provide the
15
appearance of the original structure.
 Note increased parapet height and improved guiderail attachments.
Case Study #
Finished Bridge
16
Case study #1
How was Section 106 handled
 PennDOT District 6-0 Stone Arch Bridge Management Plan




17
Ranked #57 (Not recommended for long term preservation).
Pro-active approach by PennDOT engineering and cultural
resource staff to develop rehabilitation procedures.
Memo with project description prepared and forwarded to
PHMC for review and approval.
Finding of “No Adverse Effect”.
All work performed within existing right-of-way.
Case study #1
Lessons Learned/Conclusions
 Through the development of a streamlined repair methodology,
PennDOT has been able to efficiently and cost effectively
rehabilitate its stone arch bridges.
 Over the past year, construction contracts for 20 masonry arches
have been let employing these procedures.
 Close coordination with the PHMC has resulted in findings of “No
Adverse Effect”.
Project has been awarded a 2010 Grand Jury Award by The
Preservation Alliance for Greater Philadelphia
18