Transcript Presentation Title>>
Aug 2008
xunaa [printed: ____] [saved: ____] Presentation2
Truba Alam Manunggal Engineering Tbk
Management Presentation
1
Company Updates
xunaa [printed: ____] [saved: ____] Presentation2
Highlights
•
•
•
Profit from operations Rp143b – up more than 5,000% yoy
EPS Rp11.1 – up more than 2,000% yoy
Portfolio growth continues in 2008
EPC
– Oil and gas EPC to Chevron valued USD212m
– EPC for PLN’s power plants: Suralaya 1x625MW and Paiton 1x600MW
– More EPC opportunities in Indonesia with the current power and energy infrastructure
boom
IPP
– 3 power plants up and running with capacity of 310MW
– Six coal-fired power plants under construction with capacity of 924MW
– Strong pipeline of further growth opportunities
Coal
– 2 exploitation licenses (KP), with estimated reserves of more than 100m ton
– 6 exploration licenses
xunaa [printed: ____] [saved: ____] Presentation2
Business Segments
EPC Business
4
xunaa [printed: ____] [saved: ____] Presentation2
Solid backlog of EPC contracts
Truba Manunggal has a strong backlog* of EPC projects worth about US$900 million as of end 1Q08.
*Backlog comprises total value awarded contracts that are not completed and the revenue that is expected to be reflected over the remaining life of the
projects in process.
Peluh Merbau
2x150MW
Chevron – Duri,
Riau (Oil & Gas)
RAPP Pulps
(Paper section)
Pontianak
2x30MW
ShoaibaStage II PH.1
B-Aceh
Kuala Tanjung
2x135MW
PP9 C & D
Medan
Tarakan
Minahasa
Bangka
2x12MW
Qurayyah CCPP
Pontianak
Gorontain
Padang
Banyuasin
2x125MW
Palu
Bangka
Kotamobagu
BP – Tangguh (LNG)
Sorong
Serui
Banjarsari
2x100MW
TELPP
Mahakam
Banjarmasin
Bengkulu
Sumatra
Lampung
Ambon
Jayapura
Kobe Steel– South
Kalimantan (Coal
Processing Facility)
Inco Mining
Labuan, Banten
2x300MW
PLTU Sengkang
1x60MW
Kupang
Pelabuhan Ratu
3x350MW
Bima
Sumbawa
Indramayu
3x350MW
PLTGU Muara
Karang
720MW
PLTU Paiton
1x600MW
Sulfindo
2x60MW
Suralaya Baru
1x600MW
CP Bahari
4x30MW
Karang Asem, Bali
2x135MW
IGCC, Bali
1x330MW
EPC – on hand (power)
EPC – on hand (non – power)
5
xunaa [printed: ____] [saved: ____] Presentation2
EPC Backlog – As of March 2008
Backlog
(IDRmn)
Backlog
(US$mn)
Power Plant - Pelabuhan Ratu
1,901,598
207
Main NDD, Chevron Indonesia (oil and gas)
1,375,400
150
Power Plant - Kuala Tanjung
1,045,042
114
Cons. Services Chevron Indonesia (oil and gas)
574,672
62
Power Plant - Indramayu
510,981
56
Power Plant - Pontianak
490,501
53
Power Plant - Labuan
325,709
35
Power Plant - Suralaya
308,560
34
Power Plant - Sulfindo
291,330
32
Mitsubishi Corporation
277,974
30
Kobe Steel, Coal Processing Facility
215,056
23
Power Plant - Bangka
206,466
22
Power Plant - CP Bahari
182,432
20
Power Plant - Paiton
145,360
16
Others - Backlog below Rp100bn
264,847
29
8,115,928
882
Customers
TOTAL
6
Fast track – Power Plants in Java
xunaa [printed: ____] [saved: ____] Presentation2
No
Power Plant
Capacity (MW)
EPC Contractor
1
PLTU 1 Banten – Suralaya
1 x 625 MW
Consortium of China National Technical Import &
Export Corporation (CNTIC), China National
Machinery Import & Export Corporation, Zhejiang
Electric Power Design Institute and PT Rekayasa
Industri
2
PLTU 2 Banten - Labuhan
2 x 300 MW
Consortium Truba Jurong Engineering and
Chengda Engineering Corp.
3
PLTU 3 Banten – Lontar,Teluk Naga
3 x 315 MW
Consortium Dongfang Electric and Dalle Energy
4
PLTU 1 Jawa Barat - Indramayu
3 x 330 MW
Consortium Sinomach, CNEEC, PT Penta Adi
Samudra
5
PLTU 2 Jawa Barat – Pelabuhan Ratu
3 x 350 MW
Consortium Shanghai Electric and Maxima
Infrastruktur
6
PLTU 1 Jawa Tengah - Rembang
2 x 315 MW
Consortium Zelan, Tronoh and Priamanaya
7
PLTU 1 Jawa Timur - Pacitan
2 x 315 MW
Consortium Dongfang Electric and Dalle Energy
8
PLTU 2 Jawa Timur - Paiton
1 x 600 MW
Consortium Harbin Power Engineering and Mitra
Selaras Hutama Energi
9
PLTU 2 Jawa Tengah - Cilacap
1 x 600 MW
10
PLTU 3 Jawa Timur – Tanjung Awar-Awar
2 x 300 MW
Status
On hand
On hand
On hand
On hand
On hand
Consortium Sinomach CNEEC and PT Penta Adi
Samudra
7
xunaa [printed: ____] [saved: ____] Presentation2
Business Segments
IPP Business
8
xunaa [printed: ____] [saved: ____] Presentation2
List of our on-hand IPP projects
Capitalizing on Indonesia’s rising energy needs, Truba will be entrenching its IPP footprint in the domestic powergeneration market
All of Truba Manunggal’s IPP plants are on build/operates/own (BOO) basis
Status
In operation
Under
Construction
Pre
Construction
Mandated
Project name
Location
Commercial
operating date
Capacity
(MW)
Offtaker
CDE- Diesel
Lampung
already COD
210
CPP & CPB
Tanjung Batu
East Kalimantan
already COD
20
PLN
Gunung Megang
South Sumatra
already COD
2x40
PLN
Bangka
Bangka Island
2009
2x12
PLN
Pontianak
West Kalimantan
2009
2x30
PLN
CP Bahari
Lampung
2009
4x30
CPP & CPB
Kuala Tanjung
North Sumatra
2010
2x135
PLN
Banyuasin
South Sumatra
2010
2x125
PLN
Banjarsari
Lampung
2010
2x100
PLN
Paluh Merbau
North Sumatra
2011
2x150
PPA to be signed
with PLN
Karang Asem
Bali
2011
2x135
PPA to be signed
with PLN
IGCC
Bali
2011
330
PPA to be signed
with PLN
Total MW
310
474
450
Power Purchase Agreements last for periods between 20 and 30 years
900
2,134
9
xunaa [printed: ____] [saved: ____] Presentation2
Bangka Power Plant
Project Company
PT Bangka Manunggal Power
Location
Bangka-Belitung
Fuel
Coal
Units
2x12 MW
Minimum fuel requirements
30,000 tons per annum
Off Take
PLN
Construction status
14%
EPC contractor
PT Truba Jaya Engineering (TJE)
Expected COD
September 2009
Off Take status
25 years PPA to PLN
Off Take price
Rp.448.15/ Kwh (Coal cost pass through)
Designed delivery per annum
147,269,000 Kwh
Financing status
Secured project finance from local bank
xunaa [printed: ____] [saved: ____] Presentation2
Pontianak Power Plant
Project Company
PT Equator Manunggal Power
Location
Pontianak, West Kalimantan
Fuel
Coal
Units
2x30 MW
Minimum fuel requirements
218,000 tons per annum
Off Take
PLN
Construction status
10%
EPC contractor
PT Truba Jaya Engineering (TJE)
Expected COD
December 2010
Off Take status
25 years PPA to PLN
Off Take price
Rp.447.05/ Kwh (Coal cost pass through)
Designed delivery per annum
350,640,000 Kwh
Financing status
Secured syndicated loan from local banks
xunaa [printed: ____] [saved: ____] Presentation2
CP Bahari Power Plant
Project Company
PT Central Daya Energi
Location
Tulang Bawang, Lampung
Fuel
Coal
Units
4x30 MW
Minimum fuel requirements
590,000 tons per annum
Off Take
Central Pertiwi Bahari and Central Protein
Prima
Construction status
30%
EPC contractor
Shanghai Electric Group Company, TAME
Turnkey, PT Manunggal Engineering
Expected COD
1st unit in May 2009, and completion in
December 2009
Off Take status
30 years PPA to CPB and CPP
Off Take price
Rp.1,165/ Kwh
Designed delivery per annum
781,200,000 Kwh
Financing status
In discussion
xunaa [printed: ____] [saved: ____] Presentation2
Kuala Tanjung Power Plant
Project Company
PT Ranyza Energi
Location
Kuala Tanjung, North Sumatra
Fuel
Coal
Units
2x135MW
Minimum fuel requirements
930,000 tons per annum
Off Take
PLN
Construction status
EPC contractor
PT Manunggal Engineering and Shanghai
Machinery
Expected COD
July 2010
Off Take status
30 years PPA to PLN
Off Take price
USD cents 4.748/ Kwh (Coal cost pass
through)
Designed delivery per annum
1,789,315,920 Kwh
Financing status
In discussion
xunaa [printed: ____] [saved: ____] Presentation2
Banyuasin Power Plant
Project Company
PT Banyuasin Power Energi
Location
Banyuasin, South Sumatra
Fuel
Coal
Units
2x125MW
Minimum fuel requirements
949,000 tons per annum
Off Take
PLN
Construction status
EPC contractor
TAME Turnkey Contracting
Expected COD
December 2010
Off Take status
30 years PPA to PLN
Off Take price
USD cents 4.2568/ Kwh (Coal cost pass
through)
Designed delivery per annum
1,758,000,000 Kwh
Financing status
In discussion
xunaa [printed: ____] [saved: ____] Presentation2
Banjarsari Power Plant
Project Company
PT Bukit Pembangkit Innovative
Location
Gunung Kembang, South Sumatra
Fuel
Coal
Units
2x100MW
Minimum fuel requirements
870,000 tons per annum
Off Take
PLN
Construction status
EPC contractor
CNEEC
Expected COD
September 2010
Off Take status
30 years PPA to PLN
Off Take price
Rp.459.4/ Kwh (Coal cost pass through)
Designed delivery per annum
1,401,600,000 Kwh
Financing status
Local bank financing
xunaa [printed: ____] [saved: ____] Presentation2
Mandated Power Plants
Paluh Merbau
North Sumatra, 2x150 MW, expected COD
2011
Status
Discussion with strategic partner
Karang Asem
Bali, 2x135 MW, expected COD 2011
Status
Discussion with strategic partner
IGCC – PLTGU Syngas
Bali, 330 MW, expected COD 2011
Status
Advanced stage of discussion with strategic
partners
xunaa [printed: ____] [saved: ____] Presentation2
Business Segments
Coal Business
17
xunaa [printed: ____] [saved: ____] Presentation2
Coal Business
Coal mining and trading platform is to enhance Truba Manunggal’s coal supply reliability and
costs for its IPP business
Primary objective is to improve its suppliers network, management of quality and logistics
Coal Trading
Secondary objective is to generate modest earnings from coal supply to end users in
export markets
Through MME (Manunggal Multi Energi), Truba Manunggal owns an Exploitation license
for 1,587 ha (1st stage) with proven coal reserves of 100 million mt of calorific value
averaging 4,850 kcal.kg (gar)
Coal Mining
The mine is in close proximity to railway infrastructure, therefore coal can be easily
transported to the surrounding power plants (within radius less than 10 km)
Mining is expected to commence operation by early 2009, with first production of 0.6
million metrics tons estimated and subsequently up to 2.0 million metric tons by 2010
Awarded 7 additional licenses; 1 exploitation and 6 exploration, in Sumatra and Kalimantan
Coal stock
piling
Primary objective is to support coal trading function
Secondary objective is to generate sale of coal to domestic non-power companies (ie: pulp
and paper)
…secondary objectives of coal mining and trading is to generate a new
source of revenue for Truba Manunggal
18
xunaa [printed: ____] [saved: ____] Presentation2
Conclusion
•
•
•
Strong 1Q08 financial performance
Performance in 2008 impacted by delays in some of PLN’s EPC
Fundamentals remain attractive
EPC
– Oil and gas activities are ramping up due to increase energy prices
– GOI remains committed to fast track 10,000MW coal-fired power plant
IPP
– Construction of six coal-fired power plants underway
– Strong demand for growth due to lack of power infrastructure in Indonesia
Coal
– Market fundamentals remain robust
xunaa [printed: ____] [saved: ____] Presentation2