Project Purpose….
Replace aged infrastructure
Provide for current water demand
Provide for future water demand
Improve system reliability
Project Area….
- Ford Road
- McClure Road
- New Boonesboro Road
- Colby Road
- Old Boonesboro Road
- April Way
- Water Works Road
- Bypass Road
Area Impact….
11,761 WMU
2,365 East Clark County Water District
215 Kentucky American Water Company
14,341 Total Customers
Scope of Work….
12,000’ of 24” Ductile Iron Raw Water Line
36,000’ of 24” Ductile Iron Finished Water Line
KY Raw Water Intake and Pump Station
Improvements
In total 9 miles of large diameter raw and
finished water transmission lines
Project Cost….
Raw Water Intake Improvements
$1,040,000.00
Raw Water Transmission Main
$2,220,000.00
Finished Water Transmission Main
$6,660,000.00
Engineering
Total Project Cost*
$875,000.00
$10,795,000.00
*Does Not Include WMU Staff Time
Project Disruptions….
Road Closures / Detours
Noise
Dust
Easements….
Temporary and Permanent Easements Required
New easement – Not in flood plain – $4.00/ft.
New easement – In the flood plain – $3.00/ft.
Existing easement (Increase width) – $2.00/ft.
Temporary (all) – $1.00/ft.
*Any variance from this payment schedule will require authorization
from the WMU Commission.
Project Schedule….
Design Phase
Advertising/Bidding Phase
6/14/14
6/14/14 thru 7/8/14
Bid Opening
8/1/14
Begin Construction
8/1/14
Substantial Completion Date
2/1/16
Construction Time
18-19 Months
Key Contacts….
General Manager:
Michael Flynn
Director of
Engineering/Operations:
Utility Engineer:
Kenneth “Duke” Dryden
Eddie Hightower
Winchester Municipal Utilities
150 North Main Street
PO Box 4177
Winchester, KY 40392-4177
Phone: (859) 744 – 5434
Fax: (859) 745 – 4146