WECC Phase 1 Rating Process Study Coordination

Download Report

Transcript WECC Phase 1 Rating Process Study Coordination

WECC Phase 1
Rating Process
Coordinated Planning
and
Technical Studies
July 18, 2008
Portland Oregon
Order 2004 Sensitive
1
Welcome
Darrell Gerrard - PacifiCorp
2
Big Tent Meeting
July 18, 2008
Embassy Suites Hotel – Portland
9:00 a.m. – 12:00 noon
Agenda
9:00
Welcome – Darrell Gerrard
Background from January 2008 Session
Goals Supporting Coordination
9:15
FERC Perspectives – Shelton Cannon, Director
9:30
TCWG Work Plan- What has been accomplished since
January 2008 – Ben Morris
10:00
Individual Project Updates (By Project Sponsor)
11:30
Next Steps and Timelines for TCWG – Darrell Gerrard
11:45
Inputs and Commentary – Sponsor Panel
3
Background

Purpose: status update for 9 proposed projects significant to Northwest

All projects currently in or will be in WECC Phase 1 Rating Process

Began January 2008 with Transmission Coordinated Work Group (TCWG)

Goal is submission of Phase 1 reports in the September – November 2008

Sponsors are reasonably on schedule

Each project sponsor will be submitting an individual Project Phase 1 Rating
report to WECC

Expectations are that projects enter Phase 2 together in the fourth quarter
of 2008
4
Goals Supporting Coordination

Develop ideas to ensure robust proposals brought to sub-regional &
regional engagement

Avoid duplication of study work and facilities constructed

Ensure efficient use of resources, siting, permitting, environmental

Regional view of transmission requirements necessary long term

NW Transmission Hub concept formulated

Optimize current expansion plans from commercial as well as technical
views

Open and transparent FERC Order 890 compliant planning

Improved certainty of project Phase 2 ratings expected via WECC process
5
FERC Perspective
Shelton Cannon, Director
Office of Energy Market Regulation
Federal Energy Regulatory Commission
6
General Plan for WECC
Phase 1 Coordination
Ben Morris
7
Objectives

Coordinate the WECC Phase 1 Rating (non Simultaneous) studies for
projects that meet the following criteria:





Projects that meet such Criteria include: (list in order of presentation)











Currently (or soon will be) in Phase 1
Planned submission of Comprehensive Progress Reports in Sep-Nov
Agree to using a common methodology
All projects involve construction in the Northwest
West of McNary Project (BPA)
I-5 Corridor Reinforcement BPA)
Idaho-Northwest Project (Idaho Power and Others)
Walla Walla-McNary (PacifiCorp)
Hemingway-Captain Jack (PacifiCorp)
Canada to Northern California Project (PG&E and Others)
Canada to Northern California Project – Devil’s Gap Interconnection (Avista)
Southern Crossing Project (PGE)
Northern Lights Project (TransCanada)
Others
Coordination facilitated by the Technical Coordination Work Group
8
Technical Coordination Work Group (TCWG)

Group formed to



Establish consistent assumptions/methods for Project Sponsors
Provide feedback on the Project Sponsor study work
Activities

Develop consistent Assumptions, Switch Decks, Base Cases
 Identify and establish consistent assumptions for the analysis of Hubs
 Review and Comment on Project Sponsor Study Plans, Assumptions, Study
Results and Comprehensive Progress Report
 Attend monthly meetings or conference calls through study completion



Six meetings held
Next meeting scheduled for August 21
Participation – Approximately 30 meeting attendees and more than 80 on
the correspondence list


Representatives from Phase 1 projects
Other stakeholders with interest in providing feedback on technical studies
9
New Transmission Projects in the Northwest
Planned Operation: 2010 – 2015
10
New Transmission Projects in the Northwest
Planned Operation: 2010 – 2015
11
Transmission Projects in Regional Planning and/or Phase 1
Planned Operation: 2010 – 2015
Sponsor/
Participants
Project Name
PacifiCorp
Walla Walla to McNary
BPA
West of McNary Generation
Integration Project
Idaho Power and
Others
Idaho to Northwest
(Hemingway-Boardman)
PGE
Southern Crossing
BPA
Online
Date
Voltage
Capacity
WECC Milestones *
2010
Single-230kV AC
400 MW
RP Initiated – 11/2007
2012 &
2013
Single 500kV AC
and 500kV Sub/
Single 500kV AC
1,500 MW
each
RP Completed – 02/2008
Ph 1 is pending
2012
Single 500kV AC
1,500 MW
RP Completed – 05/2008
Ph 1 Initiated – 02/2008
2013 &
2015
Single 500kV AC
1,500 MW
RP in progress
Ph 1 initiated – 01/2008
I-5 Corridor Reinforcement
Project
2014
500kV Sub/Single
500kV AC
1,500 MW
RP Completed – 03/2008
Ph 1 is pending
PacifiCorp
Idaho to Capt. Jack (part of
Gateway West)
2014
Single 500kV AC
1,500 MW
RP Initiated – 11/2007
PG&E and Others
Canada – Northwest California (CNC)
2015
Double 500kV AC
and HV DC
3,000 MW
RP Completed – 11/2007
Ph 1 Initiated – 10/2007
Avista Corp
Canada – Northwest –
California – Avista
Interconnection - Spokane
Area Upgrades
2015
500kV Sub and local
230kV upgrades
500 MW
RP Initiated – 11/2007
Ph 1 Initiated – 11/2007
TransCanada
Northern Lights
2015
+/- 500 kV DC
2,000 MW
RP Completed – 01/2008
Ph 1 Initiated – 01/2008
*
RP = WECC Regional Planning Process
Ph 1 = WECC Rating Process: Phase 1
12
Project Sponsor Activities/Progress for Phase 1

Developed Study Plan

Developed Study Assumptions

Identified the location and capacity of new incremental generation to be
accessed with the proposed project
 Listed Major paths to be monitored and their target flows
 Identified the projects in the WECC Phase II Rating process to be modeled in
the cases
 Set of critical contingencies to be studied

Developed Base Cases:

Seasonal cases:





2015 Heavy Summer (North-South Flow)
2017 Heavy Winter (South-North Flow)
2011 Light Spring (East-West Flow)
2010 Light Autumn (East-West Flow)
Reviewed and adjusted Load and Generation balance as necessary
13
Project Sponsor Activities/Progress

Conduct Studies pre and post Project (In Progress)

Power flow
 Transient Stability
 Voltage Stability

Identify known interactions with existing facilities and Phase 3 projects
(In Progress)

Communication of Study Progress and Results (In Progress)

Participate in Monthly Meetings/Teleconferences of the Phase 1
 Participate in Joint Big Tent meetings
14
Next Steps: Coordination of Phase 2 Studies

TCWG is the basis for the Phase 2 Project Review Group


Timing




No need to have separate review teams for individual projects
Regular monthly meetings through Phase 2 – a meeting schedule will be
published in the 4th Quarter 2008
Recognize individual projects will proceed through Phase 2 on different
schedules
TCWG will function until the last project gets through Phase 2 at a minimum
Coordination Activities



Common/Similar assumptions
Interactions with other TCWG- coordinated projects in Phase 2
TCWG is currently developing a base case with TCWG-coordinated projects
15
Proposed Schedule for Coordinated Studies
Dec 2007 – Jan 2008

Announce Phase 1 and Form Study Teams

Joint Big Tent Meeting

Develop Assumptions (TCWG)
Feb 2008

Prepare and Finalize Project Study Plans (TCWG)
Feb 2008

Prepare Base Cases (TCWG)
Mar 2008

Pre-Project Studies (Project Sponsor)
April 2008

Joint Big Tent Meeting

Technical Studies on Individual Projects (Project Sponsor)
May-Aug 2008

Draft Comprehensive Progress Reports (Project Sponsor)
Aug-Sep 2008

Review Comprehensive Progress Reports (TCWG)
Aug-Sep 2008

Joint Big Tent Meeting

Submit Phase 1 CPR to PCC and TSS (Project Sponsor)

Phase 2 Studies (Project Sponsor and TCWG)
Jan 24, 2008
Jul 18, 2008
Nov 2008
Sep-Nov 2008
Nov 2008 and on
16
Project Presentations
17
West of McNary Generation Integration
Kyle Kohne, BPA
18
Project Overview

Major Project Elements



Anticipated rating (TTC) increase:





Depending on where new generation is
integrated.
West of McNary: 2850MW to 4500MW
West of Slatt: 4100MW to 5500MW
West of John Day: 2440MW to 3450MW
Anticipated Operating Date:



Part One: Construct a new McNary –
John Day 500 kV transmission line.
Part Two: Construct a new 500 kV
substation (“Station Z”) near Goldendale,
WA, and a 500 kV line from Station Z to
BPA’s Big Eddy substation near The
Dalles, OR.
Part One: Mid 2012
Part Two: Late 2013
Project Website:
http://www.columbiagrid.org/WMRP-overview.cfm
19
Objectives
The objectives of this project are:

To enable BPA to serve point-to-point transmission requests across
multiple congested east-west transmission paths along the
Washington – Oregon border. It would also enable BPA to
interconnect additional wind generation in Eastern Washington and
Eastern Oregon.

Increase system reliability to serve Portland area load.
20
Update

Regional Planning for the West of McNary Generation Integration
Project was initiated through Columbia Grid on June 29, 2007.
WECC approved the Regional Planning Compliance Report on
February 8, 2008.

BPA plans to initiate the WECC Phase One Rating Process in
August 2008.

Funds were approved to begin preliminary design and NEPA work.

Some Public Involvement effort has been initiated.

This project will be included in BPA’s Network Open Season (NOS)
process.
21
Project Implementation Schedule

McNary-John Day 500-kV
 Project will take approximately 3.5 years from start to
energization



Environmental Process / Design – 0.5 years
Material Procurement / Construction – Additional 3 years
Big Eddy-Station Z 500-kV (includes Station Z)
 Project will take approximately 5 years from start to energization


Environmental Process / Design – 2 years
Material Procurement / Construction – Additional 3 years
22
I-5 Corridor Reinforcement
Anthony Radcliff, BPA
23
Project Overview

Major Project Elements:


Anticipated rating (TTC) increase:


Construct a new 500 kV Substation near
Castle Rock, WA. Develop a 500 kV yard
at the existing Troutdale Substation in
Troutdale, OR. Construct a new 500 kV
transmission line between these
substations (approximately 70 miles).
South of Allston: approximately 1300 MW
Anticipated Operating Date:

Late 2014

Project Website:
 http://www.columbiagrid.org/I5CRPoverview.cfm

Alternate Option:

Construct a new 500 kV Substation near
Castle Rock, WA. Add a new 500 kV bay
at the existing Pearl Substation.
Construct a new 500 kV transmission line
between these substations
(approximately 100 miles).
24
Objectives
The objectives of this project are:

To relieve congestion along the I-5 corridor transmission path south
of Paul Substation and enable BPA to serve point-to-point
transmission service requests which impact this path.

To enable BPA to interconnect additional new resources which are
being planned along the I-5 Corridor.

Maintain reliable service to growing loads in Portland and vicinity.

Reduce dependence on existing RAS while maintaining
transmission system reliability.
25
Update

Regional Planning for the I-5 Corridor Reinforcement Project was initiated
through Columbia Grid on June 29, 2007. WECC approved the Regional
Planning Compliance Report on March 21, 2008.

BPA plans to initiate the WECC Phase One Rating Process in August 2008.

Funds were approved to begin preliminary design and NEPA work.

Preliminary design work to evaluate possible corridors for routing the line.

Some Public Involvement effort has been initiated.

This project will be included in BPA’s Network Open Season (NOS)
process.
26
Project Implementation Schedule

I-5 Corridor Reinforcement Project
 Project will take approximately 6 years from start to energization


Environmental Process / Design – 3 years
Material Procurement / Construction – Additional 3 years
27
BPA Network Open Season Update
Anders Johnson, BPA
28
Objectives

One of BPA’s most important strategic objectives is to ensure an
adequate electric power infrastructure for the Pacific Northwest

Network Open Season (NOS) is a key way to meet planning,
expansion, and reliability obligations to BPA’s Network (NT) and
Point-to-Point (PTP) customers

This project is aimed at better managing BPA’s transmission queue
and determining priorities for new transmission

BPA wants to encourage new resource development, including
development of renewable resources
29
Overview

BPA offered transmission service to all entities that requested
service on BPA’s Network (excluding interties)
 The customer committed to purchasing transmission by signing
a precedent agreement (PTSA)
 BPA’s commitment is contingent on providing service at
embedded-cost rates and completing environmental work
 BPA will perform a cluster study and commercial infrastructure
analysis

More information is available:
 http://www.bpa.gov/corporate/pubs/fact%5Fsheets/08fs/Factshe
et-Network_Open_Season_March_2008.pdf
30
Summary of Results to Date
31
Gateway West
Idaho Power and PacifiCorp Joint Project
Dave Angell, Idaho Power
32
Project Overview


Conceptual Major Project Elements

Eastern Wyoming - Two AC circuits (230kV/500kV) from Windstar,
near Dave Johnston, to Jim Bridger

Western Wyoming – Double circuit 500 kV AC from Jim Bridger to
Populus, southern Idaho

Southern Idaho – Two circuits of 500 kV AC from Populus to
Hemingway, near Boise
Potential rating:


Operating Date:


3000 MW
2012/2014
Project Website:
http://www.idahopower.com/newsroom/projnews/Gateway/default.htm
33
Objectives

Connect resource centers to load centers (hub and
spoke concept)


Transmission to forecasted load growth areas
Transmission to forecasted resources areas

Relieve congested transmission paths

Meet transmission requirements of Integrated Resource
Plans (IRP)

Satisfy OATT obligation for transmission service
requests in excess of 1000 MW

Provide transmission for generation interconnection
queue
34
Background

Project developed through Northern Tier Transmission
Group (NTTG) Fast Track Project Process

Milestones:
 NTTG Fast Track Process 1/1/2007 – 6/1/2007
 Initiated Regional Planning 7/5/2007
 Completed Regional Planning 5/30/2008
 Initiated Phase 1 Rating Process 2/19/2008
 Complete Phase 1 Comprehensive Planning Report
8/31/2008
 Initiated NEPA process for siting the lines
35
Proposed Schedule
2007
ID
Task Name
Start
2008
2009
2010
2011
2012
2013
2014
End
Q3
1
NEPA Process
7/2/
2007
12/31/
2009
2
WECC Rating
Process
7/5/
2007
12/31/
2009
3
BLM Right of
Way Grants
1/1/
2009
12/31/
2010
4
Right of Way
Acquisition
9/3/
2007
12/31/
2010
5
Permitting
8/11/
2008
12/31/
2010
6
Engineering
1/1/
2008
12/11/
2012
7
Construction
1/3/
2011
8/2/2018
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
36
Q4
Idaho to Northwest
(Hemingway Boardman)
Dave Angell, Idaho Power
37
Project Overview

Conceptual Major Project
Elements
 Single
500 kV AC
circuit from
Hemingway, Idaho to
Boardman, Oregon

Potential ratings:
 800
MW NW-ID
 1500
MW ID-NW

Project Operating Date:
2012

Project Website:
http://www.idahopower.com/newsroom/projnews/hemingway_boardman/default.htm
38
Objectives

Meet Idaho Power Network Transmission requirements
for imports from the northwest


225 MW of northwest resource import – Integrated Resource
Plan
Additional Network Customer load growth

Satisfy OATT obligation for transmission service
requests in excess of 1000 MW

Connect resource centers to load centers (hub and
spoke concept)



Transmission to forecasted load growth areas
Transmission to forecasted resources areas
Relieve congested transmission path
39
Background

Project initiated through Idaho Power IRP

Milestones:
 NTTG Fast Track Process 1/1/2007 – 6/1/2007
 Initiated Regional Planning 7/5/2007
 Completed Regional Planning 5/30/2008
 Initiated Phase 1 Rating Process 2/19/2008
 Complete Phase 1 Comprehensive Planning Report
8/31/2008
 Initiated NEPA and OEFSC process for siting the line
40
Proposed schedule
2007
ID
Task Name
Start
2008
2009
2010
2011
2012
End
Q3
1
NEPA Process
7/2/
2007
12/31/
2009
2
WECC Rating
Process
7/5/
2007
12/31/
2009
3
BLM Right of
Way Grants
1/1/
2008
12/30/
2009
4
Right of Way
Acquisition
1/1/
2008
5/2/2011
5
Permitting
1/1/
2008
12/31/
2010
6
Engineering
1/1/
2008
12/31/
2010
7
Construction
1/3/
2011
6/1/2012
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
41
Walla Walla to McNary/Boardman
230 kV Line Project
Hemingway to Captain Jack
500 kV Line Project
Tom Tjoelker - PacifiCorp
42
Project Overview; Walla Walla to McNary/Boardman

Conceptual Major Project Elements: Single 230 kV circuit from Walla Walla
Washington to McNary/Boardman Oregon with a tie to Wallula Substation

Potential bidirectional rating: 400 MW

Proposed Project Operating Date: 2010
43
Objectives

Meet transmission requirements of PacifiCorp Integrated Resource Plans
(IRP)

Relieve congested transmission path

Improve Wallula Area Transmission Reliability

Satisfy OATI obligation for transmission service requests

Provide transmission for generation interconnection queue
44
Progress and Future Activities

Initiated Regional Planning November 2007

Conducted regional planning meetings July 2008

Initiate Phase 1 Rating Process July 2008

Complete Regional Planning Report August 2008

Complete Phase 1 Comprehensive Planning Report September 2008

Information can be found on
www.pacificorp.com/energygateway
45
Project Overview: Hemingway to Captain Jack

Conceptual Major Project Elements

Single 500 kV circuit from Hemingway Idaho to Capt. Jack Oregon

Potential east to west rating of 1500 MW, west to east rating to be
determined

Proposed Project Operating Date: 2014
46
Objectives

Meet transmission requirements of PacifiCorp Integrated Resource Plans
(IRP) by increasing transmission capacity between PacifiCorp’s East and
West Control Areas

Relieve congested transmission paths (Idaho to Northwest)

Connect resource centers to load centers (Wyoming Resources to Southern
Oregon Loads)
47
Progress and Future Activities

Initiated Regional Planning November 2007

Conducted regional planning meetings July 2008

Initiate Phase 1 Rating Process July 2008

Complete Regional Planning Report August 2008

Complete Phase 1 Comprehensive Planning Report November 2008

Information can be found on
www.pacificorp.com/energygateway
48
Canada to Northern California
Steve Metague, PG&E
49
Project Overview

Major Project Elements
Selkirk Sub

HVAC from Selkirk to Boardman
area via Spokane area sub
Legend:
500 kV AC



HVDC or HVAC from Boardman
area to Olallie/Maupin area to
Tesla/Tracy
HVDC converter stations either in
the Boardman area or Olallie area
and Tesla/Tracy and potential third
terminal in the Cottonwood area
Devil’s
Gap
AC or DC
HVDC
Boardman Hub
Olallie/
Maupin area
Potential Bidirectional rating:

3000 MW North to South

2000 MW South to North

Project Operating Date: late 2015

Project Website:
http://www.pge.com/canada/
Cottonwood
To SF Bay Area
Substation
50
Objectives

Enhance access to significant incremental renewable resources in
Canada and the Pacific Northwest.

Improve regional transmission reliability.

Provide market participants with beneficial opportunities to use the
facilities.
Other considerations:

Minimize the footprint on the land by using existing and under
utilized corridors where possible

Use an open stakeholder planning process to provide benefits to
customers in all the regions the line traverses.
51
Background

Project steering team: Avista Corp, BCTC, PacifiCorp, Portland
General, PG&E

Milestones reached:

Initiated Regional Planning 12/16/2006.
 Completed Regional Planning 11/1/2007.
 Initiated Phase 1 Rating Process 10/31/2007.
 Completed load and resources, technical feasibility and economic
screening analysis. Reports posted on project website 11/1/2007.

Milestones planned for 2008




Develop Preliminary Plan of Service – August-September 2008.
Complete Phase 1 Studies – September 2008.
Begin Phase 2 Studies (following PCC/TSS acceptance of Phase 1
Studies) – expected by November-December 2008.
Continue to perform pre-permitting studies including environmental and
design activities – throughout 2008-2009.
52
Technical Study Activities

Developed 2015 heavy summer case and 2017 heavy winter benchmark
and project base cases and shared the data with TCWG members.

Developed two and three terminal HVDC models for power flow and
dynamic studies and shared the information with TCWG members.

Developed wind generator model for power flow and dynamic studies.

Working with TCWG members reviewed project interconnection alternatives
in Oregon:
 Boardman HVDC alternative
 Olallie HVDC alternative
 Southern Oregon Hub alternative
 Station K alternative – development in progress

Completed preliminary power flow studies and shared the information with
TCWG members for review and comment.

September 2008 – Issue draft Phase 1 report including preliminary plan of
service.
53
Preliminary Findings

Preliminary findings suggest that desired rating of 3000 MW (north-south) is
feasible for all segments of the project from Selkirk-BC to Northern
California terminal at Collinsville

Among the interconnection alternatives evaluated in the technical studies,
the Southern Oregon Hub alternative had more adverse impact on the
existing PACI intertie requiring mitigation measures at added cost.

Based on preliminary technical studies, routing studies and considerations
for regional benefits, the preliminary plan of service includes:
 500 kV AC from Selkirk to the Olallie area via Devils Gap and the
Boardman Hub
 500 kV HVDC from the Olallie area termination to Collinsville area
substation in Northern California
 A potential third terminal in the Cottonwood area of Northern
California
 500 kV AC from Collinsville to Tesla/Tracy
54
Basic Elements of Conceptual Project Schedule
Task Name
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
FEASIBILITY
ANALYSIS
PROJECT
PERMITTING
PROJECT DESIGN
PROJECT LAND
ACQUISITION
PROCUREMENT OF
MATERIALS
CONSTRUCTION
RELEASE TO
OPERATION
Note: This conceptual project schedule was prepared based on preliminary information without the benefit of route screening, preliminary engineering or other tasks
necessary to finalize a detailed schedule. The timeframes set forth herein may change as the result of pre-application studies.
55
Canada to Northern California Avista Interconnection
Scott Waples, Avista
56
Project Overview

PG&E-CAN
500 kV Line
Major Project Elements:
Westside
230-115 kV

500/230 kV interconnection at
Devils Gap
 230 kV Phase Shifting
Transformers
 2-230 kV interconnections to the
Spokane Area 230 kV Grid

Potential Bidirectional rating:


Devil’s Gap
500-230-115 kV
500 MW
Project Operating Date: 2015
Sunset
230-115 kV
Beacon
230-115 kV
Major Highways
Existing 230 kV
Proposed 230 kV
Existing 115 kV
57
Objectives and Resources

The Avista interconnection to the PG&E Canada to Northern California 500
kV Project will provide up to 500 MW of access to the “Main Stem” Project
from the Avista transmission system for renewable resources in the Avista
service territory.

The interconnection will allow Avista access to other renewable resources in
the Northwest as well as in Canada.

The project may also allow Avista to integrate some of its existing thermal
resources to its loads over its own transmission, and may allow for
additional imports of economy energy into the Avista system.

Potential resources are wind resources located in various locations on the
Avista system, including but not limited to wind farms near Spokane,
Othello, Lewiston, and Clarkston Washington, as well as Grangeville, Idaho.
Avista presently has 12 interconnection requests pending.
58
Background, Study Work, and Future Meetings:

Avista announced a Regional Planning Process that will run concurrently
with a WECC Phase I Rating Process. The letter announcing these
processes went to the WECC Committees and other stakeholders in the
fourth quarter of 2007.

Preliminary studies that have been run on this project indicate that a
500/230 kV interconnection at Devils Gap with the associated 230 kV
construction is feasible. The studies further indicate that a phase shift angle
of plus 20 degrees to minus 40 degrees will be sufficient to satisfy the goal
of a bi-directional rating of 500 MW. There may be a requirement to trip the
interconnection and some generation for some outages. Studies continue.

Avista hosted an initial meeting in Spokane on 2-29-08, and will be hosting
a second meeting in the near future to review the first draft of our study
report.
59
Draft Project Schedule
Task
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
FEASIBILITY
ANALYSIS
PROJECT
PERMITTING
PROJECT DESIGN
PROJECT LAND
ACQUISITION
PROCUREMENT OF
MATERIALS
CONSTRUCTION
RELEASE TO
OPERATION
Note: This draft project schedule was prepared based on preliminary information without the benefit of transmission route screening, preliminary design engineering,
or other tasks necessary to finalize a detailed schedule. The planning timeframes set forth herein may change as a result of pre-application studies, permitting
requirements, and other external conditions.
60
Southern Crossing
Philip Augustin, PGE
61
Project Overview

Conceptual Major Project Elements

500 kV transmission lines
 500/230 kV substation
Coyote Springs
reconfiguration and
36 miles of NEW 500kV Transmission line
Coyote Avista
Coyote PGE

Slatt
substation
Potential Bidirectional rating:

1500 MW
 1500 MW
McNary
substation
Boardman
reconfiguration
kV
500
EW
f N n line
o
io
es
mil miss
114 trans
Portland General Electric
Service Teritory
an
rdm
a
o
B
HUB
Potential new resources
(Wind or other)
Salem, OR
Bethel substation
Project Operating Date:
s
ile
is
ex
g
tin
75 miles of existing
Transmission Corridor
expanded from single
circuit 230 kV to double
circuit 500 kV and 230 kV
V
0k
23
2013
 2013/2015 if staged
M

New 230/500kV Substation
"Olallie"
25

Pelton / Round Butte
Hydro generation

Project Website: PGE OASIS


Grizzly substation
Redmond substation
http://www.oatioasis.com/pge/index.html
http://www.nwpp.org/tcwg/
Southern Crossing Project
Existing transmission system
connected to Project
500 kV
230kV
62
Objectives

Meet the state mandated Renewable Portfolio Standard requirements for
2015

Deliver future wind and other resources to load

Opportunity for integration of existing resources

PGEs 2002 and 2007 Integrated Resource Plans (IRP) - Identified
significant demand and energy requirement, and the critical nature of
transmission

OPUC directed PGE to work with region to develop transmission capacity
over the Cascades to access additional resources

Access to a new Transmission Hub

Balanced scheduling of diverse wind resources at Transmission Hub

Reliability Improvement to Willamette Valley customers

Provide some congestion relief to current transmission system
63
Status

Project is currently being studied by PGET under the OATT process. Feasibility Study
completed, System Impact Study in progress.

Exchanged technical results with adjacent utilities

Formed Regional Planning Review Group

Report on Projects conformance to WECC Regional Planning Guidelines delivered to
Review Group for review and comment

Established Project planning assumptions, and began preliminary discussions with
state permitting authorities

Initiated ROW investigations

Initiated detailed economic evaluation financial model

Consultant developed preliminary EPC estimate
64
Project Implementation Schedule
Task Name
OATT Interconnection Process
• Regulatory & Stakeholder Coordination
• Corridor Options
• High Level cost and schedule
•Feasibility and System Impact Studies
WECC Phase 1 & Regional Review
• Comprehensive Progress Report (CPR)
-Identify the non-simultaneous and known
interactions of the project
• CPR reviewed by PCC & TSS membership
• Informal reports are presented at TSS
meetings
• Letter to TSS and PCC requesting
Phase 2 Status
WECC Phase 2
• Identify the simultaneous transfer capability
for project
• Address mitigations for any adverse impacts
to existing system
• EFSC permitting process
• Land Acquisition
WECC Phase 3
•Definitive commercial agreements
• Engineering
• Procurement
• Construction
• Release To Operation
Duration
Start
Finish
18 months
Q3
2007
Q4
2008
8 months
Q1
2008
Q3
2008
30 months
Q4
2008
Q4
2010
2007
2008
2009
2010
2011
2012
2013
2014
2015
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Q2
2013
48 to 72
months
Q1
2009
or
2013
through
Q2
2015
65
Alberta to Pacific Northwest
Bill Hosie, TransCanada
66
NorthernLights Overview


HVDC transmission line
from Edmonton/Heartland
area to Buckley, Oregon
3000 MW design capacity

900 miles

$2 billion (‘08$), 2000 MW
initial capacity

Merchant intertie line

6 years to permit and build

Edmonton/Heartland
AB
BC
SK
Calgary
Spokane
WA
Buckley
MT
ID
Operational in 2015
OR
NorthernLights
AC or DC Connectors
Project web site:
http://www.transcanada.com/company/projects
_initiatives.html
Converter
67
Objectives

Create a bi-directional path between Alberta and the Pacific
Northwest

Enhance regional resource reliability by providing bi-directional
market access (AESO’s 2007 Market Roadmap)

Provide opportunities for markets to access large-scale renewable
energy resources – wind, hydro IGCC with sequestration, nuclear

Enhance regional wind capacity factors though geographic diversity

Improve regional transmission reliability.

Provide market participants with beneficial opportunities to use the
facilities.
68
Background

NTAC’s Canada to NW to California study demonstrated the cost
effectiveness of HVDC to interconnect the PNW with California

Milestones reached:
 Initiated Regional Planning July 11, 2006
 Regional Planning Meeting in Portland September 22, 2006
 Completed Regional Planning January 2008
 Initiated Phase 1 Rating Process December 10, 2007
 Alberta Transmission Regulations amended – multiple Alberta terminals
allowed for merchant interties December 19, 2007
 Alberta Government signifies support of significant intertie capacity
increase Fall 2007
69
Project Schedule
2008
2009
2010
2011
2012
2013
2014
2015
Initial Feasibility
(complete 2006)
Market Verification &
Commercial Support
2012: Fully Permitted
and Committed Line
Open Season
Detailed Siting and
Permitting
Detailed Technical
Studies / Path Rating
Finalize Land Acquisition
and Construct
Commence Operations
70
Progress

Southern HVDC terminal confirmed at Buckley

BPA Interconnection Application submitted May, 2008

Coordinated PNW Path Rating and Interconnection Study scoped

Integrated Alberta/WECC dynamic model complete and tested

Completed North – South Alberta corridor assessment

26 AESO open houses for Alberta North – South capacity
71
Other Updates
72
Recap of Next Steps and Timelines
Darrell Gerrard - PacifiCorp
73
Next Steps and Timelines for TCWG

Joint Big Tent Meeting
Jul 18, 2008

Technical Studies on Individual Projects (Project Sponsor)
May-Aug 2008

Draft Comprehensive Progress Reports (Project Sponsor)
Aug-Sep 2008

Review Comprehensive Progress Reports (TCWG)
Aug-Sep 2008

Joint Big Tent Meeting

Submit Phase 1 CPR to PCC and TSS (Project Sponsor)

Phase 2 Studies (Project Sponsor and TCWG)
Nov 2008
Sep-Nov 2008
Nov 2008 and on
74
Inputs and Commentary
Sponsor Panel
75