Expanding and Modernizing the Electrical Grid: Essential

Download Report

Transcript Expanding and Modernizing the Electrical Grid: Essential

Expanding and Modernizing the Electrical Grid:
Essential Infrastructure for the
Midwest’s Clean Energy Future
Des Moines Public Library
Des Moines, Iowa
October 21, 2010
Removing Policy Barriers to Transmission
for Renewable Energy
Beth Soholt
Wind on the Wires
[email protected]
Background on Wind on the Wires
• Non-profit Advocacy Organization launched in 2001 to overcome the
barriers to bringing wind energy to market in the Midwest.
• Members include non-profit environmental organizations, tribal
representatives, farm groups, wind developers and manufacturers,
American Wind Energy Association, businesses that provide goods and
services to the wind industry.
• Work in 3 areas:
– Technical – work with electric utilities and Midwest Independent
System Operator (MISO – regional “grid” operator) on transmission
planning for wind, market and operational rules that treat wind fairly
– Regulatory – actively participate in cases where states are approving
new transmission lines that will deliver wind energy
– Policy education/outreach/advocacy – work with governors, state
regulators, legislators, local elected officials, regional groups, colleague
organizations, general public on wind and transmission issues
• Support – Foundation grants and member contributions
Wind on the Wires Footprint
Regional Transmission Organizations
4
MISO State RES Requirements (May 2009)
•
•
•
•
MISO existing wind:
~8,000 MW
MISO State RESs:
~25,000 MW
MISO-wide 20% wind: ~50,000 MW
MGA 30% by 2030: 75-100,000 MW
5
On-Going Challenges for Wind Power and Transmission
• Transmission planning process needs to properly accommodate
public policy goals and move timely through the regulatory process
• Cost allocation – how to pay for new transmission. Cost for large,
regionally beneficial transmission facilities needs to be broadly
allocated
• Fair Market and operational “rules of the road” – must realize and
recognize unique characteristics of variable resources like wind
power
• Wind Integration issues – these issues show up in transmission
planning, the energy market and operations
• Siting/routing new transmission lines
Transmission to Support a Clean Energy Future
• Transmission Expansion
CapX 2020 Initiative
MISO Regional Generation Outlet Study (RGOS)
MISO Candidate Multi-Value Projects (MVP)
CapX 2020 Initiative
• CapX 2020 Initiative undertaken by Minnesota utilities
• Transmission planning done for a number of “future” scenarios out to 2020
– Minnesota generation build out
– Generation from west (North and South Dakota)
– Generation from east markets
• Lines moved forward that were common to all futures
• 3 345 kV lines – Fargo-St. Cloud, Brookings to Twin Cities, SE MN line
• Regulatory proceedings:
– Certificate of Need, including Environmental Report
– Siting/Routing
• All lines have received CON; 2 lines have received Site/Route permit;
currently in Siting/Routing for SE MN line
• Segments will be placed into service between 2013-2015
Regional Generation Outlet Study (RGOS)
•
Developed transmission portfolios needed to implement Renewable
Portfolio Standards or goals at the least cost for consumers while
continuing to reliably serve load.
•
RGOS summary:
– Renewable energy: ~ 40 GW of total wind (~28.5 GW new & ~11 GW ‘existing’)
– Iterative development of transmission plans; options include 345 kV, 765 kV, and
HVDC; analysis included power flow, production cost models (PROMOD), and
business case / value metrics
– The three transmission overlay plans represent potential investment of $16B to
$22B (2010 dollars) over the next 20 years and consist of new transmission
mileage of 6,400 miles to 8,000 miles
– RGOS identified a set of Starter Projects considered viable for near term
development; The estimated cost for this starter set is approximately $5.8 Billion
(2010 dollars), $4.4 billion of which is within the Midwest ISO borders
RGOS Identified Starter Projects
$5.8 B ($4.4 B in MISO)
1
2
3
4
10
5
9
11
6
7
8
Source: Midwest ISO 8/20/10 Draft MTEP10
11
RGOS Identified Starter Projects
1.
2.
3.
Big Stone to Brookings 345 kV line (2010 estimated installed cost: $150M).
Brookings to Twin Cities 345 kV line (2010 estimated installed cost: $700M).
Lakefield Junction to Mitchell County 345 kV line constructed at 765 kV specifications
(2010 estimated installed cost: $600M).
4. North LaCrosse to North Madison to Cardinal, Dubuque to Spring Green to Cardinal
345 kV lines (2010 estimated installed cost: $811M).
5. Sheldon to Webster to Hazleton 345 kV line (2010 estimated installed cost: $458M).
6. Ottumwa to Adair to Thomas Hill, Adair to Palmyra 345 kV lines (2010 estimated
installed cost: $295M).
7. Palmyra to Meredosia to Pawnee, Ipava to Meredosia 345 kV lines (2010 estimated
installed cost: $345M).
8. Sullivan to Meadow Lake to Greentown to Blue Creek 765 kV line (2010 estimated
installed cost: $908M).
9. Collins to Kewanee to Pontiac to Meadow Lake 765 kV line (2010 estimated installed
cost: $964M).
10. Michigan Thumb 345 kV transmission loop (2010 estimated installed cost: $510M).
11. Davis Besse to Beaver 345 kV line (2010 estimated installed cost: $71M).