Transcript Document
PPC Industry Forum, 06 March 2008 Partial Private Circuits Disclaimer •BT has taken reasonable care to check that the information contained in the following slides was accurate at time of publication. •Any price indications or timescales contained within this presentation are estimates for information purposes only and do not constitute any contractual or other obligation. •In relation to any products/services referred to in this presentation which are currently under development and/or trial, BT gives no undertaking or other commitment that the product/service will be made commercially available •BT reserves the right to make changes to the information in this presentation at any time without further notice •Exclusive reliance on the information in this slide pack is at your own risk Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Agenda •Introduction – •Review of previous actions – •Product Development Update – •Product In Life Update – Pauline Cowie Pauline Cowie/All Pauline Cowie/All Pauline Cowie/All • QoS • Billing • Communications •AOB – All •Meeting Review •Date of next meeting Managed Bandwidth Services BTW Products and Strategy – - Pauline Cowie All Partial Private Circuits Action Point Review Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 12/1 (01/12/05) – “BT to investigate the inclusion of eCo Repair in the data quality monitoring on the One Truth Data Base” Update: Removed from Q4 development schedule and will be reviewed status in Q3 2008. Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 03/11 (01/03/07) – B End Shift – Internal/External Shifts: Cost does not appear to be correct BT to Investigate. Update: Cost analysis ongoing, internal escalation by Leslie Hurrell-Smith to seek suitable resource to complete commercial modelling. Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 06/05 (07/06/07) – Exchange Closure: Update: BT is currently working on an exchange closure notification plan, which will include details of post code changes where appropriate and their replacements where applicable Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 06/09 (07/06/07) – Firm Offer Confirmation (FOC): BT to provide CPs with the next steps to address the Highband planning problems, which affects BT meeting FOC timescales. Update: Formal SoR raised with BT Operate as part of the Lead to Cash project. The SoR was submitted 30 Jan 08 with a target response date of 25 April 08 at the latest. Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 06/14 (07/06/07) – Interim Feedback: Industry requests BT provide interim feedback on issues between meetings. BT to ensure published Issues/Action lists are updated when information known and not wait for next forum. Update: Short term resource obtained to produce this interim feedback and will be distributed by end Feb. Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 18/01 (18/09/07) – Customer Satisfaction: •Industry request a list of the Customer Satisfaction survey question before being surveyed. Industry requests the details of their Customer Satisfaction Contact, this should also include details of their CRM and other useful BT Contacts. Update: During February and March 08 customer satisfaction questionnaires are to include opportunities for customers to comment regardless of CFI scores. BT requires industry to confirm they have been asked to provide comments regardless of whether the scores are low. Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 18/02 (18/09/07) – PPC eCo Rationalisation: BT to set up workshop with Industry in attendance. Customer Sat rep offers to facilitate. Update: 4 CPs have been engaged and were positive in their feedback. BT waiting further responses from 2 CPs Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 18/04 (18/09/07) – Online Pricing Tool Industry requests BT organise a workshop to look at developing the pricing tool regarding identification of capacity at Point of Handovers (PoHs). Update: Workshop held 04/02/08 Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 18/07 (18/09/07) – Communications BT requests Industry provides BT with details of whom within their organisation should be invited to the PPC Industry Forum. BT Account Teams to collate. Update: Waiting Industry to confirm they have provided their account teams with their preferred contacts. Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 18/08 (18/09/07) – Excess Construction Charge (ECC) Industry expressed concern at the increase in ECC charges being raised against PPC new provision and request justification. BT to investigate and feedback. Update: BT waiting evidence from industry to enable investigation Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 06/01 (06/12/07) – FOCR on B End Shifts: Industry expressed concerns at not receiving FOCR on B End Shifts. BT to investigate and re-brief CMC where necessary Update: CMCs re-briefed regarding FOCR on B End shifts. BT requests industry to provide evidence where this is not happening to enable further investigation. Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 06/02 (06/12/07) – 4x2Mbit/s Package: Industry requests BT provide information on how this new product will be linked into eCO and brief out to Industry. Update: Product Handbook being updated to be distributed shortly. Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 06/03 (06/12/07) – Additional Package for 5, 6 or 7 circuits: Verizon Business to provide BT with details of an additional requirement in respect of circuits which fall outside of the 4x2Mbit/s package criteria. Update: SoR submitted, feasibility of development taking place Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 06/04 (06/12/07) – PPC Additional Charges: Star Technologies to review with their sales team whether there is a requirement for the PPC Product Team to present to them on PPC pricing Update: Waiting for Star to submit requirement. Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 06/05 (06/12/07) – QoS – New Install Failures: BT to further investigate reasons for new install failures attributed to Industry. Industry believes this may be due to “loops” rather than true failures. Update: Repair representative to attend next Forum to provide guidance. The slide pack has been amended with the correct information. Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 06/06 (06/12/07) – QoS - Stats: BT to re-do Stats presented to industry as showing some inconsistencies. Slides to be update prior to publication on PPC website. Update: Slides updated and published on PPC Web site. Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 06/07 (06/12/07) – QoS – FOCR Performance: Industry requests BT show 2Mbit/s and Highband performances separately and a plan to action for improvement Update: Performance data to be provided in published QoS stats. 2Mbit/s performance is at a level where no action is required. SoR submitted requesting improvements in Highband performances. Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 06/08 (06/12/07) – ISH Extension: Industry to review BT’s proposal presented in the “SDH Serving Notes Determination at the Point of Handover (AEnd)” and feedback their views by 20 Dec 07. Update: Workshop held 04/02/08. Agreement reached and recommendations taken away. Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Action Point 06/09 (06/12/07) – Out of Hours Repair: Virgin Media expressed concerns at being advised that out of hours fault repair is on voluntary basis. Industry requests BT investigate, as Enhanced Care is a paid 24hr service. BT to investigate. Update: Repair representative to attend next forum to discuss issue. Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Product Development Update Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits – Development Road Map Q3 OctQ3 – Dec Oct07– Q4 Jan – Mar 07 – Mar Q106 Apr – Jun 08 Q2 Jul06 – Sep 08 Q2 July Q3 Oct – Dec - Sept 0608 Dec 05 Q4 Jan Q1 Apr-June PPC RPC to PPC Managed Conversion Process Launched ISH Extension Prices Migration of PPC billing to the Geneva platform 22nd January 08 9th October 07 1st PPC Annual Price Control PPC 4x2Mbit/sPackage Launch 22nd January 08 19th October 07 E-Connect Product Launch PPC Handover Requirements Suspended November 07 Completion March 08 PPC Equipment Cancellation Charges 8x2Mbit/s Commercial Offering Q2 08 TBC Q3 08 TBC April 08 Reduction in PPC Lead Times PPC B End Shift Charges TBC PPC ‘Tungston’ Product Launch April 08 TBC PPC Contract Review 155Mbit/s Price Review Q2 08 TBC Q2 08 TBC PPC Geographic Pricing Q2 08 TBC PPC Fibre & Copper Availability Q2 08 TBC PPC Highband FOCR Improvements Q2 08 TBC BTW Products and Strategy Version 07/11/07e 21 CN Migration – TDM TBA 21 CN Migration – sub 2mbit/s TBA PPC Priority Repair March 08 Managed Bandwidth Services By 2014 PPC SoR Details SoR Received Owner CP has requested that BT review the PPC & RBS equipment cancellation charges as they believe they are unfair. Cancellation charges are currently charged as a percentage of kit cost, regardless of whether that kit is deployed or not, and the kit can then be reused by BT. These cancellation charges apply to both PPCs and RBS. 03/05/07 Tim Nolan 2Mb PPC prices are currently only differentiated into National and CLZ. This SoR is requesting lower prices in "business areas" (similar to CLZ in London) of major cities e.g. Birmingham, Manchester, Merseyside area, West London/Heathrow 25/10/07 Pauline Cowie SoR Description 10289 High Bandwidth "Bronze" PPC services Change to the existing high bandwidth PPC services 34/45 and 155 service. Remove the second fibre access feed this will potential improve the leadtime and also reduce the final cost to the customer. This will be a “new” alternative service; the existing high bandwidth product will be retained. The main driver for this service is that it will be cheaper and also quicker to deliver alleviating the problems with the second fibre delays etc. The second reason for the development is that BTW could potentially provide two accesses with separation between products/circuits for customers. At this moment in time CP’s are using different supplies to build in this protection as they build up/out their own networks. If we could also offer 2 diverse fed highband megastream with some type of managed separation between each circuit/path (access and core). This may be of additional interest? 10247 RBS & PPC Cancellation Charges 10425 Geographic 2Mb PPC prices for "CLZ-like" zones in major cities area, Watford, Leeds/Bradford area, Croydon area and Bristol Managed Bandwidth Services BTW Products and Strategy PPC SoR Details continued 10481 PPC Customers' High Priority Service Enhancement Requirements PPC customers have stated that improvements to PPC lead times and repair times are of 28/01/08 a high priority to them. The PPC provision process currently allows customers to order a proportion of their circuits with reduced lead times. Customers have asked for the number of circuits which they can order in this way to be increased and for the reduced lead times to be 'guaranteed'. They have also asked for an option to nominate key PPC sites/circuits which will attract improved repair timescales. Pauline Cowie 10492 Highband FOCR Improvement 34Mbit/s to 155Mbit/s PPCs, Ofcom delivery date, costs and delivery medium currently has to be provided by BT by day 8. This target is rarely met. The requirement is usually achieved at day 20/21. This is considered far too long and the performance has been worsening. Ofcom and PPC Industry require BT to improve on this significantly on requirement. PPC Industry is willing to support a reasonable day when the requirement delivered. The initial indication is that day 10 will be the best and day 15 the least acceptable delivery date on the requirement. 30/01/08 Stephen Olugbode 10493 Spare Fibre and Copper Availability PPC customers are unable to place orders with BT until they have confirmed whether excess construction charges will be applicable. This takes between 5 days for wideband/narrowband circuits and 21 days for Highband circuits. Where spare fibre or copper is available at the customer site, excess construction charges will not be applicable. Upfront access to availability information will enable our customers make informed decisions to place orders with BT and improve the our ability to generate revenues much earlier. 30/01/08 Stephen Olugbode 8x2Mbit/s A PPC 4x2Mbit/s pricing structure was launched on 19th October 2007. PPC customers Commercial Offering have asked for a similar commercial offering for 8x2Mbit/s. Managed Bandwidth Services BTW Products and Strategy Pauline Cowie Partial Private Circuits Product In-Life Update •QoS •Billing •Communications Managed Bandwidth Services BTW Products and Strategy QoS QoS Performance - Reporting Update •Q3 Aggregated Report published on website •Q3 CP reports distributed •Retail Comparison available on CDD, CRD and Repair PPC/Retail Comparison Q3 •CDD Retail 97.15% PPC 97.98% •Repair Retail 85.65% PPC 90.38% Managed Bandwidth Services BTW Products and Strategy QoS PPC CDD Performance 120 100 Performance 80 Narrow band 60 Highband Wideband 40 20 Month Managed Bandwidth Services BTW Products and Strategy De c07 No v07 ct07 O Se p07 Au g07 Ju l-0 7 Ju n07 07 M ay - Ap r-0 7 M ar -0 7 Fe b07 Ja n07 De c06 No v06 0 QoS 5000 90 4500 80 4000 70 3500 60 3000 50 2500 40 2000 30 1500 1000 20 500 10 0 Managed Bandwidth Services BTW Products and Strategy Months ec em ber 2 0 07 Oc to ber t oD to Se ptem be r 2 007 J uly April to J u ne 20 07 07 rch 2 0 o Ma J anu a ry t ec em ber 2 0 06 Oc to ber t oD to Se ptem be r 2 006 J uly 06 to J u ne 20 April J anu a ry t o Ma rch 2 0 06 0 % new install faults New install population/faults New Install chart New install fault population New install faults % New install faults due to BT % New install faults due to customer QoS QoS Performance – Q3 - Highlights •Circuit CDD performance remains high at 97.78% and compares favourably with last quarter's performance of 97.17%. •(CPs) CDD performance at 97.78% continues to compare favourably with Retail CDD performance of 97.15%. •Overall, the percentage of orders exceeding FOCR excluding Stop the Clock delays is 16.53% (570 of 3449 orders). For 2M RP circuits the equivalent FOCR percentage excluding Stop the clock delays is 8.07% (44 of 545 orders) and for 2M RRP circuits, the equivalent FOCR percentage excluding is 11% (237 of 2147 orders). •The number of RRP orders meeting CRD increased significantly to 71.38% against 65.33% in the last quarter. •Retail performance (85.65%) continues to track lower than PPC repair performance (90.38%) •The average out of hours continues to be below 5 hours at 2.52 hours against 2.79 hours in the last quarter. •The number of faults in the quarter decreased to 8458 from 8977 in the last quarter. •The fault rate reduced to 0.41 from 0.44 in the last quarter. Managed Bandwidth Services BTW Products and Strategy QoS •QoS Performance – Q3 - Lowlights •The number of Stop the Clock instances increased to 1690 from 1469 in the last quarter. This is against a decrease in the supply volume of 3475 from 3523 in the last quarter. •95% of the Stop the Clock instances are due to the Third party customer. A large proportion of the delays are due to site access issues or the site not being prepared and ready or requests to delay order progression. •Due to late closure of a few response time flags, the response time is extremely high on some bandwidths. This was due to human error. This is being addressed within BT through training. •BT experienced several serious network incidents cause by third parties. Over a dozen higher order cables were damaged and adversely affected BT's ability to fix affected circuits. Managed Bandwidth Services BTW Products and Strategy Billing Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Monthly Billing commenced 1st January 08, most PPC customers have moved from quarterly to monthly billing Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits PPC Migration to GenIUS: Billing Migration of PPC inventory takes place during March, managed in three phases with one day data freeze for each phase. Phase 1 – 8th & 9th March with one day data freeze on 6th March. Phase 2 – 10th & 11 March with one day data freeze on 12th March. Phase 3 – 21st 22nd 23rd & 24th March with one day data freeze on 19th March. •The data freeze affects new orders only, no orders will be raised on BT internal order management system (COSMOSS). •CPs can input requests via eCo, electronic PPCRF or standard PPCRF as normal . •In-flight orders will be managed as usual with updates provided business as usual. Billing to continue on PCNBS until 1st July 2008 when Wholesale GenIUS will become the new billing system. Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Communications: Service Outage on Wholesale.com •Service Suspended from: 00.00hrs Sunday 30th March 2008 •Service Restored to Fault Diagnostics only: 06.00hrs Sunday 30th March 2008 •Service Fully Restored: 10:00hrs Sunday 30th March 2008 During this time, access to btwholesale.com and all associated applications will be unavailable, Pricing Notifications: •ACCN 822 to 824 - Partial Private Circuits Price Review - effective 30th January 2008 •ACCN 827 to 831 - Excess Construction Charges - effective 1st February 2008 Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Briefings: 079/08 – Outcome of Partial Private Circuits (PPCs) Contract Review – 07/02/08 086/08 – Billing Migration – Data Freeze – 27/03/08 087/08 - PPC Migration and Managed Conversion Data Freeze – 29/03/08 Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits Forum Review Managed Bandwidth Services BTW Products and Strategy Partial Private Circuits A.O.B Next Meeting Scheduled 12th June 2008 BTC, Business Showcase Managed Bandwidth Services BTW Products and Strategy