U.S. (FHWA) MICROPILE
PRACTICE AND UPDATE
“ Implementation Manual
& Teaching Modules”
TOM A. ARMOUR, P.E.
SESSION VII
CODES, STANDARDS AND GUIDELINES
IWM 2002
MAY 29 – JUNE 1, 2002
REFERENCE PROGRAMS
“Funded by FHWA to Speed Up
the Implementation of Micropiles”

State of the Practice Review (Step 1) -1997

Design and Construction
Implementation Manual (Step 2)
- 2000

National Technical Workshop
(Step 3)
- 2002
IMPLEMENTATION MANUAL
- (STEP 2)
“Recommended Guidelines”

Micropile Definition & Classification System

Micropile Design Guidelines

Service Load Design

Load Factor Design

Load Testing Recommendations

Quality Assurance Quality Control (QA/QC)

Contracting Methods

Owner Controlled Design

Contractor Design/Build

Guideline Specifications

Alternative Procurement Methods

Micropile Contractor Prequalification

Geotechnical Design Summary

Contractor Submittals

Pile Load Testing

Measurement and Payment
NATIONAL TECHNICAL
WORKSHOP- (STEP 3)
“Training Module”

Primary Objective
To develop a national
technical workshop targeted
at Federal and State Dept.
of Transportation specialists
involved in design, construction
and specification development
for transportation facilities.

NATIONAL TECHNICAL
WORKSHOP- (STEP 3)
“Training Module”

Other Objectives
1.
Introduce micropile
technology
2.
Present site investigation,
load testing and QA/QC
recommendations
3.
Present comprehensive
design methods
4.
Provide example plans and
guideline specifications
NATIONAL TECHNICAL
WORKSHOP- (STEP 3)
“Training Module”

Important Statistics

Contractor is ADSC – “The
Industry”

15 month contract to
complete module

2- Day Training Course

75 training courses
anticipated to be taught
throughout USA over next
3 - 4 years
USA MICROPILE PRACTICE
“Where We Are Today”

No AASHTO Approval

2001 AASHTO LRFD Highway
Bridge Construction Specifications

Public Agencies gaining
knowledge with increased use

Specialty Contractors still leading
the charge in the development and
specification of micropile
applications

FHWA/Industry increasing
micropile focus through ADSC/DFI
INDUSTRY UPDATE
“Current Works In Progress”

Industry Seminars

Industry Short Courses

Operator Training
Courses

Inspector
Training/Certification

Design/Construction
Training Modules
INDUSTRY UPDATE (con’t)
“Current Works In Progress”

Regional Educational
Presentations

Regional Technical
Assistance

Research &
Development

IWM
INDUSTRY UPDATE (con’t)
“Current Works In Progress”

Fund Raising

Technical Library

Practice Updates

Public Relations
