Construction Planning & Controls
Download
Report
Transcript Construction Planning & Controls
Basics of Project Planning
Planning Concepts
Construction Planning
Setting Milestones for overall completion
Organizing
activities for Individual area completion, duly
acknowledging their inter dependence
Providing various Resources
Directing the Planning for execution
Review and Redirection
Planning in total….
Planning is assembling total inputs
Men, Machine, Materials
Tools / Small Tools
Lay down area
Clearances
Apply productivity while planning
Break job into activities
Quantify each activity
Find out unit quantum of the job, may be a joint, major or
minor lift
Study rate of achieving unit quantum
Pace the job by setting tougher norms every day
Sequencing Activity
Interdependence to each other
Gang Movement
Resource Leveling
Review and Redirect
Planning once done, is not done for ever
Periodical review sets the rhythm
More looks on planning throw more clarity on the path of
our progress
You need to set new dates, reschedule resources
Planning Levels
Term
Objectives
Periodicity
Total
Project milestones setting and
Quarterly
resource budgeting
3 months Intermilestones setting and Resource Monthly
mobilisation
Week
Direction for field execution
Weekly
Day
Productivity, Quality, Safety assurance Day
S0
S1
MPCS
Schedules
Work
Schedule
Invoicing Schedule
S2 Milestone Schedule
S3 P&M Schedule
S4 Staff Schedule
S5 Labour Schedule
S6 Material Schedule
S7 Special Agency Schedule
S8 Direct Cost Schedule
S9 Indirect Cost Schedule
S10- Fund Flow Schedule
3 Months look ahead planning - Pictorial
Representation
WORK
PERIOD IN MONTH
SL NO
ACTIVITY
UNIT
SCOPE DURATION
1
1
MOBILIZATION
LS
-
2
3
4
5
6
15 DAYS
495
2
EXCAVATION
CUM
1480
45 DAYS
3
FOUNDATION WORK
CUM
476
60 DAYS
4
PAINTING & BACKFILLING
CUM
443
45 DAYS
5
STRUCTURE FABRICATION
MT
660
75 DAYS
6
STRUCTURE ERECTION
MT
660
60 DAYS
7
SPOOL FABRICATION
LM
1500
75 DAYS
8
SPOOL ERECTION
LM
1500
75 DAYS
9
TESTING AND COMMISSIONING
LS
-
60 DAYS
10
HANDING OVER #
LS
-
45 DAYS
NSH
NSH
985
215
200
261
295
148
300
160
130
400
130
500
700
300
200
750
550
7
8
EQUIPMENT SCHEDULE FOR PIPE RACK WORK
PERIOD IN MONTH
SL NO
EQUIPMENT DESCRIPTION
UNIT
QTY
DURATION
1
1
EXCAVATOR / JCB
NO
1
2
3
4
45 DAYS
NSH
NSH
2
DUMP TRUCK
NOS
2
75 DAYS
3
LOADER
NO
1
60 DAYS
4
BOBCAT
NOS
3
45 DAYS
5
PLATE COMPACTOR
NOS
5
90 DAYS
6
CRANE, 100T
NOS
2
135 DAYS
7
CRANE, 50T
NO
1
90 DAYS
8
TRAILER
NO
1
90 DAYS
9
MAN BASKET
NOS
2
135 DAYS
5
6
7
8
DIRECT MANPOWER SCHEDULE FOR PIPE RACK
WORK
PERIOD IN MONTH
SL NO
TRADE
UNIT
QTY
DURATION
1
CIVIL FOREMAN
EA
1
90 DAYS
2
MASON
EA
7
60 DAYS
3
STEEL FIXER
EA
9
75 DAYS
4
CARPENTER
EA
15
60 DAYS
5
LABOUR
EA
19
225 DAYS
6
SCAFFOLDER
EA
21
150 DAYS
7
STRUCTURAL FOREMAN
EA
2
60 DAYS
8
STRUCTURAL FITTER
EA
13
60 DAYS
9
PIPING FOREMAN
EA
2
135 DAYS
10
PIPE FITTER
EA
12
135 DAYS
11
WELDER
EA
7
135 DAYS
EA
107
240 DAYS
1
2
3
4
1
1
2
1
6
10
6
8
12
12
18
20
30
6
8
TOTAL
15
5
6
7
8
25
25
18
12
10
15
25
25
25
15
1
2
2
2
8
16
16
12
1
2
2
2
2
1
8
14
18
16
8
6
4
8
10
10
8
6
2
60
122
101
94
69
43
19
NSH
NSH
NSH
DIRECT MANPOWER SCHEDULE FOR PIPE RACK
WORK
CONSTRUCTION PROGRAM M E FOR PIPE RACK WORK
SL
NO
PERIOD IN MONTH
ACTIVITY
UNIT
SCOPE
DURATION
1
1
MOBILIZAT ION
LS
-
15 DAYS
2
EXCAVAT ION
CUM
1480
45 DAYS
3
FOUNDAT ION WORK
CUM
476
60 DAYS
4
PAINT ING & BACKFILLING
CUM
443
45 DAYS
2
495
200
6
7
ST RUCT URE FABRICAT ION
ST RUCT URE ERECT ION
SPOOL FABRICAT ION
MT
MT
LM
660
660
1500
5
6
7
8
6
7
8
5
6
7
8
10
REMARKS
NSH
NS
N
261
295
148
300
160
75 DAYS
130
400
130
500
700
300
200
750
60 DAYS
75 DAYS
8
SPOOL ERECT ION
LM
1500
75 DAYS
9
T EST ING AND COMMISSIONING
LS
-
60 DAYS
HANDING OVER
LS
-
45 DAYS
10
4
985
215
5
3
550
EQUIPM ENT SCHEDULE FOR PIPE RACK WORK
SL
NO
PERIOD IN MONTH
EQUIPMENT DESCRIPTION
UNIT
QTY
DURATION
REMARKS
1
1
EXCAVAT OR / JCB
2
DUMP T RUCK
NO
1
45 DAYS
NOS
2
60 DAYS
3
4
LOADER
NO
1
60 DAYS
BOBCAT
NOS
3
45 DAYS
5
PLAT E COMPACT OR
NOS
5
90 DAYS
6
CRANE, 100T
NOS
2
135 DAYS
7
CRANE, 50T
NO
1
120 DAYS
8
T RAILER
NO
1
150 DAYS
9
MAN BASKET
NOS
2
120 DAYS
2
3
4
5
NSH
NS
N
#
#
DIRECT M ANPOWER SCHEDULE FOR PIPE RACK WORK
PERIOD IN MONTH
SL
NO
1
2
TRADE
CIVIL FOREMAN
UNIT
EA
MASON
EA
QTY
1
7
DURATION
REMARKS
1
2
ST EEL FIXER
EA
9
1
CARPENT ER
EA
15
60 DAYS
LABOUR
EA
19
225 DAYS
6
SCAFFOLDER
EA
21
150 DAYS
8
7
ST RUCT URAL FOREMAN
EA
2
60 DAYS
8
ST RUCT URAL FIT T ER
EA
13
60 DAYS
10
11
PIPE FIT T ER
WELDER
#
#
#
TOTAL
EA
EA
2
12
2
1
6
10
6
8
12
12
18
20
30
25
25
18
12
25
15
NSH
NS
N
75 DAYS
5
PIPING FOREMAN
1
60 DAYS
4
9
4
90 DAYS
6
3
3
15
25
25
1
2
2
2
8
16
16
12
1
2
2
2
2
1
8
14
18
16
8
6
4
8
10
10
8
6
2
60
122
101
94
69
43
19
135 DAYS
135 DAYS
EA
7
135 DAYS
EA
107
240 DAYS
15
Schedule : Labour
Purpose ….
Histogram (Average / Peak Strength)
Labour License / Colony Planning
Sub-contracting strategy
Staff Planning
Schedule : Material
Purpose ….
Bulk purchase arrangement
Vendor development
Local / outside purchase decision
Storage facilities
Schedule : P&M
Purpose ….
Resource leveling
Workshop facilities planning
Electrical infrastructure
Mobilization / Release commitments
Schedule : Work / Invoicing
Purpose ….
Peak capacities
Client input dates
Work valuation / Annual Budgeting
Working capital
Fabrication / enabling facilities
Thank You