Selling an Idea or a Product

Download Report

Transcript Selling an Idea or a Product

12th ANTAH GROUP CONFERENCE
11th- 14th AUGUST 2005
Guoman Hotel, PortDickson
Negeri Sembilan
PRIVATISATION OF LEBUHRAYA KAJANG - SEREMBAN
Project Information
Project Title
Privatisation of Lebuhraya Kajang Seremban (KASEH)
Concessionaire/ Client
KASEH Lebuhraya Sdn. Bhd.
Turnkey Contractor
IJM Construction Sdn. Bhd.
Design Consultant
HSS Integrated Sdn. Bhd.
Project Architect
Arkitek M & L Sdn. Bhd.
Toll Equipment Consultant (TCS &
TCSS)
Perunding Eagles
Sub-Contractor (Package 1B & 2A)
WCT Construction Sdn. Bhd.
Packages
Package 1B
Package 2A
Package 2B
Package 3
Project Information
Other Consultants
Scope Of Work
SADEC Projects Sdn Bhd
Technical Support Services
SADEC Sdn Bhd
Project Advisor
Zul Rafique and Partners
Legal
Hasrah Sdn Bhd
Land Consultant
Symonds Travers Morgan/MAG
Traffic Consultants
Khairi Consult Sdn Bhd
Independent Consulting Engineer
TRARS Consult Sdn Bhd
Road Safety Audit
Raine & Horne (M) Sdn Bhd
Land Valuer
PRIVATISATION OF LEBUHRAYA KAJANG SEREMBAN (KASEH)
Relationship Between Various Parties With Respect of the Works
Governmen
t
KASEH
Lenders
reporting
reporting
reporting
reporting
IJM
(Turnkey
Contractor)
information
MHA
Contractual Relationship
Functional Responsibility
Independent
Consulting
Engineer (ICE)
Khairi Consult
monitoring
Design &
Consultant (SC)
HSS Integrated
Arkitek M&L
Perunding Eagles
Highway Information
SECTION
SUB-SECTION
SECTIONAL
LIMITS
LOCATION
Section 1
1A
Section 2
1B
CH 0.00
to Kajang Selatan
Interchange
Kajang Selatan
Interchange to
CH 18200
CH 0.00
Kajang Selatan
to Kajang Selatan
I/C to
I/C
South of Pajam I/C
2A
2B
Section 3
-
CH18200
To
CH26000
CH26000
To
CH32700
CH32700
To
CH44275
South of Pajam I/C
To south of
Mantin I/C
South of Mantin I/C
to south of
Setul I/C
South of Setul I/C
To Paroi (partial
Grade Separated Junction)
7.80
6.70
11.575
TOTAL
LENGTH (Km)
1.44
16.76
44.275
INTERCHANGES
3 nos
2 nos
1 nos + Partial
Grade Separated Junction
7
3 nos
2 nos
1 nos
6
TOLL PLAZAS
REST & SERVICES
AREAS
2 nos
-
Note: Section 1A has been completed
2
-
Legend:
KAJANG
KASEH Highway
BEROGA
KAJANG SELATAN
INTERCHANGE
1
Proposed Realignment of Mantin-Setul Road
Revised Alignment between Jelebu to Panchor as
approved by UPEN
B34
SEMENYIH
SEMENYIH
INTERCHANGE
SELANGOR
NEGERI SEMBILAN
BERANANG
B18
N34
BANGI
BANGI
INTERCHANGE
1
N36
MANTIN
INTERCHANGE
PAJAM
INTERCHANGE
KLIA
INTERCHANGE
Revised Alignment
between
Jelebu to Panchor
as approved by UPEN
86
MANTIN
PAJAM
Proposed
Nilai - Pajam
Link Road
Lebuhraya ELITE
PANTAI
Alignment as per
Concession Agreement
N28
Proposed Realignment
of Mantin-Setul Road
JELEBU
INTERCHANGE
N38
SETUL
INTERCHANGE
PAROI
INTERCHANGE
86
51
NEW NILAI
INTERCHANGE
SEREMBAN
NILAI
INTERCHANGE
1
97
Proposed
Senawang – Paroi
Link Road
NILAI
1
N24
N38
SEREMBAN (N)
INTERCHANGE
PORT DICKSON
INTERCHANGE
PRIVATISATION OF LEBUHRAYA KAJANG SEREMBAN
SENAWANG
INTERCHANGE
Tolling Concept
FR51
FR1
FR86
FR1
Toll Plaza
N36
Toll Plaza
Kajang Selatan
Toll Plaza
Toll Plaza
B18
Kajang Selatan I/C
Setul
Toll Plaza
Jelebu
Toll Plaza
FR 1
,
Semenyih
Interchange
Section 1
Pajam
Interchange
Mantin
Interchange
Setul
Interchange
Section 2
Jelebu
Interchange
Paroi
Interchange
Section 3
Implementation Programme
YEARS
1997 - 2003
PACKAGES
J
F
M
A
M
J
J
A
2004
S
O
N
D
J
F
M
A
M
J
J
2005
A
S
O
N
D
J
F
M
A
M
J
J
2006
A
S
O
N
D
J
F
M
A
M
J
J
2007
A
S
O
N
D
J
F
M
A
Period
(months)
PACKAGE 1A
Completed
PACKAGE 1B
24
PACKAGE 2A
24
PACKAGE 2B
24
PACKAGE 3
24
Effective Date of CA
10th July 1997.
Construction
Supplemental Concession Agreement (SCA)
CHANGES TO THE CONCESSION AGREEMENT
In principle the Steering Committee for Privatisation have agreed to forward the following
changes to be part of the Supplemental Concession Agreement.
1
To adopt PLUS’s Toll Rates approved in 2002.
2
To extend to Concession Period by seven years ending 2037.
3
To extend the construction period to first quarter of 2007.
4
To reschedule the payment for the reimbursable land cost after
all commercial borrowings had been fully paid.
5
To accept and adopt the realignment proposal for Package 2B
(Mantin to Setul).
6
To allow for Sectional Tolling on completed sections.
Status of Land Acquisition
 PACKAGE 1A
-
FULL POSSESSION OF SITE OBTAINED
 PACKAGE 1B
-
FULL POSSESSION OF SITE OBTAINED
 PACKAGE 2A
-
FULL POSSESSION OF SITE OBTAINED
 PACKAGE 2B
-
MANTIN – SETUL
(PENDING FINALISATION OF REALIGNMENT)
 PACKAGE 3
-
LAND ACQUISTION 100% COMPLETED
Progress Status
Packages
Commencement Date
Package 1B
Package 2A
Package 2B
Package 3
15-Jul-04
To be advised by
KASEH
To be advised by
KASEH
To be advised by
KASEH
29.25
0
0
0
30.45
0
0
0
-1.2
0
0
0
-9
0
0
0
98.80%
99.10%
33.85%
47.67%
Physical Progress
Schedule
Ahead / Delays
Ahead / Delays (days)
Design Progress
Progress Photographs
Progress Photograph
Location : CH 0+800 FR 1 (Kajang Selatan Interchange)
Description : Pavement works in progress
Progress Photograph
Location : Bridge No. 1 (Kajang Selatan Interchange)
Description : Maintain Load Test for 500mm dia spun pile
Progress Photograph
Location : Bridge No. 1
Description : Rebar fixing for I-18 beam
Progress Photograph
Location : CH 3+300 (Mainline – Kajang Selatan Toll Plaza Area)
Description : Earthworks in progress
Progress Photograph
Location : CH 3+500 (Mainline - Kajang Selatan Toll Plaza Area)
Description : Earthworks in progress
Progress Photograph
Location : CH 0+525 (Semenyih Interchange)
Description : Bridge over Mainline
Progress Photograph
Location : CH 1500 – Slip Road 2B (Semenyih Interchange)
Description : Earthworks in progress.
Progress Photograph
Location : Semenyih Toll Plaza Area
Description : Installation of Rebar for DBC No. S-4
Progress Photograph
Location : CH 5+900
Description : Preparation of formation
Progress Photograph
Location : CH 6+600 (Mainline)
Description : Preparation of formation
Progress Photograph
Location : Bridge No.3 (B18)
Description : Location of Mainline Bridge at Semenyih-Bangi road (B18)
Progress Photograph
Location : Bridge No. 4 - Sg. Semenyih
Description : I-18 Beam casting in progress
Progress Photograph
Location : Bridge No. 4 - Sg. Semenyih
Description : Preparation of formation (view looking northbound)
Progress Photograph
Location : CH 8+300 (Mainline)
Description : Preparation of formation (view looking northbound)
Progress Photograph
Location : CH 10+850 (Mainline)
Description : Earthworks in progress
Progress Photograph
Location : CH 13+750 (Mainline)
Description : Preparation of formation (view looking southbound)
Progress Photograph
Location : Bridge No.6 - Sg. Batang Benar
Description : Bored pile works in progress
Progress Photograph
Location : Ch 14000 (Mainline)
Description : Preparation of formation level in progress
Progress Photograph
Location : CH 14+750 (Mainline)
Description : Laying of sub-base (view looking northbound)
Progress Photograph
Location : Bridge No.7
Description : Bore hole works for soil investigation in progress.
Progress Photograph
Location :CH 0+400 Slip Road (Pajam Interchange)
Description : Earthworks in Progress
Progress Photograph
Location :CH 1+200 Slip Road 2A/2B (Pajam Interchange)
Description : Earthworks in Progress
Progress Photograph
Location : DBC TR11-1 CH17660
Description : Construction of RC sump in progress
Progress Photograph
Location : Pajam Toll Plaza
Description : View of site office
THANK YOU
PRIVATISATION OF LEBUHRAYA KAJANG - SEREMBAN