Future Circular Collider (FCC) Study

M. Benedikt

gratefully acknowledging input from FCC global design study team

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

1

Outline

• • • •

Introduction, motivation, scope Parameters & design challenges Study organization and status Summary

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

2

Summary: European Strategy Update 2013

Design studies and R&D at the energy frontier

….“to propose an ambitious

post-LHC accelerator project at CERN

by the time of the next Strategy update”:

d) CERN should undertake design studies for

accelerator projects in a global context,

• • •

with emphasis on proton-proton and electron-positron high- energy frontier machines.

These design studies should be coupled to a vigorous accelerator

R&D programme, including high-field magnets and high-

gradient accelerating structures,

in collaboration with national institutes, laboratories and universities worldwide.

•

http://cds.cern.ch/record/1567258/files/esc-e-106.pdf

strategy adopted at Brussels in May 2013, during exceptional session of the CERN Council in presence of the European Commission

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

3

• • •

Future Circular Collider Study - SCOPE CDR and cost review for the next ESU (2018)

Forming an international collaboration to study:

•

pp-collider (FCC-hh)

 main emphasis, defining infrastructure requirements

~20 T

100 TeV pp in 80 km 80-100 km infrastructure

in Geneva area

e

+

e

collider (FCC-ee)

as potential intermediate step

p-e (FCC-he) option Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

4

CepC/SppC study (CAS-IHEP), CepC of 2014, e

+

e

-

CDR end collisions ~2028; pp collisions ~2042

Qinhuangdao (

秦皇岛)

CepC, SppC 54 km 70 km

Future Circular Collider Study

Michael Benedikt Yifang Wang th January 2015

“Chinese Toscana”

5

Previous studies in Italy (ELOISATRON

300km

), USA (SSC

87km

, VLHC

233km

), Japan (TRISTAN-II

94km

)

ex. ELOISATRON

Superdetectors: 25th Workshops  Supercolliders Proceedings of the 19th and of the INFN Eloisatron Project

ex. SSC ex. TRISTAN

Tristan-II Exploit synergies with other projects and prev. studies

ex. VLHC

VLHC Design Study Group Collaboration

June 2001

. 271 pp.

SLAC-R-591, SLAC-R-0591, SLAC-591, SLAC-0591, FERMILAB-TM-2149 http://www.vlhc.org

/ SSC Low Energy Component Prototypes

option 1

Synchrotron, IEEE Press, 1997

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

6

FCC hadron collider motivation: pushing the energy frontier

• • •

Seems the only approach to reach the 100 TeV c.m. range in the coming decades. Access to new particles (direct production) in the few TeV to 30 TeV mass range , far beyond LHC reach.

Much-increased rates for phenomena in the sub-TeV mass range →increased precision w.r.t. LHC and possibly ILC

M. Mangano

The name of the game of a hadron collider is energy reach

𝐸 ∝ 𝐵

𝑑𝑖𝑝𝑜𝑙𝑒

× 𝜌

𝑏𝑒𝑛𝑑𝑖𝑛𝑔

Cf. LHC: factor 3-4 in radius, factor 2 in field

factor 7-8 E Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

7

FCC-hh integration and options

LHC Geneva SPS PS LHC 27 km, 8.33 T 14 TeV (c.m.) “HE-LHC” 27 km,

20 T

33 TeV (c.m.) L. Bottura B. Strauss FCC-hh (alternative) 80 km,

20 T

100 TeV (c.m.) FCC-hh (baseline) 100 km,

16 T

100 TeV (c.m.)

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

8

Hadron collider FCC-hh parameters

• • • • • • • • • • • • •

Energy Circumference Dipole field (50 TeV) Dipole field (3 TeV inject.) 100 TeV c.m

.

~ 100 km (baseline) [80 km option] ~ 16 T (baseline) [20 T option] ~ 1 T (baseline) [1.2 T option] Bunch spacing

Bunch population (25 ns) Emittance normalised #bunches

Stored beam energy 25 ns [5 ns option]

1x10 11 p 2.15x10

10500 -6 m, normal.

8.2 GJ/beam

Available from SPS/LHC today 

3 TeV injector baseline for FCC-hh

# Interaction Points b *

Luminosity

2 main experiments 1.1 m [baseline]

5x10 34 cm -2 s -1

[baseline]

Synchroton radiation arc ~30 W/m/aperture (fill. fact. ~78% in arc) Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

9

Preliminary layout

First layout developed (different sizes under investigation)  Collider ring design (lattice/hardware design)  Site studies  Injector studies  Machine detector interface  Input for lepton option Will need iterations

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

10

Site study 93 km example

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015 Preliminary conclusions: • 93km fits geological situation really well, likely better than a smaller ring size.

• 100km tunnel seems also well compatible with geological considerations.

• The LHC could be used as an injector J. Osborne & C. Cook

11

FCC-hh: high-field magnet R&D

•

FHC baseline is 16T Nb 3 Sn technology for ~100 TeV c.m. in ~100 km

-

Develop Nb 3 Sn-based 16 T dipole technology (at 4.2 K?)

, conductor developments short models with sufficient aperture (40 – 50 mm) and accelerator features (margin, field quality, protect-ability, cycled operation).

Goal: 16T short dipole models by 2018/19 (America, Asia, Europe)

•

In parallel HTS development targeting 20 T (option and longer term) Goal: Demonstrate HTS/LTS 20 T dipole technology

: • 5 T insert (EuCARD2), ~40 mm aperture and accelerator features • Outsert of large aperture ~100 mm, (FRESCA2 or other)

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

12

20 T: Nb-Ti & Nb 3 Sn & HTS

high-field dipole magnets

Arc magnet system will be the major cost factor for FCC-hh

“hybrid magnets” example block-coil layout

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015 only a quarter is shown L. Rossi, E. Todesco, P. McIntyre

13

SC magnets for detectors

    Need BL 2 ~10 x ATLAS/CMS for 10% muon momentum resolution at 10-20 TeV.

Solenoid: B=5T, R in =5-6m, L=24m

 > 5000 m 3 of Fe in return joke 

size is x2 CMS. Stored energy: ~ 50 GJ

alternative: thin (twin) lower-B solenoid at larger R to capture return flux of main solenoid

Forward dipole à la LHCb: B~10 Tm

F. Gianotti, H. Ten Kate

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

14

•

FCC-hh: some design challenges

Stored beam energy: 8 GJ/beam (0.4 GJ LHC) = 16 GJ total

 equivalent to an Airbus A380 (560 t) at full speed (850 km/h)   

Collimation, beam loss control, radiation effects: very important Injection/dumping/beam transfer: very critical operations Magnet/machine protection: to be considered from early phase Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

15

Synchrotron radiation of protons

At 50 TeV even protons radiate significantly Critical energy 4.3keV, close to B-factory Protons loose energy

Radiation damping

 

Emittance improves with time Useful for lumi levelling?

• Transverse damping time ~1 hour

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

16

Synchrotron radiation/beam screen

High synchrotron radiation load (SR): ~30 W/m/beam (@16 T)

5 MW total in arcs

 (LHC <0.2W/m, total heat load 1W/m) • • • •

Beam screen to capture SR and “protect” cold mass Power mostly cooled at beam screen temperature; Only minor part going to magnets at 2 – 4 K Optimisation of temperature, space, vacuum, impedance, e-cloud required.

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

17

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

contributions: beam screen radiation)

• •

Contributions to cryo load: beam screen (BS) & cold bore (BS heat radiation) At 1.9 K cm optimum BS temperature range: 50-100 K; But impedance increases with temperature

instabilities 40-60 K favoured by vacuum & impedance considerations

100 MW refrigerator power on cryo plant

P. Lebrun, L. Tavian

18

Lepton collider FCC-ee

• Here the name of the game is

luminosity: as many collisions as possible

high beam current, small beam size.

• The energy reach of circular e+e- colliders is limited due to synchrotron radiation of charged particles on curved trajectory: D

E

∝

(E kin /m 0 ) 4 /

r m prot = 2000 m electr

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

19

Lepton collider FCC-ee parameters

•

Design choice: max. synchrotron radiation power 50 MW/beam

• Defines the max. beam current at each energy • 4 Physics working points • Optimization at each energy (bunch number & current, etc).

Parameter E/beam (GeV) I (mA)

Bunches/beam Bunch popul. [10 11 ]

Z 45 1450

16700 1.8

28.0

WW 80 152

4490 0.7

12.0

H 120 30

1360 0.46

6.0

tt bar 175 6.6

98 1.4

1.7

LEP2 104 3

4 4.2

0.012

L/IP (10 34 cm -2 s -1 ) • Large number of bunches at Z and WW and H requires 2 rings.

• High luminosity means short beam lifetime (few mins) and requires continues injection.

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

20

FCC-ee: RF parameters and R&D

• • •

Synchrotron radiation power: 50 MW per beam Energy loss per turn: up to 7.5 GeV (at 175 GeV, t)

• • System dimension compared to LHC:

LHC 400 MHz

2 MV and ~250 kW per cavity, (8 cavities per beam) FCC-ee: ~600 cavities 20 MV / 180 kW RF

12 GV / 100 MW

•

R&D Goal is optimization of overall system efficiency and cost!

1. SC cavity R&D

 •

large

𝑄 0

, high gradient, acceptable cryo power!

Recent promising results at 4 K with Nb3Sn coating on Nb at Cornell, • 800 ℃ ÷ 1400 ℃ heat treatment JLAB, beneficial effect of impurities FNAL.

2. High efficiency RF power generation from electrical grid to beam

• Amplifier technologies • Klystron efficiencies >65%, alternative RF sources as solid state amplifier, etc.

3. High reliability Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

21

FCC-ee top-up injector

Beside the collider ring(s), a booster of the same size (same tunnel) must provide beams for top-up injection o o o o same RF voltage, but low power (~ MW) top up frequency ~0.1 Hz booster injection energy ~5-20 GeV bypass around the experiments injector complex for e + and e beams of 10-20 GeV o Super-KEKB injector ~ almost suitable

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015 A. Blondel

22

RF?

FCC-ee preliminary layout

INJ + RF EXP + RF INJ + RF RF? COLL + EXTR + RF COLL + EXTR + RF RF? EXP + RF EXP + RF Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

EXP + RF RF? 23

• • • •

FCC study status

Study launched at FCC kick-off meeting in Feb. 2014 Presently forming a global collaboration based on general MoU between CERN and individual partners. Specific addenda for each participant.

First international collaboration board meeting on 9. and 10. September 2014 at CERN. Chair Prof. L. Rivkin (PSI/EPFL).

Design study proposal for EU support in the Horizon 2020 program was submitted, evaluation expected for Jan 2015.

• First FCC Week workshop from 23. to 27. March in Washington DC.

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

24

FCC work plan study phase

2014 2015 2016 2017 2018 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

Prepare Kick-off, collaboration forming,

study plan and organisation Ph 1: Explore options “weak interaction”

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3

4 large FCC Workshops Workshop & Review

identification of baseline Ph 2: Conceptual study of baseline “strong interact.” Workshop & Review, cost model, LHC results

study re-scoping?

Ph 3: Study consolidation 1 st 23 FCC workshop – 27 March 2015 Workshop & Review

contents of CDR Report Release CDR & Workshop on next steps

Q4

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

25

CERN roadmap and FCC planning

CDR and Cost Review 2018

Kick-off meeting: 11 th Nov. 2013 (Daresbury) FCC Kick-off meeting February 2014 Study CDR and Cost Review for 2018 Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

Project 26

FCC MoU Status

42 collaboration members & CERN as host institute , 7. Jan. 2015 ALBA/CELLS, Spain U. Bern, Switzerland BINP, Russia CASE (SUNY/BNL), USA CBPF, Brazil CEA Grenoble, France CIEMAT, Spain CNRS, France Cockcroft Institute, UK U Colima, Mexico CSIC/IFIC, Spain TU Darmstadt, Germany DESY, Germany TU Dresden, Germany Duke U., USA EPFL, Switzerland Gangneung-Wonju Nat. U., Korea U Geneva, Switzerland Goethe U. Frankfurt, Germany GSI, Germany Hellenic Open U, Greece HEPHY, Austria IFJ PAN Krakow, Poland INFN, Italy INP Minsk, Belarus U Iowa, USA IPM, Iran Istanbul Aydin U. ,Turkey JAI/Oxford, UK JINR Dubna, Russia KEK, Japan KIAS, Korea King’s College London, UK Korea U. Sejong, Korea MEPhI, Russia Northern Illinois U., USA NC PHEP Minsk, Belarus PSI, Switzerland Sapienza/Roma, Italy UC Santa Barbara, USA U Silesia, Poland TU Tampere, Finland Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

27

FCC Work and Organisation (i)

-

Work/meeting structures established based on INDICO, see: FCC Study: https://indico.cern.ch/category/5153/

-

In particular: FCC-hh Hadron Collider Physics and Experiments VIDYO meetings

-

https://indico.cern.ch/category/5258/ Contacts: [email protected]

, [email protected]

, [email protected]

-

FCC-ee Lepton Collider (TLEP) Physics and Experiments VIDYO meetings

-

https://indico.cern.ch/category/5259/ Contacts : [email protected]

, [email protected]

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

28

FCC Work and Organisation (ii)

-

FCC-hh Hadron Collider VIDYO meetings

-

https://indico.cern.ch/category/5263/

-

Contacts: [email protected]

-

FCC-hadron injector meetings

-

https://indico.cern.ch/category/5262/

-

Contacts: [email protected]

-

FCC-ee (TLEP) Lepton Collider VIDYO meetings

-

https://indico.cern.ch/category/5264/

-

Contacts: [email protected]

,

-

FCC infrastructure meetings

-

https://indico.cern.ch/category/5253/

-

Contacts: [email protected]

, [email protected]

Future Circular Collider Study

Michael Benedikt Epiphany 2015 Cracow, 8 th January 2015

29

++...

First FCC Week Conference Washington DC 23-27 March 2015

http://cern.ch/fccw2015

First FCC Week, Washington DC 23-27 March 2015 – DRAFT SCHEDULE

hoping to see you there!

Conclusions

• There are strongly rising activities in energy-frontier circular colliders worldwide.

• The FCC collaboration is being formed with CERN as host laboratory, to conduct an international study for the design of Future Circular Colliders (FCC).

• Worldwide collaboration in physics, experiments and accelerators will be essential to advance and reach the goal of a CDR by 2018.

• FCC presents challenging R&D requirements in SC magnets, SRF and many other technical areas.

•

Need to establish global collaboration and use all synergies to move forward!