Transcript Slide 1
SEBUTHARGA BRIEFING
PROVISION OF UPGRADING WORKS OF THE
MAIN SWITCH BOARD 1 (MSB1)
AT MIMOS WAFER FAB 2
www.mimos.my
© 2008 MIMOS Berhad. All Rights Reserved.
MIMOS COMPLEX
FAB1
FAB2
www.mimos.my
© 2008 MIMOS Berhad. All Rights Reserved.
FAB2 INCOMING
Air Compressor
Wafers
Compressed Dry Air (CDA)
Process Cooling Water (PCW)
Process Cooling Water
(PCW Heat Exchanger)
linked
Ultrapure Process Water
(UPW)
Chiller
DI Water Plant
Air Conditioned
& Humidity
Air Handling Units
(AHU)
Waste Water
SSB
Vacuum System
Production
Equipment
Waste Water Treatment
Central Exhaust System
FACILITIES SUPPORT SERVICES AT FAB 2
11KV/208V
TX
11KV/415V
TX
MSB1 LAYOUT - OVERALL
www.mimos.my
© 2008 MIMOS Berhad. All Rights Reserved.
Chilled pump
Air compresor 1
Air compresor 2
Chiller 2
Chiller 3
Cond pump
Chiller 1
CURRENT MCC-AC
1600 A SSB (MCC-AC)
MSB1
PROBLEM STATEMENT
• 1600A SSB under capacity. 3 chillers can’t run in parallel
• All critical support services in SSB. Once trip, all
services affected
PROPOSED SOLUTION
• Expand the MSB 1 and create another SSB.
• Split the critical services
EMSB1
AMF Board
EXTEND
MSB 1
Chiller 2
Cond pump
Chilled pump
Air compresor 2
Chilled pump
Cond pump
Chilled pump
Air compresor 1
Air compresor 2
Chiller 2
Chiller 3
Cond pump
Chiller 1
PROPOSED UPGRADING OF MSB1
1600 A SSB (MCC-AC)
1000 A NEW SSB
MSB1
EMSB1
AMF Board
PROJECT DURATION
• 4 Weeks after receiving LOA
• SHUTDOWN DATE: 25/06/2011
www.mimos.my
© 2008 MIMOS Berhad. All Rights Reserved.
THANK YOU