Transcript Slide 1
SEBUTHARGA BRIEFING PROVISION OF UPGRADING WORKS OF THE MAIN SWITCH BOARD 1 (MSB1) AT MIMOS WAFER FAB 2 www.mimos.my © 2008 MIMOS Berhad. All Rights Reserved. MIMOS COMPLEX FAB1 FAB2 www.mimos.my © 2008 MIMOS Berhad. All Rights Reserved. FAB2 INCOMING Air Compressor Wafers Compressed Dry Air (CDA) Process Cooling Water (PCW) Process Cooling Water (PCW Heat Exchanger) linked Ultrapure Process Water (UPW) Chiller DI Water Plant Air Conditioned & Humidity Air Handling Units (AHU) Waste Water SSB Vacuum System Production Equipment Waste Water Treatment Central Exhaust System FACILITIES SUPPORT SERVICES AT FAB 2 11KV/208V TX 11KV/415V TX MSB1 LAYOUT - OVERALL www.mimos.my © 2008 MIMOS Berhad. All Rights Reserved. Chilled pump Air compresor 1 Air compresor 2 Chiller 2 Chiller 3 Cond pump Chiller 1 CURRENT MCC-AC 1600 A SSB (MCC-AC) MSB1 PROBLEM STATEMENT • 1600A SSB under capacity. 3 chillers can’t run in parallel • All critical support services in SSB. Once trip, all services affected PROPOSED SOLUTION • Expand the MSB 1 and create another SSB. • Split the critical services EMSB1 AMF Board EXTEND MSB 1 Chiller 2 Cond pump Chilled pump Air compresor 2 Chilled pump Cond pump Chilled pump Air compresor 1 Air compresor 2 Chiller 2 Chiller 3 Cond pump Chiller 1 PROPOSED UPGRADING OF MSB1 1600 A SSB (MCC-AC) 1000 A NEW SSB MSB1 EMSB1 AMF Board PROJECT DURATION • 4 Weeks after receiving LOA • SHUTDOWN DATE: 25/06/2011 www.mimos.my © 2008 MIMOS Berhad. All Rights Reserved. THANK YOU www.mimos.my © 2008 MIMOS Berhad. All Rights Reserved.