Transcript Document

W1.6: Life Cycle
Technology Assessment
Wednesday, March 10 8:00 - 9:15 a.m.
Thomas M. Keel, M.B.A.
Representing CABA
7/7/2015
1
Discussion Topics
Introduction
Snapshot - Today
Trends and Initiatives
Major Challenge
Major Driver
Tomorrow…?
7/7/2015
2
Introduction – CABA IIBC
Continental Automated Buildings
Association (CABA), Intelligent &
Integrated Buildings Council (IIBC)
specifically will review opportunities,
strategize, take action, and monitor
initiatives that relate to integrated systems
and automation in the "large building"
sector.
7/7/2015
3
Introduction – Task Force 3
CABA Task Force 3 – The Life Cycle Costs of Intelligent
and Integrated Buildings
The charge: Task Force 3 (TF3) will develop a white
paper on the “Life Cycle Costs of Integrated - Open
Standards Based Building Technologies” as compared to
traditional stand-alone, closed system buildings.
The task: to analyze BAS-related costs
The goal: to develop verifiable documentation for LCC
(time-value of money) comparisons.
7/7/2015
4
Introduction–LCC Definition
Section 707 of Executive Order 13123
defines life cycle costs as “…the sum of
present values of investment costs, capital
costs, installation costs, energy costs,
operating costs, maintenance costs, and
disposal costs over the life-time of the
project, product, or measure.”
7/7/2015
5
Introduction–LCC Definition
According to Dell’Isola and Kirk, “…LCC is
a technique that satisfies the requirements
of owners for adequate analysis of total
costs.”
Dell’Isola, A. and S. Kirk, Life Cycle Costing for Facilities, Reed Construction Data (page 12)
7/7/2015
6
Introduction–LCC Definition
Life Cycle Costing incorporates both


7/7/2015
Life Cost Planning, which occurs during
development, and
implementation of that plan by Life Cost
Analysis as the asset is used or occupied.
7
Introduction - LCCA
The life cycle costing analysis (LCCA)
method is mandated by Title 10, Code of
Federal Regulations
7/7/2015
8
Introduction - LCCA
10 CFR Sec. 436.12 Life cycle cost methodology
states:

“The life cycle cost methodology for this
part is a systematic analysis of relevant costs,
excluding sunk costs, over a study period,
relating initial costs to future costs by the
technique of discounting future costs to
present values”.
7/7/2015
9
Introduction - LCCA
Guidance on Life-Cycle Cost Analysis
Required by Executive Order 13123 April
26, 2000 Section 401 requires that
“Agencies shall use life-cycle cost analysis
in making decisions about investments in
products, services, construction, and other
projects to Life Cycle Assessment (LCA)
7/7/2015
10
Introduction – LCC History
1930, Eugene L. Grant, Principles of Engineering Economy.
1933, Comptroller General of the United States, tractor acquisition by predicted total cost after 8,000
hours of operation, General Accounting Office (GAO).
1940 -1950, Lawrence D. Miles, concept of value engineering at the General Electric Company.
1952, AT&T, Engineering Economy.
1950 – 1960, P.A. Stone, in England at the Building Research Station.
1965, Assistant Secretary of Defense published an influential report analyzing DoD contracts.
1971, DoD Directive 5000.1 mandates LCC procurement for major systems.
1972, Comptroller General of the United States issued an exhaustive and devastating report on the life
cycle costs for U.S. hospital facilities.
1972, Alphonse J. Dell’Isola, Value Engineering in the Construction Industry.
1973, DoD, Life Cycle Costing Guide for System Acquisition.
1974, Florida and 1975, Alaska became the first states to require LCC
1975, Energy Policy and Conservation Act and the Energy Conservation Act influenced procurement
practices.
1975, ASHRAE Standard 90-71
1979, Building Energy Performance Standards (BEPS)
National Institute of Standards and Technology (NIST), NIST Handbook 135 – Life Cycle Costing Manual
for Federal Energy Management Program.
1981, Alphonse J. Dell’Isola and Dr. Stephen J. Kirk, Life Cycle Costing for Design Professionals.
1999, ASHRAE Handbook HVAC Applications, Chapter 35: “Owning and Operating Costs”.
7/7/2015
11
Introduction
Why promote life cycle costing?

7/7/2015
"the bottom line is the bottom line".
12
Introduction – Why this
Research
Do owners buy technology?


7/7/2015
They buy solutions to their problems.
They buy solutions that improve their
bottom line.
13
Major Driver
Sustainability (EPA, DOE, NIST)





7/7/2015
ASHRAE 90.1, 90.2, 62, 62.2, 55 (ASHRAE.org)
LEED (U. S. Green Building Council, usgbc.org)
ANSI/MSE 2000, GA Tech Economic Development Institute
ISO 1400 (iso.ch)
BEPAC
14
Introduction – Why this
Research
The perception that integrated systems are
more expensive to build is a big hurdle.
“Smart buildings are generally more expensive to build than
conventionally designed buildings. However, the added value of
smart building infrastructure results in much lower life-cycle
costs…". Design Brief for Smart Buildings, sponsored in part by
BOMA, (data from the 1990s).
7/7/2015
15
Introduction – Why this
Research
Life cycle costing research will
substantiate that LCC-based
construction is the lowest overall cost
of construction.
7/7/2015
16
Introduction - Strategy
To develop verifiable documentation for
LCC (time-value of money) comparisons
To convince owners and developers to
employ LCC methodology when buying
building automation.
7/7/2015
17
Snapshot - BAS Market
North American BCS [building control
systems] installation markets were just
under $1 billion in 2002.
Installation markets include: application
engineering, system installation, system
start up and calibration, and customer onsite training.
Source: Ron Caffrey and Terry McMahon, BCS Partners, Leonia, NJ
7/7/2015
18
Snapshot - BAS Market
Almost 10% of U.S. nonresidential
buildings have automated energy
management.



Over 500,000 ft2 = 70% +
200-500,000 ft2 = 55%
100-200,000 ft2 = 50%
Source: Ron Caffrey and Terry McMahon, BCS Partners, Leonia, NJ
7/7/2015
19
Snapshot – BAS Forecast
By 2007, the North American building controls
market could approach $4 billion (worldwide
almost $13 billion).
Adding fire alarm, intrusion detection, and
access control brings the worldwide market for
indoor environment regulation and security to
nearly $22 billion for nonresidential buildings.
Source: Ron Caffrey and Terry McMahon, BCS Partners, Leonia, NJ
7/7/2015
20
Trends and Initiatives
The Building Controls industry has made great
strides in the creation of communications
standards. Both BACnet and LonTalk are now
viable, commercially accepted solutions that
provide owners with open communications.
7/7/2015
21
Trends and Initiatives
BACnet has worldwide support and is
maintained by a professional society under rules
that provide open access and cannot be
dominated by companies with particular
commercial interests.
LonTalk® certification program is limited to
devices that contain a defined interface. Both
software and hardware are the end-certified
products. Only LonMark® Partner and Sponsor
Members can have products certified.
7/7/2015
22
Trends and Initiatives
The ever lowering cost of Ethernet / TCP/IP /
XML communications is finding its way into our
industry.
XML: The mission of the CABA Open Building
Information Xchange (oBIX) is to work
cooperatively in an open environment to create
a non-binding guideline for the use of Internet
communications standards such as XML and
Web Services for use in broad facility
management.
7/7/2015
23
Trends and Initiatives

Create an open, non-proprietary specification
www.ctrlspecbuilder.com © 2003 Automated
Logic Corporation 1150 Roberts Blvd.,
Kennesaw, Georgia, 30144 USA
The document, a Microsoft® Word file, is based
on ASHRAE Guideline 13-2000: Specifying
Direct Digital Control Systems and follows the
Construction Specifications Institute (CSI)
MasterFormat—Division 15 Mechanical, Section
15900 HVAC Instrumentation and Controls to
create an open, non-proprietary specification for
building automation systems.
7/7/2015
24
Analyzing the Life Cycle
Cost of Integrated
Building Systems
Produced by: Thomas J. Lohner, P.E.
Vice President, TENG Solutions
7/7/2015
25
Systems Integration Comparative Life Cycle
Cost
You Can Not Afford Not to do it Right
7/7/2015
26
Facility Integration
Life Cycle Costs
First Cost
Changes, Additions & Upgrades
Operating & Maintenance
Utility Costs
7/7/2015
27
Typical Buildig
Approach to Automatio
No
Itegratio
5 User
Iterface
!
Emergency Generator
Workstatios
!
Main Service Switchgear
Computer
Room A/C
UPS
Fire Management System
7/7/2015
Door Access Control &
Intrusion Detection
Lighting Control System
HVAC Control System
28
Non-Integrated Building
Engineering Left up to Contractors
Sole Sourcing Required to Provide
Integration - $$$$
Stand Alone Systems - Single Purpose
Nobody Responsible for Technology
Integration
7/7/2015
29
Partial
Proprietary
Control Sub-systems
Itegratio
Clie Cocept
FMS
t
SNMP over
IP
Computer
Room A/C
Workstatio

Datab
ase
Serve
r
Main Service Switchgear
Web
Serve
r
Facility
IP Network
Secu
rity
Coso
le
Web
Serve
r
Modb
us
Emergency Generator
Web
Serve
r
Web
Serve
r
Web
Serve
r
UPS
7/7/2015
Fire Management System
Door Access Control &
Intrusion Detection
Lighting Control System
HVAC Control System
30
Partial Integration Issues
Software Integration on IP networks
Use Web Enabled - FMS Application
Program
Methodology Employed for Existing
Buildings
Hardware Intensive - Many I/O Servers
7/7/2015
31
BENEFITS
Partial Integration
Single User Interface for all Systems
Web based GUI - Defacto Standard
Permits Migration to Open Control
Networks - Competitive Bids !
Permits Development of Campus Wide
Relational Database
Database Permits - Maintenance Management
, Energy Management , Asset Management, etc.
7/7/2015
32
Full Itegratio
Open Standards
Based Control Sub-systems
Cocept
Clie
t
SNMP over
IP
Computer
Room A/C
FMS
Workstatio

Facility
IP Network
Secu
rity
Coso
le
Web
Serve
r
Datab
ase
Serve
r
Modb
us
Main Service Switchgear
Web
Serve
r
Emergency Generator
Web
Serve
r
LONTALK - EIA
709.1 & BACNET
 ANSI/ASHRAE
135A
UPS
7/7/2015
Fire Management System
Door Access Control, Intrusion Detection, Lighting & HVAC Control System
33
Full Integration Issues
Open Standards Applied Where Possible
I/O Servers Minimized
Number of Devices Reduced - Shared
Information
7/7/2015
34
BENEFITS
Full Integration
Same as Partial Integration Approach
PLUS
Competitive Bids in each Building
Integrated Building Sub-systems

Lighting, HVAC, Power Management and
Security
Lowest Life Cycle Cost Approach
7/7/2015
35
Life Cycle Cost
Analysis Assumptions
150,000 SF Building
Major M & E Equipment Cost - $6.00/SF ($18.00/SF TOTAL)
Proprietary Systems Life Cycle - 7 years (FAR)

Replacement Cost = 125% of the Initial System Cost

50% of the Proprietary Systems are Replaced (Next Generation)

20% of the Open Systems are Replaced (Age & Obsolescence)
Average Cost per Control Device - $400
Open and Proprietary Control Devices Base Bid Costs are the Same
Training Costs - $3000/ GUI; $1500/ Protocol; 50% of 1st year cost for
years 2 and up
7/7/2015
36
Life Cycle Cost
Analysis Assumptions
Dynamic
Control Subsystems
HVAC Controls
Lighting Controls
Power Monitoring
Intrusion Detection
Total
7/7/2015
Base Year
Base Year Annual
Initial
Service Changes &
Cost
Contract Modificatons
($/SF)
($)
(% of 1st Cost)
$1.5/SF
$1.0/SF
$0.5/SF
$0.3/SF
$3.3/SF
15,000
10,000
5,000
3,000
$ 33,000
2%
3%
1%
2%
$39,000
37
Comparative First Costs
System Component
Graphical User Interface Hardware & Software
Equipment Networking Uprades
Web Servers
Control Device Reduction (5%)
NonIntegrated
Partial
Building Integration
Full
Integration
5 @ $15K
0
0
0
1 @ $20k
4 @ $2k
5 @ $10k
0
1 @ $20k
4 @ $2k
3 @ $10k
-24750
TOTAL
$75,000
$78,000
$33,000
Full Integration Savings
$42,000
$45,000
No Account For Division 17000 Savings - 20 to 30%!!!
No-Itegrated HVAC, Lightig
& Itrusio Detectio
Echelo World Headquarters
Dimmable
Lighting Control
VAV Boxes
No Occupancy Control
Blinds & 24v Wiring
Itegrated HVAC, Lightig, Itrusio
Detectio & Blid Cotrol
Echelo World Headquarters
User Scene Control Switch
Lighting, HVAC &
Occupancy Sensor Control
Trunk
Sensor and 120v Wiring
Changes, Additions and
Upgrades Issues
Cost Premium Paid for Additions &
Changes to Proprietary Controls
Limit Scope of Future Improvements and
Modifications
Cost Premium for Non Competitive
Service Contracts
7/7/2015
41
Changes, Additions and Upgrades
(Annual Costs- 2nd Year & On )
O & M Cost Issues
Service Contracts
Future Additons &
Remodeling
Future Software
Upgrades
Year 7 Replacement
Cost Reserve ( 9% APR)
Total
Full Integration Savings
Non
Competitive
NonCost
Integrated
Partial
Full
Premium
Building Integration Integration
25%
$
41,250
$
41,250
$
33,000
25%
$
49,500
$
49,500
$
39,600
5 @ $1k
$
$
$
33,629
1 @ $2k
1 @ $2k
$
33,629
$
13,452
129,379 $
126,379
$
88,052
41,327
$
38,327
Operating and Maintenance
(Annual Costs- 2nd Year & On )
System Component
NonIntegrated
Partial
Building Integration
Training
$
11,250
Improved O & M Staff Efficiency
0
IT Support
5 @ $2k
Management Reporting
0
Total
21,250
Full Integration Savings $17,500
$
5,250
SOFT
1 @ $3k
(3 @ $1k)
$
5,250
$
1,500
Computerized Maintenace Management
$
(Extend Major M & E Equipment Life; 25yrs vs 20yrs)
Future Worth ($ @ Yr 20)
$
Present Worth (P/F @ 9%)
$
Full
Integration
$
3,750
SOFT
1 @ $3k
(3 @ $1k)
$
3,750
25,000 First Cost
180,000
32,112
Typical Energy Use Profile
Other (Elevators, etc.)
5% Ave Annual Energy
Use
Power
25% Ave Annual Energy
Use
$0.07 / SF / YR
$10,000 / YR
$0.33 / SF / YR
Lighting
HVAC
Power
Other
$50,000 / YR
HVAC
Lighting
30% Ave Annual Energy
Use
40% Ave Annual Energy
Use
$0.4 / SF / YR
$0.53 / SF / YR
$60,000 / YR
$80000 / YR
TOTAL
$1.33 / SF / YR
$200,000 / YR
Energy Costs
(Potential Annual Cost Savings)
System Component
NonSavings Energy Integrated
Factor Cost ($) Building
Partial
Integration
Full
Integration
Integrated Lighting & HVAC Control
Improved Load Factor ( .5 to .55)
Better Maintained Equipment
5%
5%
1%
$60,000
$200,000
$60,000
0
0
0
0
$10,000
$600
$3,000
$10,000
$600
Coordinated Supply/Demand EMS Strategies
5%
$200,000
0
$10,000
$10,000
$0
$20,600
$23,600
Integrated Building Control System
Savings
Conclusion:
Full Integration will Result in the Lowest
Net Present Value
The Value of the Integrated Approach will
Increase w/ IT Advances
Information will be your Competitive
Advantage
7/7/2015
46
System Integration
Life Cycle Cost Summary
NonIntegrated
Partial
Full
Life Cycle Cost Component Building Integration Integration
Comparitive First Cost
Changes, Upgrades & Additions
Operating & Maintenance
Utility Cost
$75,000
$129,379
$21,250
$200,000
Net Present Value $2,325,232
Discount Rate
9%
Life Cycle Period (yrs)
10
Savings $551,739
$78,000
$126,379
$5,250
$179,400
$33,000
$88,052
$3,750
$179,400
$2,074,091
$1,773,493
$300,598
Next Steps
IIBC TF – 3 (Develop LCC
Model)
Building Construction Delivery




7/7/2015
Who is responsible for Technology??
Integrated Systems must be designed
Performance Specs are not adequate
Owners must require as a deliverable
48
TF – 3 Major Challenges
Locating the data sources
The need for relevant quality data


It is costly and time-consuming to collect.
Verifying the validity of the data
Sorting out design-bid-build projects from
design-build
Not measuring LCC and VE that resulted in:


7/7/2015
Cheaper components
Reduced functionality
49
Case Study
7/7/2015
50
GSA Federal Complex - Region 5
One of TENG’s/World’s Largest
Example of Open Building Automation
Migration to LonWorks began in 1996
HVAC, Lighting, Power, Security
2000+ Control Products, 15,000+ points
Based on EIA Standard 709.1 (LonTalk)
Over 2.5 Million Sq. Ft. (3 facilities)
6 Different Contractors, 14
Manufacturers,
6 Construction Phases
GSA WAN Connectivity
7/7/2015
Chicago, Illinois
51
LCC Impact
Implementation Cost: $8,000,000+ over 7
years
Savings Estimate: Energy, Replacements,
Manpower, Service Contracts, Software

Energy
$12,000/day Utility Costs
20% Savings - $2400/day - $876,000/year


Achieved Presidential Mandate 1 Year Ahead of Schedule
Replacements
Less Than $100,000 over 7 years
Savings - $4,000,000 (3-7 year lifecycle)

7/7/2015
Conservative Estimate (1/2 of Installed Cost)
52
LCC Impact

Manpower
$4800/Day Direct Labor (10 x $20 x 24)
20% More Efficient - $960/day - $350,400/year

Service Contracts
Savings - $100,000+/Year

Software
Savings - $50,000+/Year
Conservative (4 year basis) Total
Savings:
 $10,907,200
7/7/2015
53