Proposed Interim Guidance – Small Starts

Download Report

Transcript Proposed Interim Guidance – Small Starts

FTA’s Small Starts Program
Charlotte, North Carolina
October 11, 2007
Small Starts Program Overview


Program funding at $200m/yr
Simplified Process




Alternatives Analysis
Project Development
Construction
Simplified Project Construction Grant Agreement





Scope
Cost
Schedule
Federal Funding Maximum Amount and Schedule
Local Funding Sources
2
Eligibility - Costs
• Total cost < $250 million
• Small Starts share < $75 million
• Exempt projects (< $25 million New Starts
share) may:
– Remain exempt until Final Rule – then be
evaluated and rated if construction not started
or
– Be evaluated and rated now as Small Starts
3
Program Goal
Fund meritorious projects
• Develop reliable information on project benefits and
costs
• Ensure projects treated equitably nationally
• Facilitate communication between FTA, transit
industry and Congress
4
Guiding Principles for Development
of Small Starts Interim Guidance
• Evaluation process should not change
dramatically from existing process to minimize
rating changes given those anticipated in the
NPRM
• Requirements should ensure level playing field
for all projects
• Requirements should be mode-neutral
• Costs, benefits and impacts should be developed
using established methodologies
5
Eligibility - Project Definition
• Project a fixed guideway for 50% or more of its
length during peak, or
• Project a corridor bus project including at least:
–
–
–
–
–
Transit stations
Traffic signal priority or pre-emption
Low floor buses or level boarding
Premium service branding
10 min peak/15 min off-peak headways at least 14
hours a day
6
Eligibility – Additional Features for Very
Small Starts
• Simple, low-cost projects that qualify for
streamlined process
• Very Small Starts eligibility criteria:
– Existing daily riders over 3,000
– Total cost under $50 million
– Under $3 million per mile, excluding rolling stock
7
Interim Guidance
Evaluation of Small Starts Project
Justification
Subset of Existing New Starts Criteria:
- Land-use
- Cost-effectiveness
- Other factors, including economic
development, congestion and pricing
strategies, and the case for the project
8
Interim Guidance
Evaluation of Local Financial Commitment
• Projects receive “medium” for local financial commitment
if:
– Reasonable plan to secure local share (all non-New Starts
funding committed for PCGA)
– Project O&M under 5 percent of agency operating budget
– Agency in solid financial condition
• Projects that cannot meet the conditions above submit a
financial plan
– According to FTA guidance
– Covering period up to and including opening year
– Evaluated based on criteria used for New Starts
9
Simplification of Small Starts Program
Requirements Compared to New Starts
Very Small Starts
– AA could contain two alternatives and require no more information
than developed for a project funded only with local funds
– Project justification evaluation requires meeting easily developed
information on costs and existing ridership
– Local financial commitment evaluation could require meeting 3
easily demonstrated conditions; otherwise financial plan extends
only to opening year
– No final design approval
– Simplified PMP and cost reviews
– Simplified PCGA
10
Simplification of Small Starts Program
Requirements Compared to New Starts
Small Starts
– AA could contain few alternatives, use forecasts of transportation
benefits with simplified methods and address project opening, not
20-year forecasts
– Land use submission reduced for project justification
– Local financial commitment evaluation could require meeting 3
easily demonstrated conditions; otherwise financial plan extends
only to opening year
– No final design approval
– Simplified PMP and cost reviews
– Simplified PCGA
11
Projects in Project Development
•
•
•
•
•
Los Angeles Metro Rapid Bus Closure
Kansas City Troost Corridor BRT
Springfield (OR) Pioneer Parkway BRT
King Co (WA) Pacific Highway South BRT
Portland Streetcar Loop
12
Pending Project Development Requests
Projects
• Mason (CO) Transportation Corridor BRT
• Fitchburg (MA) Commuter Rail
• South Corridor BRT in Grand Rapids, MI
• Perris Valley (CA) Metrolink Commuter Rail Extension
• Others in St. Petersburg, Sarasota, Tucson, San Diego,
San Francisco, Oakland, Reno, Des Moines, and Aspen
Common Issues
• AA not completed
• Finances not identified
• Project not in metro plan
13
Planned Schedule for Rulemaking
• July 2007: Publication of the Notice of Propose
Rulemaking for New and Small Starts
• July 2007: Publication of Measures document for
NPRM
• Early Summer 2008: Publication of the Final Rule
for New and Small Starts
• Early Summer 2008: Publication of Weights and
Measures document for Final Rule
14
No Longer FTA’s Presentation!
David Vozzolo, HDR
October 11, 2007
15
Emerging Industry Comments
• Due Nov 1 (yikes!)
• Working Draft comments by APTA, Community
Streetcar Coalition, New Starts Working Group
• Encourage comments from individual agencies
and organizations!
• Volume does matter!
• Comments also set stage for New Authorization
in 2009.
16
Emerging Industry Comments
• Suggest a more simplified project rating and
project development process
• Increased consideration of land use and
economic development benefits
• Reduced (or no) consideration of user benefits travel time savings measures
• Reduced time and cost required for project
milestones and grant agreement
17