Transcript Slide 1
Small Structure Design 101
Purdue University Road School 2011
Small Structure Design 101
Presenters:
Mark Williams, PE
INDOT Design, Vincennes District
Richard Thomas, PE
INDOT Design, Vincennes District
Site Criteria
A culvert should be used
Where a bridge is not hydraulically required.
Where debris and ice are tolerable.
Where it is more economical than a bridge.
Site Criteria (Cont.)
Length and Slope
Approximate existing topography.
Invert should be aligned with channel
bottom and skew angle of stream.
Clear-zone and embankment geometry
may dictate length.
Site Criteria (Cont.)
Location in Plan
Place normal to roadway if no defined
channel.
Minimize channel relocation and erosion.
Locate utilities before final location is
chosen.
Location in Profile
Approximate natural stream profile.
Hydraulic Design Criteria
Allowable Headwater (AHW)
Roadway Serviceability
Maximum Velocity
Minimum Velocity
Allowable Headwater (AHW)
New Alignment
1.5 in. Maximum Backwater.
Exceptions
Backwater Dissipates to 1.5 in. or less at
R/W.
Backwater is Contained in the Channel.
Allowable Headwater (Cont.)
Existing Conditions
Proposed Surcharge ≤ Existing Surcharge.
If Existing Surcharge > 1 ft., Proposed
must not be > 1 ft. above the Natural
Channel Flood Profile.
Allowable Headwater (Cont.)
Right of Way
The Ponding Limit Cannot Exceed the R/W
for New Alignment.
Upstream Channel
The Ponding Limit Cannot Exceed the
Banks of Upstream Channel for New
Alignment.
Allowable Headwater (Cont.)
Other Constraints
Grades of Adjacent Drives.
Finished Floor Elevations of Buildings.
Elevation of Existing Cropland or Other
Property.
Design Storm Frequency
Roadway Serviceability
For Q100 Design Storm
Headwater must be at least 2 ft below
edge of pavement
For Design Storm less than Q100
Headwater cannot exceed edge of
pavement
Maximum Velocity
Vo ≤ 6.5 ft/s
Revetment Riprap
6.5 ft/s ≤ Vo < 10 ft/s
Class 1 Riprap
10 ft/s ≤ Vo < 13 ft/s
Class 2 Riprap
Vo ≥ 13 ft/s
Energy Dissipator
Vo = Outlet Velocity
Minimum Velocity
Typical Minimum Outlet Velocity is
3 ft/s.
Culvert Sizing Process
Priority System
Interior Designation
Minimum Culvert Size
Cover
Priority System
Trial
Trial
Trial
Trial
Trial
Trial
1.
2.
3.
4.
5.
6.
Single Circular Pipe.
Single Deformed Pipe.
Single Specialty Structure.
Multiple Circular Pipes.
Multiple Deformed Pipes.
Multiple Specialty Structures.
Interior Designation
Run Hydraulic Design for both Smooth
Interior and Corrugated Interior.
Four Possible Situations.
Interior Designation (Cont.)
Situation 1. Required Smooth and
Corrugated Sizes are Identical.
Situation 2. Required Smooth and
Corrugated Sizes are Different.
Situation 3. Acceptable Size for one but
not the other.
Situation 4. No Acceptable Size.
Minimum Culvert Size
Pipe Cover
Circular Pipe
Deformed Corrugated
Pipe
Minimum Cover
Maximum Cover
1 Ft
100 Ft
1.5 Ft
13 Ft
Pipe Material Selection
Computer Program (INDOT Website)
Information Required
Pipe Classification
Pipe Interior Designation (Smooth/Corrugated)
Pipe Criteria (Size, Cover, Slope)
Pipe Service Life
Abrasive or Non-Abrasive Site
Structure pH
Pipe Classification
Type 1. Under Mainline or Public Road.
Type 2. Storm Drain.
Type 3. Under Drive or Field Entrance.
Type 4. Underdrain or Drain Tile.
Type 5. Broken Back or other which
requires coupled pipe.
Pipe Service Life
Based on Functional Classification of
Mainline Roadway
75 Years- Freeway, Expressway, Arterial
50 Years- Collector or Local Road
Abrasive or Non-Abrasive
Abrasive
Mainline Culvert
Public Road or Drive Culvert Installed in a
Natural Channel.
Non-Abrasive
Storm-Drain, Public Road, or Drive Culvert
on a Constructed Side Ditch Line.
Structure pH
Maximum pH. Cannot Exceed the Map
pH (Fig. 28-6A IDM).
Lack of Sample. Use pH From Nearest
Structure. If Not Available Within
Project Limits Use pH Map Value.
Side Ditch Culvert. Use pH for the Most
Downstream Culvert for Each Culvert in
Ditch Line.
Plans
Plan & Profile Sheet. Appropriate
Location for Drainage Structure
Identification.
Detail Sheet. Detail Drainage Structures
and Features that are not included in
the Standard Drawings.
Plans (Cont.)
Structure Data Sheet.
Backfill Method, Structure Backfill (CYS), Type.
Flowable Backfill (CYS), Type.
Scour Protection Information
Sump Depth (IN), Geotextile (SYS),
Riprap (Type & Tons)
Video Inspection Length.
Pipe Material Sheet. List Acceptable Pipe
Materials for each Pipe Structure.
Structure Backfill
Type 1
Longitudinal or Transverse Structure Within
5 ft. of the back of paved Shoulder or back
of Sidewalk of a New Facility.
Structure for an Existing Facility Where all
Existing Pavement is to be Replaced.
Structure Backfill (Cont.)
Type 2
Longitudinal or Transverse Structure Within
5 ft. of the back of paved Shoulder or back
of Sidewalk Where Undisturbed Existing
Pavement is to Remain.
Precast Concrete 3 Sided or 4 Sided
Structure with Cover of 2 ft or Greater.
Structure Backfill (Cont.)
Type 3
Behind Mechanically Stabilized Earth
Retaining Walls.
Type 4
Trench Where Utility Line is Present.
Behind Reinforced Concrete Slab Bridge
End Bent.
Structure Backfill (Cont.)
Type 5
Precast Concrete 3 Sided or 4 Sided
Structure with Cover Less than 2 ft.
Filling Voids in an Underground Facility.
Filling an Abandoned Pipe or Structure.
Other Application that does not Require
Excavation.
Backfill Methods
Method 1
Under New or Replacement Mainline or
Public Road.
Under Median Embankment.
New Structure Under Existing Mainline or
Public Road.
Backfill Methods (Cont.)
Method 2
Placed Under a Drive in New or
Replacement Work.
Method 3
Under New or Replacement Median
Trench.
Backfill Quantities
Measured by CYD Computed from Neat
Line Limits.
Hand Calculation
IDM Chapter 17
Standard Drawings Section 715-BKFL
Computer Program
www.in.gov/dot/div/contracts/standards/0
7Bkfl-qt.xls
Pavement Replacement
Longitudinal Pay Limits
Pipe Under Existing Roadway
Culvert Modifications
Culvert Slip Lining
Culvert Extension
Culvert End Treatment
Headwalls and Anchors
Culvert Slip Lining
Two Common Types
High Density Polyethylene Pipe (HDPE)
Cured in Place (CIPP)
Culvert Slip Lining (Cont.)
Review Pipe Inspection Report
Structures with an overall rating of 2 to 5
should be considered for lining.
Overall ratings of 0 or 1 are normally
structures that need to be replaced.
Field Review
Pictures
Measurements
Culvert Slip Lining (Cont.)
Factors to Consider
Structure barrel should be relatively
straight and not significantly deformed.
Existing backfill free from large voids.
Should be sufficient room to work from at
least one end of the existing structure.
In a location where road closure is
undesirable or impractical.
Hydraulic capacity of liner.
Liner cost vs. replacement cost
Lining Design Criteria
Time of Concentration < 1 Hour
May increase backwater over existing if:
Time of Concentration > 1 Hour
Headwater maintains road serviceability.
Headwater does not reach fixed private
property structures.
May not increase backwater, unless
contained within channel banks or R/W.
Check Outlet Velocity
Lining Design Procedure
HDPE Liners
Manning’s n=0.012.
Use maximum pipe liner size from tables in
Standard Specification Section 725.
Use largest possible liner, even if smaller
liner is hydraulically adequate.
Lining Design Procedure (Cont.)
CIPP Liners
Only considered if HDPE will not work (cost).
Manning’s n=0.012.
Structures < 96” diameter or equivalent.
Will reduce existing structure size as follows:
Dia.
Dia.
Dia.
Dia.
≤ 24”, reduce by 1”
from 27” to 48”, reduce by 2”
from 54” to 72”, reduce by 3”
from 78” to 96”, reduce by 4”
Culvert Extensions
Match Existing Pipe Size and Interior
Designation.
Perform Appropriate Hydraulic Analysis.
Culvert End Treatment
Projecting
Extends beyond the roadway embankment.
Can be damaged during maintenance.
Low construction cost.
Poor hydraulic efficiency.
Anchor should be used for 42” or larger
diameter.
Clear zone requirements.
Culvert End Treatment (Cont.)
Mitered
Hydraulically more efficient than projecting.
Mitered to match fill slope.
Pipe End Section
For corrugated metal or concrete pipe.
Retards embankment erosion.
May improve hydraulic efficiency.
Culvert End Treatment (Cont.)
Wingwall
Retain roadway embankment
Used where side slopes of channel are
unstable.
Best hydraulic efficiency if flare angle is
between 30° and 60°.
Should be used on precast concrete
drainage structures.
Culvert End Treatment (Cont.)
Apron
Reduce scour
Should extend at least one pipe diameter.
Should not protrude above normal
streambed elevation.
May be constructed of riprap and
geotextile or concrete.
Culvert End Treatment (Cont.)
Cutoff Wall
Prevent piping along culvert barrel.
Should be used for culverts with headwalls.
Should be minimum of 20” depth.
Specialty Structures
Precast Concrete Box Culvert
Maximum span is 12 ft.
The recommended layout is to extend the
box to the point where the roadway
sideslope intercepts stream flowline.
End of box culvert should be protected
with guardrail or located beyond the clear
zone.
Specialty Structures
Precast Concrete Oversize Box Structure
12’ < Clear Span ≤ 20’
Three-sided structure with base slab may
be an acceptable alternate. Consult with
Hydraulics Team for guidance. Run cost
comparison.
If distance from top of structure to top of
pavement is less than 2’, then all top slab
reinforcement should be epoxy coated.
Wingwalls and headwalls required.
Wingwalls and Headwalls
Information on Plans
Plan view showing total length of structure,
skew angle, distance from roadway centerline
to each end, and flare angle of wingwalls.
Elevation view of structure including
wingwalls and headwalls. Dimension span,
rise, and height of headwalls.
Wingwalls and Headwalls (Cont.)
Information on Plans
Label wingwalls A to D and include a table
with dimensions, elevations, areas for each
wingwall.
Show approximate footing configuration with
typical section through each wingwall. Footing
dimensions should not be shown. Contractor
is responsible for footing design.
Wingwalls and Headwalls (Cont.)
Information on Plans
Include a table with soil parameters
Allowable soil bearing pressure.
Angle of friction between wingwall footings and
foundation soil.
Angle of internal friction of the foundation soil.
Ultimate cohesion of foundation soil.
Ultimate adhesion between foundation soil and
concrete.
Wingwalls and Headwalls (Cont.)
Information on Plans
Show conceptual layout for precast concrete
structures or precast wingwalls and headwalls.
Fabricator will design and detail structure after
work is under contract.
For structures > 12’ span, fabricator will
provide design computations and shop
drawings for approval.
Culvert Sumping
Structure invert elevation and scour
protection placed below the stream
flowline to satisfy IDEM 401 Permit.
Show scour protection limits on plans.
Identify geotextile and riprap quantities
for scour protection in Structure Data
Table. These quantities are not pay
quantities.
Culvert Sumping
Three-Sided Structure
18” sump for sand stream bed.
12” sump for other soil type stream bed.
3” sump for rock stream bed.
Pipe or Box Structure
Refer to Standard Drawings and IDM Figure
31-3B(1).
Structure diameter or rise may need to be
increased if sump exceeds 3”.
Geotechnical Requirements
Pipe structure replacements require a
geotechnical investigation.
Pipe structures < 36 in. diameter or
pipe extensions < 5 ft may qualify for
geotechnical waiver.
Check with INDOT’s Office of
Geotechnical Engineering.
References
Standard Specifications
211.
213.
714.
715.
716.
717.
Structural Backfill
Flowable Backfill
Concrete Box Structures
Pipe Culverts
Trenchless Pipe
Structural Plate Pipe
References (Cont.)
Indiana Design Manual (IDM)
Chap.
Chap.
Chap.
Chap.
17.
28.
31.
34.
Quantity Estimating
General Information (Hydraulics)
Culverts
Energy Dissipators
External Dissipator (Example)
Existing
66” x 260’ CMP
Ample R/W at Outlet.
Proposed
HDPE Liner
Vo = 17.15 fps
HY8 to design External Dissipator.
External Dissipator (Example)
External Dissipator (Example)
External Dissipator (Example)
Internal Dissipator (Example)
Existing
42” x 295’ CMP
Distance from Outlet to R/W = 6 ft.
Proposed
HDPE Pipe Liner
Vo = 18.6 fps
No room for External Dissipator
HY8 to design Internal Dissipator
Vo = 9.0 fps (w/Internal Dissipator)
Internal Dissipator (Example)
Internal Dissipator (Example)
Internal Dissipator (Example)
Box Culvert Plans (Example)
Box Culvert Plans (Example)
Box Culvert Plans (Example)
Box Culvert Plans (Example)
Box Culvert Plans (Example)
Box Culvert Plans (Example)
Box Culvert Plans (Example)
Box Culvert Plans (Example)