Dry Stacking of Cycloned Tailings.

Download Report

Transcript Dry Stacking of Cycloned Tailings.

Dry Stacking of Cycloned Tailings

W. Lugão - VOGBR, Brazil M. Almeida - VOGBR, Brazil A. Guimarães - VOGBR, Brazil F. Magalhães - VOGBR, Brazil S. Mohallem - ARCELORMITTAL, Brazil

Introduction

Tailings at ArcelorMittal Mineração’s Serra Azul Mine are currently disposed of in a tailings dam, which is at the end of its useful life. Another tailings disposal facility is required and there is no place for another conventional dam.

A drained stacking scheme was proposed, with the following advantages over conventional dams:

- It allows tailings to be stored in stacks, which poses less risk as it does not involve the storage of water; - It will be located in an area that was occupied by a fines stockpile (sinter feed), which is why no additional land will have to be purchased; - It allows mining operations to proceed without interruption.

IMAGE: 09-14-2007 – GOOGLE EARTH

SERRA AZUL MINE TAILINGS DAM SINTER FEED

IMAGE: 07-30-2011 – GOOGLE EARTH

SERRA AZUL MINE TAILINGS DAM DRY STACKING TAILINGS

Design Concept

DRY STACKING DRYING PONDS OVERFLOW TAILINGS CONTAINMENT DIKE SEDIMENT CYCLONE

WASTE PILE

Design Concept

A

WASTE/TAILINGS CO-DISPOSAL DRY STACKING

INTERNAL DRAINAGE

Design Concept

ROCK-FILL STARTER EMBANKMENT JIG TAILINGS DRAIN - SECTION

Design Concept

A

Example: Plant level 1,030 m – tailings/waste co-disposal

SECTION A WASTE PILE UNDERFLOW TAILINGS JIG TAILINGS ROCK-FILL STARTER EMBANKMENT OVERFLOW / UNDERFLOW TAILINGS

8m 25m 100m

TAILINGS CELLS

Schematic profile (section A)

Design Concept

ROCK-FILL STARTER EMBANKMENT JIG DIKES OVERFLOW/UNDERFLOW UNDERFLOW DIKES WASTE PILE

Design Concept

Conception: Underflow dikes – vertical drainage!!!

UNDERFLOW DIKES

Conception: Overflow – drainage in top and base!!!

Pilot Tests – Total Tailings

Pilot Tests - Cyclone

CYCLONE UNDERFLOW TAILINGS

Tailings characterisation

Grain size - millimeters

Jig Tailings Total Tailings AM01 Underflow AM02 Underflow Overflow

Table Test results

Sample SG

Total tailings AM-1 Underflow AM-2 Underflow Overflow Jig 3.717

3.741

3.838

3.405

3.544

Clay (%)

4.4

1.8

1.4

7.2

0.2

Full gradation Silt (%)

60.9

30.6

Sand (%)

34.7

67.4

Gravel (%) w Compaction optimum (%)

r

max (g/cm³) Void ratio e max e min

0.0

0.2

1.01

0.71

33.6

77.2

5.0

64.7

15.6

65.5

0.2

0.0

29.3

13.0

2.208

1.09

0.77

Table Permeability test summary

Re-moulding conditions Sample Relative compaction (%) Degree of compaction (%)

-

Moisture (%)

AM-1 Underflow 60 11.6

AM-2 Underflow 70 11.7

85 Overflow 12.8

r

dry (g/cm³)

2.039

2.038

1.878

Permeability (m/s)

1.10e-06 1.40e-06 4.20e-08

Table 6 Parameters for materials used in stress-strain and stability analyses Table Triaxial test results

Effective strength parameters Sample c’ (kPa)

f

’ ( ° )

AM-1 Underflow 3.89

29.7

AM-1 Underflow Overflow 5.00

4.05

31.2

30.1

Total strength parameters c (kPa)

f

( ° )

0 26.5

17.20

5.20

18.7

11.6

Table Parameters for materials used in stress-strain and stability analyses

Material Density (kN/ m³) c’ (kPa )

f

’ ( ° ) Deformation modulus (MPa)

n (

Poisson’s ratio

) Foundation Rock-fill Underflow Overflow Jigue Waste 17.0

23.0

22.8

20.0

23.0

22.0

15 0 0 2 0 0 28 42 30 26 36 34 20,000 80 20 4.0

27.5

40 0.20

0.25

0.30

0.40

0.25

0.33

Stress-strain analysis

MATERIALS FINITE ELEMENT MODEL (SIGMA) FINAL STACK CONDITION

Stability Analyses

The safety factor for the critical failure surface is 1.97 and is therefore satisfactory.

Stability analysis results for waste rock/tailings co-disposal – Global – Non-Circular failure.

Operation

OVERFLOW TAILINGS – DISPOSAL SEQUENCE

Building the tailings cells

Situation - December 2012

ROCK-FILL STARTER EMBANKMENT CONTAINMENT DIKE UNDERFLOW LEVEL 1000.5 m DRYING PONDS OVERFLOW LEVEL 1000 m

Final Remarks

• Stability analyses have arrived at a satisfactory safety factor, assuming the long-term (drained) final stack condition; the maximum predicted subsidence in dry stacks will be acceptable even in the most critical long-term condition; • It is suggested that the cyclone system operating techniques should be reviewed, as the system is now working with overflow rates in excess of design rates. As a result, underflow requirements are being filled with jig tailings currently available at the mine for such purpose.

• It is also recommended that alternative methods should be developed for carrying overflow tailings from dewatering ponds to the storage basins, including alternative deposition methods, with a view to improving the process which is currently undertaken using trucks.

• An investigation campaign is programmed, composed of SPT, CPTU, Vane, permeability and laboratory tests; • ArcelorMittal will continue monitoring the performance of the system.

Thank you!

Contact: [email protected]