Federal Regulation of Natural Gas Transportation and
Download
Report
Transcript Federal Regulation of Natural Gas Transportation and
University of Pittsburgh School of Law
Energy Law & Policy Institute
August 1, 2013
U.S. Natural Gas Pipelines:
Regulatory and Policy Developments
David L. Wochner, Partner
Washington, DC
[email protected]
© Copyright 2013 by K&L Gates LLP. All rights reserved.
Overview
FERC Regulation of Natural Gas
General Agency Overview
FERC Process
Pre-Filing Process
Formal Application
Environmental Review
FERC Decision
Other Issues
Supply Changes
Environmental
Commercial
klgates.com
1
FERC REGULATION OF NATURAL GAS
klgates.com
2
FERC Regulation of Natural Gas
General Agency Overview
FERC Process
Pre-Filing Process
Formal Application
Environmental Review
FERC Decision
klgates.com
3
FERC Basics
Independent (non-political) agency
5 Commissioners
5-year terms
Senate confirmed
3 from President’s political party
2 from the opposition party or Independent
klgates.com
4
FERC Organization
klgates.com
5
FERC General Regulation
FERC regulates:
Transportation and sale of natural gas for resale in
interstate commerce
Transportation of oil and products by pipeline in
interstate commerce
Transmission and wholesale sale of electricity in
interstate commerce
Other matters related to the operation of oil, natural
gas, electric, and hydro-projects
klgates.com
6
FERC Regulation of Natural Gas
Natural Gas Pipelines and Storage Facilities
Rates (Pipelines and natural gas storage, not LNG)
Regulates to ensure rates and terms of service are “just and reasonable” and
detailed in publicly available “tariffs”
Access
Requires open and non-discriminatory access to interstate natural gas
facilities and services
Abandonment
Regulates termination of service and abandonment of interstate facilities
Siting, Construction, Operation
Approves location, construction and operation of facilities for liquefaction,
regasification, transportation and storage of interstate natural gas
Environmental
Coordinates requirements relating to natural gas pipeline and LNG projects
klgates.com
7
Natural Gas Act of 1938
Basis of FERC’s authority to regulate facilities used for
the transportation and wholesale sale of natural gas in
interstate commerce
Section 3
Import/export of natural gas
LNG facilities
Section 4
Pipeline and storage rate
filings
Terms and conditions of
service
“Just and reasonable” rates
Section 4A
Market manipulation
Section 5
Complaint oversight
Section 7
Construction and operation
of facilities
Section 21
General enforcement
Section 23
Transparency
Reporting requirements
klgates.com
8
FERC Regulation of Natural Gas
General Agency Overview
FERC Process
Pre-Filing Process
Formal Application
Environmental Review
FERC Decision
klgates.com
9
FERC Process
To construct a natural gas pipeline, developer must first
obtain from FERC a certificate of public convenience
and necessity
FERC’s review addresses rate, terms and conditions of
service, environmental and safety issues
FERC coordinates with multiple federal, state, and
local government agencies who provide input to FERC
regarding their respective areas of authority and
influence
klgates.com
10
FERC Process
Phases to the traditional FERC certification process
Applicant’s planning process
FERC review procedure
Pre-filing process – Optional for natural gas pipelines
Preparation of (draft and) final resource reports
Formal application
Participation of interested parties
Preparation of draft and final environmental impact
Statement (“EIS”) or environmental assessment (“EA”)
consistent with the National Environmental Policy Act
(“NEPA”)
FERC decision
Construction process
klgates.com
11
FERC Regulation of Natural Gas
General Agency Overview
FERC Process
Pre-Filing Process
Formal Application
Environmental Review
FERC Decision
klgates.com
12
Pre-Filing Process
Under EPAct 2005, FERC was required to enact rules mandating
FERC’s previously voluntary NEPA environmental pre-filing
process for LNG facility proposals
FERC’s regulations made pre-filing voluntary for pipelines
However, many new pipelines and expansion now utilize the prefiling process
Regulations require that pre-filing procedures be initiated a
minimum of 6 months prior to filing formal application
FERC’s pre-filing process is an informal review process
No ex parte rules apply so FERC Staff is free to have private,
non-public conversations with the project proponent
During the pre-filing process FERC Staff works with the applicant to
gather information about the proposed project
Identify and resolve as many potential issues or obstacles in
advance of the formal application when ex parte rules do apply
klgates.com
13
Pre-Filing Process
Source: http://www.ferc.gov
klgates.com
14
FERC Regulation of Natural Gas
General Agency Overview
FERC Process
Pre-Filing Process
Formal Application
Environmental Review
FERC Decision
klgates.com
15
Formal Application
Source: http://www.ferc.gov
klgates.com
16
Formal Application
Once a party files its formal application, FERC will issue
notice of the application and all interested parties may
intervene and submit comments
FERC will prepare an EA or a draft/final EIS, which
interested parties also may comment on
Detailed filings required, including rate analysis and
justification for proposed cost-based rate, a draft tariff,
engineering and design information, maps and diagrams,
an environmental report, pro forma tariffs and initial rate
services, as well as financial and operational information
Even an uncontested application can take between 8-12
months for FERC to review and issue decision
FERC approval process is elaborate and public
klgates.com
17
FERC Regulation of Natural Gas
General Agency Overview
FERC Process
Pre-Filing Process
Formal Application
Environmental Review
FERC Decision
klgates.com
18
Environmental Review
NEPA requires that federal agencies conduct an
environmental analysis of proposed federal actions prior to
decision-making
Approval or denial of an application to site, construct, or
operate an interstate natural gas pipeline is a federal action
FERC conducts comprehensive environmental assessment
and coordinates with other agencies and with retained thirdparty environmental contractor paid for by the applicant
Environmental review is time consuming
Must submit extensive environmental reports, including
studies and consultations with federal, regional, state and
local agencies
klgates.com
19
Environmental Review
FERC’s environmental review includes
The applicant’s receipt of environmental authorizations from
other government bodies
The applicant’s preparation and submission of resource
reports
FERC’s preparation of an EA, and/or possibly an EIS
klgates.com
20
Environmental Authorizations
from Other Agencies
FERC’s final authorization is conditioned on satisfaction of statutory
environmental requirements
Two primary federal environmental laws figure into FERC’s
analysis
Clean Air Act
Clean Water Act
Authority to administer these federal laws is delegated to the states
in which the proposed activities occur
These are federal laws and are of equal power and authority to
FERC’s authority under the Natural Gas Act
If a state environmental agency determines that the proposed
activities have not and cannot comply with one of these federal
laws, it likely has the authority to stop a project
klgates.com
21
Resource Reports
To implement NEPA, FERC’s regulations require an
applicant to submit an Environmental Report that consists
of 13 resource reports
The Environmental Report contains the applicant’s analysis
of the environmental impact of the proposed activity
The applicant submits draft versions of its resource reports
during the pre-filing process
The applicant submits the final version of its resource
reports with its formal application
Cooperating federal and state agencies have the opportunity
to comment on the draft resource reports
klgates.com
22
Resource Reports
Report
Description
Required For
1
General project description
All applications
2
Water use and quality
All applications outside area of existing compressors,
meters, and regulator stations
3
Fish, wildlife, and vegetation
All applications outside improved area of existing
compressors, meters, and regulator stations
4
Cultural resources
All applications
5
Socioeconomics
All applications involving aboveground facilities
6
Geological resources
All applications outside the boundaries of existing
aboveground facilities
7
Soils
All applications involving soil disturbance
8
Land use, recreation, and aesthetics
All applications
9
Air and noise quality
New LNG facilities
10
Alternatives
All applications
11
Reliability and safety
New and recommissioned LNG facilities
12
PCB contamination
Removal or abandonment of PCB pipe
13
Engineering and design material
New and recommissioned LNG facilities
klgates.com
23
EIS v. EA
EAs serve three main purposes
To briefly provide sufficient evidence and analysis for
determining whether to prepare an EIS
To aid FERC’s compliance with NEPA when no EIS is
necessary
To facilitate preparation of an EIS when one is necessary
EAs are concise documents and must include a brief
discussion of the proposal, alternatives, the environmental
impacts of the proposal and alternatives, and a list of the
agencies and persons consulted
EAs conclude either with a finding of no significant impact
(“FONSI”) or a finding that an EIS is required
40 CFR § 1508.9
klgates.com
24
EIS v. EA
By contrast, an EIS is a more robust and
comprehensive document
The process for preparing an EIS is proscriptive
Publish notice of intent to prepare an EIS in the Federal
Register (public notice)
Scoping
Prepare and circulate draft EIS
Receive comments from interested parties on draft EIS
Issue final EIS
Prepare and issue CPCN that adopts and sometimes
modifies the environmental conclusions and alternatives and
mitigation measures recommended in the final EIS
klgates.com
25
FERC Regulation of Natural Gas
General Agency Overview
FERC Process
Pre-Filing Process
Formal Application
Environmental Review
FERC Decision
klgates.com
26
FERC Decision
Source: http://www.ferc.gov
klgates.com
27
FERC Decision
No deadline for FERC to issue a decision on a new pipeline
certificate project
If FERC approves a project, its order will contain a number of
environmental mitigation measures
Once FERC issues a decision, the applicant and parties who
intervened in the proceeding can file a request for rehearing
within 30 days
FERC is then required under the NGA to answer that request
within 30 days or the request is deemed denied
FERC may issue a tolling order
If FERC rejects a party’s request for rehearing, the party may file
an appeal of the decision in U.S. federal appeals court within 60
days
If the project developer has satisfied all of the measures in
FERC’s order, it will be able to continue construction of the
project throughout any appeals process
klgates.com
28
CURRENT ISSUES
klgates.com
29
Current Issues – Supply Changes
U.S. domestic gas picture has changed
Massive new technically and economically recoverable shale gas
resources
Surplus has quelled concerns of many elected officials about
adequacy of supply
Support of domestic natural gas production and use from
White House … kind of
Repeated statements by President Obama recognizing economic
and environmental benefits of natural gas
Growth in manufacturing and petrochemical sectors
Increased use as a transportation fuel
As a result, substantial increase in natural gas pipeline
infrastructure
klgates.com
30
Current Issues – Environmental
Keystone XL is a line in the sand for the U.S. environmental
movement
Movement has now shifted to hydraulic fracturing and LNG
exports – Sierra Club is leading the opposition
Quantifiable shift from previous position in first half of last decade
Opposition is rooted in concerns over increased shale gas
production and hydraulic fracturing
Asserts that FERC and DOE should look at the environmental
impacts of hydraulic fracturing since allowing exports
necessarily will result in additional shale gas production
Argues that the environmental reviews are inadequate and do
not satisfy NEPA
Indirect effects
Reasonably foreseeable
klgates.com
31
Current Issues – Environmental
April 2012 Sierra Club letter to White House Council on
Environmental Quality (CEQ) asserting the alleged harms
of natural gas production and use in generation
“Unconventionally sourced LNG is the very dirtiest form of a dirty
fuel.”
EPA regional inquiries in FERC pipeline certificate
proceedings related to upstream production
Methane emissions from natural gas pipelines
Questions about adequacy of technology
Questions about pipelines’ ability to recover costs
klgates.com
32
Current Issues – Commercial
Conversion of existing natural gas pipelines to
transport oil and oil products
Existing customer protections
Substantial new pipeline capacity in previously lessserved regions provide utilities and large industrials
opportunities for new gas supply
Become an “anchor shipper”
klgates.com
33
QUESTIONS?
klgates.com
34
35