Federal Regulation of Natural Gas Transportation and

Download Report

Transcript Federal Regulation of Natural Gas Transportation and

University of Pittsburgh School of Law
Energy Law & Policy Institute
August 1, 2013
U.S. Natural Gas Pipelines:
Regulatory and Policy Developments
David L. Wochner, Partner
Washington, DC
[email protected]
© Copyright 2013 by K&L Gates LLP. All rights reserved.
Overview
 FERC Regulation of Natural Gas






General Agency Overview
FERC Process
Pre-Filing Process
Formal Application
Environmental Review
FERC Decision
 Other Issues
 Supply Changes
 Environmental
 Commercial
klgates.com
1
FERC REGULATION OF NATURAL GAS
klgates.com
2
FERC Regulation of Natural Gas






General Agency Overview
FERC Process
Pre-Filing Process
Formal Application
Environmental Review
FERC Decision
klgates.com
3
FERC Basics
 Independent (non-political) agency
 5 Commissioners
 5-year terms
 Senate confirmed
 3 from President’s political party
 2 from the opposition party or Independent
klgates.com
4
FERC Organization
klgates.com
5
FERC General Regulation
 FERC regulates:
 Transportation and sale of natural gas for resale in
interstate commerce
 Transportation of oil and products by pipeline in
interstate commerce
 Transmission and wholesale sale of electricity in
interstate commerce
 Other matters related to the operation of oil, natural
gas, electric, and hydro-projects
klgates.com
6
FERC Regulation of Natural Gas
 Natural Gas Pipelines and Storage Facilities
 Rates (Pipelines and natural gas storage, not LNG)
 Regulates to ensure rates and terms of service are “just and reasonable” and
detailed in publicly available “tariffs”
 Access
 Requires open and non-discriminatory access to interstate natural gas
facilities and services
 Abandonment
 Regulates termination of service and abandonment of interstate facilities
 Siting, Construction, Operation
 Approves location, construction and operation of facilities for liquefaction,
regasification, transportation and storage of interstate natural gas
 Environmental
 Coordinates requirements relating to natural gas pipeline and LNG projects
klgates.com
7
Natural Gas Act of 1938
 Basis of FERC’s authority to regulate facilities used for
the transportation and wholesale sale of natural gas in
interstate commerce
 Section 3
 Import/export of natural gas
 LNG facilities
 Section 4
 Pipeline and storage rate
filings
 Terms and conditions of
service
 “Just and reasonable” rates
 Section 4A
 Market manipulation
 Section 5
 Complaint oversight
 Section 7
 Construction and operation
of facilities
 Section 21
 General enforcement
 Section 23
 Transparency
 Reporting requirements
klgates.com
8
FERC Regulation of Natural Gas






General Agency Overview
FERC Process
Pre-Filing Process
Formal Application
Environmental Review
FERC Decision
klgates.com
9
FERC Process
 To construct a natural gas pipeline, developer must first
obtain from FERC a certificate of public convenience
and necessity
 FERC’s review addresses rate, terms and conditions of
service, environmental and safety issues
 FERC coordinates with multiple federal, state, and
local government agencies who provide input to FERC
regarding their respective areas of authority and
influence
klgates.com
10
FERC Process
 Phases to the traditional FERC certification process
 Applicant’s planning process
 FERC review procedure
 Pre-filing process – Optional for natural gas pipelines
 Preparation of (draft and) final resource reports
 Formal application
 Participation of interested parties
 Preparation of draft and final environmental impact
Statement (“EIS”) or environmental assessment (“EA”)
consistent with the National Environmental Policy Act
(“NEPA”)
 FERC decision
 Construction process
klgates.com
11
FERC Regulation of Natural Gas






General Agency Overview
FERC Process
Pre-Filing Process
Formal Application
Environmental Review
FERC Decision
klgates.com
12
Pre-Filing Process
 Under EPAct 2005, FERC was required to enact rules mandating
FERC’s previously voluntary NEPA environmental pre-filing
process for LNG facility proposals
 FERC’s regulations made pre-filing voluntary for pipelines
 However, many new pipelines and expansion now utilize the prefiling process
 Regulations require that pre-filing procedures be initiated a
minimum of 6 months prior to filing formal application
 FERC’s pre-filing process is an informal review process
 No ex parte rules apply so FERC Staff is free to have private,
non-public conversations with the project proponent
 During the pre-filing process FERC Staff works with the applicant to
gather information about the proposed project
 Identify and resolve as many potential issues or obstacles in
advance of the formal application when ex parte rules do apply
klgates.com
13
Pre-Filing Process
Source: http://www.ferc.gov
klgates.com
14
FERC Regulation of Natural Gas






General Agency Overview
FERC Process
Pre-Filing Process
Formal Application
Environmental Review
FERC Decision
klgates.com
15
Formal Application
Source: http://www.ferc.gov
klgates.com
16
Formal Application
 Once a party files its formal application, FERC will issue
notice of the application and all interested parties may
intervene and submit comments
 FERC will prepare an EA or a draft/final EIS, which
interested parties also may comment on
 Detailed filings required, including rate analysis and
justification for proposed cost-based rate, a draft tariff,
engineering and design information, maps and diagrams,
an environmental report, pro forma tariffs and initial rate
services, as well as financial and operational information
 Even an uncontested application can take between 8-12
months for FERC to review and issue decision
 FERC approval process is elaborate and public
klgates.com
17
FERC Regulation of Natural Gas






General Agency Overview
FERC Process
Pre-Filing Process
Formal Application
Environmental Review
FERC Decision
klgates.com
18
Environmental Review
 NEPA requires that federal agencies conduct an
environmental analysis of proposed federal actions prior to
decision-making
 Approval or denial of an application to site, construct, or
operate an interstate natural gas pipeline is a federal action
 FERC conducts comprehensive environmental assessment
and coordinates with other agencies and with retained thirdparty environmental contractor paid for by the applicant
 Environmental review is time consuming
 Must submit extensive environmental reports, including
studies and consultations with federal, regional, state and
local agencies
klgates.com
19
Environmental Review
 FERC’s environmental review includes
 The applicant’s receipt of environmental authorizations from
other government bodies
 The applicant’s preparation and submission of resource
reports
 FERC’s preparation of an EA, and/or possibly an EIS
klgates.com
20
Environmental Authorizations
from Other Agencies
 FERC’s final authorization is conditioned on satisfaction of statutory
environmental requirements
 Two primary federal environmental laws figure into FERC’s
analysis
 Clean Air Act
 Clean Water Act
 Authority to administer these federal laws is delegated to the states
in which the proposed activities occur
 These are federal laws and are of equal power and authority to
FERC’s authority under the Natural Gas Act
 If a state environmental agency determines that the proposed
activities have not and cannot comply with one of these federal
laws, it likely has the authority to stop a project
klgates.com
21
Resource Reports
 To implement NEPA, FERC’s regulations require an
applicant to submit an Environmental Report that consists
of 13 resource reports
 The Environmental Report contains the applicant’s analysis
of the environmental impact of the proposed activity
 The applicant submits draft versions of its resource reports
during the pre-filing process
 The applicant submits the final version of its resource
reports with its formal application
 Cooperating federal and state agencies have the opportunity
to comment on the draft resource reports
klgates.com
22
Resource Reports
Report
Description
Required For
1
General project description
All applications
2
Water use and quality
All applications outside area of existing compressors,
meters, and regulator stations
3
Fish, wildlife, and vegetation
All applications outside improved area of existing
compressors, meters, and regulator stations
4
Cultural resources
All applications
5
Socioeconomics
All applications involving aboveground facilities
6
Geological resources
All applications outside the boundaries of existing
aboveground facilities
7
Soils
All applications involving soil disturbance
8
Land use, recreation, and aesthetics
All applications
9
Air and noise quality
New LNG facilities
10
Alternatives
All applications
11
Reliability and safety
New and recommissioned LNG facilities
12
PCB contamination
Removal or abandonment of PCB pipe
13
Engineering and design material
New and recommissioned LNG facilities
klgates.com
23
EIS v. EA
 EAs serve three main purposes
 To briefly provide sufficient evidence and analysis for
determining whether to prepare an EIS
 To aid FERC’s compliance with NEPA when no EIS is
necessary
 To facilitate preparation of an EIS when one is necessary
 EAs are concise documents and must include a brief
discussion of the proposal, alternatives, the environmental
impacts of the proposal and alternatives, and a list of the
agencies and persons consulted
 EAs conclude either with a finding of no significant impact
(“FONSI”) or a finding that an EIS is required
40 CFR § 1508.9
klgates.com
24
EIS v. EA
 By contrast, an EIS is a more robust and
comprehensive document
 The process for preparing an EIS is proscriptive
 Publish notice of intent to prepare an EIS in the Federal
Register (public notice)
 Scoping
 Prepare and circulate draft EIS
 Receive comments from interested parties on draft EIS
 Issue final EIS
 Prepare and issue CPCN that adopts and sometimes
modifies the environmental conclusions and alternatives and
mitigation measures recommended in the final EIS
klgates.com
25
FERC Regulation of Natural Gas






General Agency Overview
FERC Process
Pre-Filing Process
Formal Application
Environmental Review
FERC Decision
klgates.com
26
FERC Decision
Source: http://www.ferc.gov
klgates.com
27
FERC Decision
 No deadline for FERC to issue a decision on a new pipeline
certificate project
 If FERC approves a project, its order will contain a number of
environmental mitigation measures
 Once FERC issues a decision, the applicant and parties who
intervened in the proceeding can file a request for rehearing
within 30 days
 FERC is then required under the NGA to answer that request
within 30 days or the request is deemed denied
 FERC may issue a tolling order
 If FERC rejects a party’s request for rehearing, the party may file
an appeal of the decision in U.S. federal appeals court within 60
days
 If the project developer has satisfied all of the measures in
FERC’s order, it will be able to continue construction of the
project throughout any appeals process
klgates.com
28
CURRENT ISSUES
klgates.com
29
Current Issues – Supply Changes
 U.S. domestic gas picture has changed
 Massive new technically and economically recoverable shale gas
resources
 Surplus has quelled concerns of many elected officials about
adequacy of supply
 Support of domestic natural gas production and use from
White House … kind of
 Repeated statements by President Obama recognizing economic
and environmental benefits of natural gas
 Growth in manufacturing and petrochemical sectors
 Increased use as a transportation fuel
 As a result, substantial increase in natural gas pipeline
infrastructure
klgates.com
30
Current Issues – Environmental
 Keystone XL is a line in the sand for the U.S. environmental
movement
 Movement has now shifted to hydraulic fracturing and LNG
exports – Sierra Club is leading the opposition
 Quantifiable shift from previous position in first half of last decade
 Opposition is rooted in concerns over increased shale gas
production and hydraulic fracturing
 Asserts that FERC and DOE should look at the environmental
impacts of hydraulic fracturing since allowing exports
necessarily will result in additional shale gas production
 Argues that the environmental reviews are inadequate and do
not satisfy NEPA
 Indirect effects
 Reasonably foreseeable
klgates.com
31
Current Issues – Environmental
 April 2012 Sierra Club letter to White House Council on
Environmental Quality (CEQ) asserting the alleged harms
of natural gas production and use in generation
 “Unconventionally sourced LNG is the very dirtiest form of a dirty
fuel.”
 EPA regional inquiries in FERC pipeline certificate
proceedings related to upstream production
 Methane emissions from natural gas pipelines
 Questions about adequacy of technology
 Questions about pipelines’ ability to recover costs
klgates.com
32
Current Issues – Commercial
 Conversion of existing natural gas pipelines to
transport oil and oil products
 Existing customer protections
 Substantial new pipeline capacity in previously lessserved regions provide utilities and large industrials
opportunities for new gas supply
 Become an “anchor shipper”
klgates.com
33
QUESTIONS?
klgates.com
34
35