Transcript TEST

Road and Bridge
Contractor use of
FieldManager in
Michigan
2004 AASHTO TUG
Mobile, Alabama
Cliff Farr - Michigan DOT
October 15, 2004
Presentation Overview






The Need for Information
Pilot Project
Pilot Project Results
Policy Implementation
Contractor Read-Only in Michigan Today
Wrap-up
The Need for Information

Contractor associations
• Better construction communication needed

FieldManager potential
•
•
•
•
Distribution capability
Stability, ease of use, accuracy of data
Quick training and implementation
Contractors could take advantage of many of
the same documented benefits
FieldManager Provides

Report access
• IDR (DWR)
• Pay Estimate
• Contract Modification (Change Order)

Lists
• IDR, Pay Estimate, Contract Modification, item,
material, contractor, etc.

Dozens of contract and project level, work
item and test material reports and
inquiries
• Various levels of payment information
• Insufficient materials at the contract and/or
Estimate level.
Optimistic Future






AASHTOWare products
New releases annually
Commitment to continuous software
improvements and enhancements
Software performance is solid
Future of products are solid
Excellent user acceptance
Scope



$1.5 billion annual construction
program
An estimated 160 active road/bridge
construction contractors in Michigan
Potential impact on out-of-state
FieldManager DOTs and agencies
The Pilot Project
Potential Benefits

Reduction in:
•
•
•
•

Telephone calls
Mailings
Faxes
Item/material status discussions
More efficient and accurate:
•
•
•
•
Estimate processing
Contract Modification processing
Contract finalization
Meetings
MDOT Apprehensions

Inspector Daily Report comments
• Inspectors will shy away from making
comments?
• Inspector comments cause
misunderstandings?


Claims flare-up?
What if the number of telephone calls
actually increase instead of decrease?
Contractor Apprehensions


What if the investment doesn’t pay off?
Learning curve
• Installation issues?
• Ease of use / logical work flows



Stability and integrity of the software
Interest of the field offices to provide files
Future of the product
Pilot Project Logistics


Voluntary participation – both sides
Contractors must license FieldManager
• License includes support from Info Tech

Contractors on board
• December, 2001
• June, 2002

Read-only copies distributed after
Estimate generation
Pilot Participants




12 Contractors
11 DOT offices
1 local agency
8 consultants
Pilot Project Contract
Statistics

Total number of contracts = 25
•
•
•
•

MDOT contracts = 14
Consultant contracts = 8
Local government contract = 1
Local government contracts managed by
consultant = 2
Number of dollars under construction
for the pilot was $587 million
Pilot Project
Results
Business Summary


By the fall of 2002, pilot participants had
gained significant experience with the
Contractor Read-Only distribution process
Questionnaires distributed, completed and
summarized
Pilot Project Findings


Participants (contractor and field office)
responded unanimously to make this a
permanent business practice
User acceptance excellent for both
contractor and field offices:
• Improved communications:
 Contract/Project/Item/Material statuses
 Bi-weekly meetings
 Contract finalization
Pilot Project Findings (cont.)





Reduced volume of phone calls, mailings
and faxes
Reduced contractor time required to
gather information
Creates an environment of more timely
and accurate information
Earlier identification of errors and
concerns
More current material tracking
Pilot Project Findings (cont.)



Eliminated some contractor spread-sheets
or hand generated data
Some offices reported improved field office
/ contractor relationships
Concerns
• Cost
• Time to import the electronic file

Recommendation formulated
• To implement as permanent policy
Pilot Project Findings (cont.)

Information to be removed from
Contractor Read-Only electronic files:
• File size issue:
 IDR attachments
• General information:
 Item Documentation Notes
 Miscellaneous Reports
Policy
Implementation
Policy Implementation


Recommendation approved by executive
management
Met with industry
• Cost (FieldManager Read-Only annual license
fee is $850)
• Time to import contracts was drastically
reduced in FieldManager release 3.3.

Policy was implemented to include all
contracts let by MDOT after September,
2003 (MDOT and local agency)
Contractor
Read-Only in
Michigan
Today
Contractor Read-Only in
Michigan Today


All MDOT field offices, local agencies, and
consultants are participating
51 contractors participating
• 48 Read-Only licenses
• 3 Full licenses

Over 1660 Read-Only files distributed by
MDOT this construction season
MDOT Involvement



Contractors and consultants license
FieldManager directly from Info Tech
Training available through Info Tech and
ACEC of Michigan
Field offices distribute the Contractor
Read-Only files
• Currently
• FieldNet 2.0 beginning in 2005
Wrap-up




Contractor Read-Only is off to an excellent
start in Michigan
FieldManager Read-Only data distribution
is easily filtered
Good communication is key
Potential solution for states and local
agencies
Questions?
Cliff Farr
FieldManager Business
Engineer
517-322-6039
[email protected]