Colorado River Canal Lining Projects Coachella & All

Download Report

Transcript Colorado River Canal Lining Projects Coachella & All

Colorado River Canal Lining Projects
Coachella & All-American Canals
ASCE Construction Division
West Coast Mega Projects Conference
January 2007
1
Colorado River Basin
2
Canal Lining Projects Location
Map Key
Existing Lined
Existing Unlined
New Canal
Coachella
Lake
Cahuilla
Salton Sea
Coachella Canal
El Centro
All American Canal
3
Canal Lining Projects
• Components of Colorado River
Quantification Settlement Agreement
• Settles a water rights dispute and litigation
dating to the 1960s
• Provides 93,700 ac-ft/yr of water
• SDCWA will receive 77,700 ac-ft annually
• SLR will receive 16,000 ac-ft annually
4
History of the All American Canal Lining Project
• Congressional authorization of the Project was under PL 100675, Title II signed into law by the President on November 17,
1988
• Concrete lining was from just downstream of Pilot Knob
(~Station 1170+27) to Drop 4, a total of about 29 miles
• During preparation of the EIS/EIR the Project was modified to
run from Station 1250+00 to Drop 3 due to:
– Major environmental issues between Drops 3 & 4 and costs to
mitigate such
– Wanted to move the starting point away from Pilot Knob, (a sacred
area of the Quechan Indians) to eliminate any potential
environmental/cultural conflicts
• Approved the Record of Decision (ROD) on July 29, 1994
5
History of the All American Canal Lining Project
•
•
•
•
•
Completed and filed EIS/EIR in July 1994
Reclamation undertook a Re-examination and Analysis of 1994
FEIS/EIR and ROD which determined said documents remained
current with the proposed action
California State Legislature passes SB 1765 continuously
appropriating $200 million for the two canal projects, with $126
million set aside for the Project. This bill was signed into law
by the Governor on September 24, 1998
California voters in 2003 approve Proposition 50; includes $20
million for the two canal projects; adds $9.65 million to Project
for total of $135.65 million
Quantification Settlement Agreement (QSA) and its related
documents signed on October 10, 2003 with the Project a key
component to reduce California’s water use to its 4.4 million
acre-feet apportionment
6
History of the Coachella Canal Lining Project
• Congressional authorization of the Project was under
PL 100-675, Title II signed into law by the President
on November 17, 1988
• Concrete lining from Siphon 7 to Siphon 32, a total of
about 35 miles
• FEIS/FEIR was completed and filed on April 27, 2001
• Record of Decision (ROD) signed on March 27, 2002
• Amendment #1 to ROD signed on changing preferred
alternative to refined parallel canal
• Key permit was the Corps of Engineers 404
nationwide permit received in June 2004
7
AACLP Project Location
8
AACLP Alignment
9
AACLP Project Elements
• Construct approximately 23 miles of
lined canal adjacent to existing canal
• DWR funding up to $135.65 Million
• Current estimates indicate significant
overrun of available funds
• Design is complete.
• Construction is expected to be
completed in Spring 2009
10
All-American Canal Typical Section
Proposed Lined Section
1.75H:1V side slope Reaches 1 & 2
2H:1V side slope Reach 3
150’
Existing Unlined Section
2H:1V side slope
24’ O&M Road
Spoils
50’
130’ +/-
11
67,700 Acre-Feet per Year of Water Conserved
from Lining the All-American Canal
SLR
11,500 ac- ft
SDCWA
56,200 ac-ft
12
How does lining 78% of the canal result in recovering
97% of seepage water?
• The seepage recovery by reach is as follows:
Reach
ac-ft
Cumulative ac-ft
1
50,850
50,850
2
14,700
65,550
3
2,150
67,700
13
Project Challenges
Project team has and is working diligently on
a fast-track basis to address a number of
design, construction, scheduling, and cost
issues to minimize costs (construction,
environmental, and operations/maintenance)
yet optimize the new canal facilities and the
required environmental mitigation.
14
Design Challenges
• New parallel alignment to minimize canal
excavation, rights-of-way, and dewatering
• Reach 1B is most difficult—a number of
alternatives were considered. The
embankment in-canal alignment was selected
• Project has and will continue to be impacted
by increases in fuel, cement, and to a smaller
extent steel prices
• Working together to ensure that all state
funds required based on current schedule
are available
15
Current Status
• Design is complete and the project is
preparing to begin construction
• Current schedule indicates construction
completion in Spring 2009
16
Canal Photos
17
18
19
CCLP Project Location
Coachella
Lake
Cahuilla
Map Key
Existing Lined
Existing Unlined
New Canal
El Centro
20
CCLP Alignment
21
CCLP Project Elements
• Construct approximately 35 miles of lined
canal adjacent to existing canal
• Construction began October 2004
• Project expected to be completed April 2007
• DWR funding up to $83.65 Million
• Construction awarded for $71,198,900
• Current estimates for environmental and other
areas indicate available funds will be
exceeded
22
Coachella Canal typical sections
Proposed Lined Section
1.5H:1V side slope
55’
Existing Unlined Section
2H:1V side slope
20’ O&M Road
Spoils
16’
40’ – 46’
23
26,000 Acre-Feet per Year of Water Conserved
from Lining the Coachella Canal
SLR
4,500 ac-ft
SDCWA
21,500 ac-ft
24
Design/Construction Challenges
• With parallel canal, raised the invert of the canal 4
feet (from 2 feet below existing canal invert to 2 feet
above existing canal invert)
• Developed a large mammal safety and water source
strategy
• Performed ecological value assessment to meet
environmental commitments in an economically
sound manner
25
Current Status
•
•
•
•
•
•
•
•
•
Construction is slightly ahead of schedule
Construction is approximately 97% complete
Lining of the canal was completed in August 2006
Tie-ins to existing canal completed in November
2006
Water cutover occurred on December 4, 2006
Total excavation – 5.6 million cubic yards (approx.)
Structural concrete – 37,000 cubic yards (approx.)
Concrete lining – 1.3 million square yards (approx.)
Fencing and electrical work is in progress
26
Canal Photos
27
28
29
30
31
32
SDCWA Funding
• Working together to ensure that all state
funds required during the construction phase
is available
– Will ensure that all state funds are used prior to
the need for SDCWA funds for costs over $83.65
million for CCLP and $135.65 for AACLP
– This will reduce financing costs to SDCWA and
the project
33
AACLP Project Organization
All American Canal Coordinating Committee (Voting Members)
• IID – Michael King • SDCWA – Kenneth Steele • Chairman – Joseph Summers
IID/DWR AACLP
Funding Agreement
IID Executive Program Manager
Kirk Dimmitt
Parsons Project Manager
Uli Kappus
Design
Bookman-Edmonston
Project Manager – Wayne Dahl
• Montgomery Watson Harza
• Various Consultants
- Canal Design - Dewatering
- Sedimentation - Soils
- Flow Measurement/
Operations
- Cost Estimating
- Construction Techniques
Design Coordination
Coordinator – Rick Cox
• Geotechnics, Inc.
• TESCO
Participants (Non-Voting)
• Reclamation – Russ Reichelt
• DWR – Chuck Keene
• San Luis Rey – Clyde Romney
• CVWD
• PVID
Construction Management
Construction Manager –
Tim Larson
Environmental Activities
Environmental
Coordinator –
Michel Remington, IID
• AFM Affiliates
Cultural Resources
• Dr. Paul Krausman
Large Mammal Surveys
• EcoSystems Restoration
Associates
Wetlands Enhancement
• RECON • Parsons
34
AACLP OM&R Coordinating Committee
Voting Members
SDCWA
CVWD
IID
SLR
Member Jointly Appointed
Non-Voting Member
USBR
IID prepares O&M plan for All-American Canal
35
CCLP Project Organization
Coachella Canal Coordinating Committee (Voting Members)
• CVWD – Patti Schwartz • SDCWA – Kenneth Steele • Chairman – Joseph Summers
SDCWA/DWR
Funding Agreement
CVWD Executive Program Manager
Kirk Dimmitt
CVWD Project Engineer
Dan Charlton
Design/Construction Management
Montgomery Watson Harza – Bookman-Edmonston
Project Manager – Wayne Dahl
• Project Engineer – Janet Atkinson
• Construction Manager – John Dahl
Participants (Non-Voting)
• Reclamation – Russ Reichelt
• DWR – Chuck Keene
• San Luis Rey – Clyde Romney
• IID – Paul Peschel
• PVID
Environmental Activities
Environmental Coordinator – Monica Swartz, PhD
• ASM Affiliates – Cultural Resources
• AMEC – Biological Manager,
Construction Environmental Monitoring
36
CCLP OM&R Coordinating Committee
Voting Members
SDCWA
CVWD
SLR
Member Jointly Appointed
Non-Voting Member
USBR
CVWD prepares O&M plan for Coachella Canal
37
Thank You
Questions?
38