Transcript Slide 1
Linac/BC2 Commissioning (Dec. 2007 through Sep., 2008) J. Frisch, et al. LCLS FAC Meeting Oct. 30, 2007 LCLS http://www-ssrl.slac.stanford.edu/lcls/internals/commissioning/index.html Oct. 30, 2007 LCLS FAC 1 Joe Frisch [email protected] LCLS Accelerator Schematic 6 MeV z 0.83 mm 0.05 % 4.30 GeV z 0.022 mm 0.71 % Linac-1 L 9 m rf -25° ...existing linac 21-1 b,c,d DL1 L 12 m R56 0 Linac-2 L 330 m rf -41° Linac-3 L 550 m rf 0° 21-3b 24-6d 25-1a 30-8c X BC1 L 6 m R56 -39 mm Injector Commissioning BC2 L 22 m R56 -25 mm LCLS FAC undulator L =130 m Commission in Jan. 2008 SLAC linac tunnel Oct. 30, 2007 13.6 GeV z 0.022 mm 0.01 % Linac-X L =0.6 m rf= -160 Linac-0 L =6 m rf gun 250 MeV z 0.19 mm 1.6 % 135 MeV z 0.83 mm 0.10 % 2 DL2 L =275 m R56 0 research yard Joe Frisch [email protected] BC2/Linac Commissioning Goals No problems expected Expect we can run at 1nC No specific problems expected – but lots to do No problems expected This is the tricky one No known issues, but there could be surprises Oct. 30, 2007 LCLS FAC 3 Joe Frisch [email protected] LCLS BC2-Area Layout OTR screens (3) Dipole magnets (4) Kicker magnet (1) Transverse RF deflector (1) S-band RF acc. sections 4 wire-scanners “de-scoped” Can measure gex,y here, with BC2 OFF OTR21 BC2 (not to scale) Oct. 30, 2007 LCLS FAC 4 wire-scanners in sec-28 (300 m downstream) BXKIK TCAV3 OTR22 (25-2d) (25-3d) OTR_TCAV (25-9) 4.3 GeV 4 Joe Frisch [email protected] Linac/BC2 Commissioning Scope New 4-dipole chicane in 24-7 – 24-8 Adjacent matching quads and new optics 3 new OTR screens, 1 collimator, 1 BPM, and 2 moved wire-scanners in sec-28 (4 wires in sec-24 are “de-scoped”) Transverse RF deflector at 25-2d + x-kicker 25-3d Two new coherent radiation-based bunch length monitors Energy and bunch length feedback loop and new SS sub-boosters in 24-1,2,3 + 24-8 (TCAV3) No new linac BPM electronics in 2008 (or ’09?) Oct. 30, 2007 LCLS FAC 5 Joe Frisch [email protected] Manpower and Scheduling Ten months of commissioning BC2/Linac (Dec - Sep) More help with commissioning shifts (H.-D. Nuhn, F.-J. Decker, Z. Huang, Y. Ding, D. Ratner) Did 3 shifts per week for 5 months in 2007 - exhausting No weekend shifts (ops only) after 1st month of startup Operators now somewhat experienced on injector Need two physicists/shift for 10 shifts/week (after 1st month) Need to cover 20 man-shifts/week - have at least 14 physicists – requires a total of 1.5 shifts/week/man (after 1st month) Shutdown LCLS for 2 weeks in March? (new gun probes + fix GTL) Oct. 30, 2007 LCLS FAC 6 Joe Frisch [email protected] Last Run’s Typical Shift Schedule Oct. 30, 2007 LCLS FAC 7 Joe Frisch [email protected] Schedule linac/BC2 Install LTU/Und/Dump FEE/NEH Install X-Ray tunnel/FEH Install Now 1st FEL Light 1st Users 1st Spont. Light 2008 Controls checkout & re-commission injector …Injector Commissioning Oct. 30, 2007 LCLS FAC 2009 Re-commission Inj/BC2 to SL2 Linac/BC2 Commissioning FEL Commissioning LTU/Und/FEE Commissioning 8 PPS 2007 PPS J A S O N D J F M AM J J A S O N D J F M AM J J A S ON D downtime commissioning time Joe Frisch [email protected] BC2 Commissioning Parameters Parameter Value Comments RF rate 30 Hz May test 120Hz Beam rate ≤30 Hz Drive-laser rate 30 Hz Bunch charge Drive-laser pulse length Final beam energy 250 pC ~6 ps fwhm 13.6 GeV 10 Hz e- beam as baseline – short term 30-Hz tests (beyond 30 Hz is unnecessary) Possible 120-Hz late in the run? Start at this low charge but later up to 1-nC Optimum not clear yet 13.6 GeV typically with tests down to 4.3 GeV May 12, 2007 Oct. 30, 2007 LCLS FAC 9 Joe Frisch [email protected] Two new OTR screens + LOLA & kicker BC2 Layout Oct. 30, 2007 LCLS FAC 10 Joe Frisch [email protected] OTR screen BPM Collimator BC2 Layout 23-m long chicane Translates horizontally up to 52 cm Oct. 30, 2007 LCLS FAC 11 Joe Frisch [email protected] New construction in BC2 (sector 24/25) Oct. 11, 2007 Oct. 30, 2007 LCLS FAC 12 Joe Frisch [email protected] New construction in BC2 (sector 24/25) Oct 26 Oct. 30, 2007 LCLS FAC 13 Joe Frisch [email protected] New Pre-Beam Tunnel Check List 17 pages Polarity conventions Installation orientation Component bar codes etc. Oct. 30, 2007 LCLS FAC 14 Joe Frisch [email protected] Magnet Power Supply Modifications Only QUAD’s 24201-24501 (4 of original 8) remain on sector-24 bulk supply (keep 0-20 A boost for each) Q24601 gets its own supply Doubled-up Q24701A/B gets its own supply Q24801 quad goes away forever (boost supply is free) Doubled-up Q24901A/B gets its own supply New QM21 & QM22 (46-cm FFTB quads) each get own supply Two new MCOR6 tweaker quads (h-correction) as in BC1 No new correctors here, but all of sectors 20-30 get new MCOR6 corrector supplies to replace old SCOR6 supplies Control divided between EPICS and SLC Have software to communicate between systems, but adds complexity. Still details to work out for LEM, etc . Oct. 30, 2007 LCLS FAC 15 Joe Frisch [email protected] BC2 Dipole Field Quality OK No quad field and sextupole is just below tolerance Oct. 30, 2007 LCLS FAC 16 Joe Frisch [email protected] Diagnostics Issues Can’t tune on something you can’t measure Engineering issues with the wire scanners Vibration limits us to slow scan speeds Can be fixed – but no sure solution in hand Physics issues with the OTR screens Coherent effects distort image May be able to fix with short wavelength filter, but not known. Oct. 30, 2007 LCLS FAC 17 Joe Frisch [email protected] Wire Scanners Measured beam size Vs. Motor Steps / second Range is 40-140 microns With slow scanning, size was reproducible to 5 microns. May be able to fix problem by adding a gear reducer to wires scanner (cheap), but not tested yet. For now, limited to slow scans 1 minute / scan, 10 minutes for emittance measurement. Oct. 30, 2007 LCLS FAC 18 Joe Frisch [email protected] Even “ideal” wire scanner only gives integrated profiles Pathological beam shape that would Not be apparent on wires Oct. 30, 2007 LCLS FAC 19 Joe Frisch [email protected] Coherent Effects in OTRs OTR12 sum signal as QB is varied. BC1 off, L1X, L1S on crest. Y beam size Varies with observed intensity Not clear if effect will be worse after BC2. Oct. 30, 2007 LCLS FAC 20 Joe Frisch [email protected] OTRs - Plans Installing diffraction gratings in front of OTR cameras Hope to find that coherence is only in long wavelength signals If signal is incoherent below ~400nm can easily add filters to cameras Installing UV (200nm) and IR (2.5um) detectors on OTRs IR detectors to understand coherence (not seen yet at DESY / FLASH or Spring-8 / SCCS) UV detectors to look for coherence at hard UV If no coherence at 200nm, can use UV cameras (but $$) Can not show from beam parameters that we don’t have coherence as short at 100nm – beyond the range of conventional cameras. In future “Laser Heater” will probably fix this problem – but would like to be able to diagnose beam without heater. Oct. 30, 2007 LCLS FAC 21 Joe Frisch [email protected] Diagnostics – BPMs Existing linac BPMs have 30 – 100 micron resolution depending on beam charge (300pc – 1nC). Readout is through SLC – EPICS communication – slow ~5 seconds. Will need good linac orbit tuning algorithms. Work underway. Need initial accuracy ~1mm. OK Then tune on emittance – should work but slow. May wish to tune at high charge (~1nC) Increase effect of wakefields Better BPM resolution Oct. 30, 2007 LCLS FAC 22 Joe Frisch [email protected] Diagnostics – where are we? Wire scanners work but: For now, just slow scans – hope for a mechanical fix soon First wires located in S28, 300 meters downstream of BC2 OTRs So far can not be used for quantitative measurements Some plans that may fix the problem, but not clear a solution exists Discussed at 3-way collaboration meeting at Spring-8 this month. Work underway at other labs. BPMs Using old LINAC BPMs. Should be OK, but readout slow Next year (?) replace with epics BPMs. Oct. 30, 2007 LCLS FAC 23 Joe Frisch [email protected] Emittance Preservation and Measurement Measure emittance after L2: In BC2 (with compressor straight) using OTR If we do not have coherent effects – otherwise: Wire scanner in Sector 28 (300M downstream) Orbit Tuning Minimize orbit on Linac BPMS Then Tune orbit on emittance In OTR21, or in S28 wires Might be slow to converge Then optimize BC2 emittance This is probably our most serious technical challenge. Oct. 30, 2007 LCLS FAC 24 Joe Frisch [email protected] Bunch Length measurement In much better shape than transverse measurements TCAV in S24 will let us resolve bunch length. Old cavity in new installation. No problems anticipated. Cross check with direct compression measurement using phase cavities Demonstrated in injector On line mm-wave bunch length monitors similar to injector monitors Shorter mm wavelengths, but should work Unique beam conditions – can always have surprises! Oct. 30, 2007 LCLS FAC 25 Joe Frisch [email protected] Other Issues LINAC controls split between EPICS and SLC systems. We have tools in place to make this work, but could be slow to get going Limited LINAC tunnel access – B-factory running. Limited time to make changes or repairs Systems designed for “Production”, not R+D. Compact, reliable, and high performance, but difficult ot modify. Oct. 30, 2007 LCLS FAC 26 Joe Frisch [email protected] Additional Run Plans Improve performance of injector Better BC1 magnet field quality X-band cavity moved to reduce steering Try programmable phase ramp in L0A to reduce bunch length / improve emittance New RF system for phase stabilization over ~1km beamline New temperature stabilized transmission lines Need to compare with beam timing and MDL. Complexities due to path length changes in bunch compressors. Commission new beam feedbacks Energy and bunch length throughout machine Energy at 3 points, bunch length at 2, beam time. Transverse feedbacks throughout machine Optimize orbit on emittance, then stabilize Oct. 30, 2007 LCLS FAC 27 Joe Frisch [email protected] Summary Linac/BC2 e- commissioning starts in early Dec. ’07 Large amount of commissioning time available (fewer shifts/week & no weekends after 1st month?) Main ’07 goal is to verify full functionality of linac/BC2 beamline, plus diagnostics and controls Optimizing performance may take longer Will need some linac access in first 1-2 months Oct. 30, 2007 LCLS FAC 28 Joe Frisch [email protected]