Transcript Document

Common Methodology Group Work
Workstream 2
(Development of the distribution reinforcement model)
Progress since the last DCMF
05 February 2009
PRESENTED BY ANDY JENKINS, CE ELECTRIC UK, ON BEHALF OF WORKSTREAM 2
05 February 2009
energynetworks.org
•1
Agenda
• Progress since the last DCMF
The primary focus has been to support Reckon LLP (ENA appointed
consultant) who is developing the new distribution reinforcement (DRM)
charging model.
• Development of the common DNO
model
• Issues escalated Ofgem
• Other areas of consideration
• Next steps
05 February 2009
energynetworks.org
2
Common DNO charging model
• Developed by Reckon in conjunction with the distribution network
operators (DNOs) and interested industry parties
• Focuses on charges for HV & LV connected customers (but also models
EHV)
• Aims to reflect Ofgem’s October 2008 decision document and includes
• Charges for independent distribution network operators (IDNOs)
• HV and LV generator charges which recognise the potential benefit that
generation can bring to the network by offsetting demand
• Reactive power charges
• Supports common tariff structures and common application processes
• The design philosophy of the model emphasises transparency over
compactness.
• The model is still under development, but the latest version can be found
on the ENA website at http://2009.energynetworks.org/structure-of-charges/
05 February 2009
energynetworks.org
3
Issues escalated to Ofgem
•
•
Briefing papers were produced on the issues encountered so far
Focused on areas where:
• the current modeling approach differed from appendix 2 of decision document
• we believed the document was ambiguous in certain areas.
•
The purpose of the briefs was to try and get early resolution of the issues
and ensure that the project remained on track.
Issue
Description
WS2 - 1
Revenue reconciliation if demand and generation incentives are merged
WS2 - 2
DRM network Assets
• Issue 2a - Method for excluding customer contributed assets from the DRM
• Issue 2b - Clarity on replacement of sole use network assets
WS2 - 3
Clarity on the final step in the derivation of the reactive power charge
WS2 – 4
Network levels for which generation benefits are to be paid
WS2 - 5
Consistency in the application of P2/6 across voltage levels
WS2 - 6
Use of reduction factors to calculate availability charges and fixed charges
05 February 2009
energynetworks.org
4
Other areas of consideration
• Time of day and time of year cost signals
• Is it appropriate to simplify the tariff offering in order to facilitate
more commonality across DNO?
• 500 MW network model
• What assets should be included in the 500MW model
• How best to incorporate the customer connections contributions
paid by the various customer types
• Some networks may be a variant, depending on local
configuration (e.g. northern Scotland)
• Generation yardsticks
• DG yardsticks have been included in the model based on
F-factors
• Two responses were received to the consultation
05 February 2009
energynetworks.org
5
Future areas of work
• Clarify Ofgems “minded to” decisions, before building
them into the charging model
• Finalise the model and associated user manual
• Identify the source of the data required to populate the
charging model
• Start to populate the charging models
• Undertake detailed impact and sensitivity analysis
05 February 2009
energynetworks.org
6