Transcript Slide 1
The Role of Defect Elimination in Reducing Hazard Exposure Presented by: Stuart Tomlins Callide Mine Context Callide Mine…… 10 Mtpa open cut thermal coal Located 1.5hrs S.W. of Rockhampton 450 full time employees Overburden is primarily removed by 2 draglines, 1 shovel & 1 excavator The excavator & shovel are supported by a fleet of 15 x 270t payload rear dump trucks (EH4500’s) This presentation discusses the EH4500 truck fleet improvement project & assesses the impact on hazard exposure Truck Fleet Availability by Year 3 years of declining performance………….. EH4500 Fleet Availability 2003- Q1, 2008 100% EH4500 Fleet Availability (%) 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 2003 2004 2005 Year 2006 2007 Actual Q1, 2008 Target …………..required action Taking Action To reverse the trend a number of processes commenced to address the EH4500 availability: Reliability data analysis * Dedicated team assigned to plan and execute the defect backlog reduction* Scheduled service process review Defect elimination* Hitachi EH4500 users forum Reliability Analysis of EH4500 Downtime Top 20 downtime components for EH4500 fleet July to Dec 07 1200 Hitachi EH4500 Rear Dump Improvement Plan Current Performance Hitachi Availability 2005 - 2008 80 80 Percentage 100 Percentage 1000 Hitachi Availability 2003 - 2008 100 60 40 20 60 40 20 0 J an05 Ma r05 Ma y05 Jul05 Se p05 No v05 J an06 Ma r06 Ma y06 Jul06 Se p06 No v06 J an07 Ma r07 Ma y07 Jul07 Se p07 No v07 J an08 0 2003 2004 2005 Month/Year EH4500 Availability 800 Budget EH4500 Availability Pareto Analysis Critical Issues 1200 1000 800 Hours 2008 How to reduce ‘Wait Labour’ delays for mechanical repairs to an acceptable level. How to effectively manage the backlog, completing defects in conjunction with the PM schedule. How to reduce ‘Wait Labour’ delays for tyre maintenance to an acceptable level. How to improve technical skills of workforce to reduce trouble shooting time on Engine Faults. How to implement product improvements with minimal impact to production. How to structure the department to support the truck fleet on 7DR How to improve focus and urgency around the performance of the rear dump fleet. How to Hitachi andmaintenance improve their focusare onnot improving fleet What if engage Operator induced events minimised eg.reliability. tyre damage, operational conditions impacting on fatigue life of chassis. Top 20 downtime components for EH4500 fleet July to Dec 07 600 400 200 S te eri ng Lu be Fa ult le ctr ic al fa ult ois tC yli nd S er ie m en s 12 3 E H y nk ta le ak O il er nk ) ra (b la ulic e ra w ork /T nc yd na el S te nk /h Fu or M in Fro el m ta e tru t rd S s/r eta ke ra te B ain w er w co d lo ak /lo e B ng in E r ub ult ne fa /H itio k/ le lin nd nt oo la s ea rin g B co A el ir m en ie S xle nt w he C /d riv es s A fa e E ng in Ty re ult 0 400 Type of downtime Improvement Plan Increase support and focus from Hitachi Type of downtime Delayed Extend Bridgestone tyre fitter coverage to 7 days / wk Stuart Tomlins 30/04/2008 ↓ in 'Wait Labour' delays. Scheduled tyre changes integrated into Mobile Maintenance Schedule Sven Gronbach 30/03/2008 ↑ Availability Complete installation of double gutter rims. (7 Trucks) Sven Gronbach 30/05/2008 ↑ Availability Review Tyre Specification & application for operation in Trap Gully Stuart Tomlins 1/04/2008 ↑ in Scrap tyre life Engage one Detroit fitter Mon-Fri for engine fault finding and maintenance. Conduct engine specific training (Improve the technical skills of maintenance personnel) Stuart Tomlins 3/03/2008 ↑ Availability Stuart Tomlins 30/05/2008 ↑ Availability Review the level of routine & PEX spares held at site and Detroit in Mky. Stuart Tomlins 1/04/2008 ↓ in 'Wait Parts' delays. Complete Develop contingency plan for engine repower on Rear Dump 1154 Implement contamination control for final drives by implementing an oil filtration process. Review final drive oil specification with Hitachi & Shell wrt extending component life. Stuart Tomlins 17/03/2008 ↑ Availability, ↓ in 'Wait Parts' delays. Complete Danny Jamieson 1/04/2008 ↑ Availability Danny Jamieson 17/03/2008 ↑ Availability Engage Hitachi (OEM) to improve Wheel motor and grid blower reliability. Danny Jamieson 1/06/2008 Independent A/C specialist to review OEM system. Conduct a review of A/C spares holding onsite Update maintenance strategy to include a 12mth major service. Danny Jamieson Stuart Tomlins Sven Gronbach 7/04/2008 1/04/2008 1/04/2008 Implement the following electrical updates : Seimens Data isolators, 5XH plug upgrade to main alternator & Temp sensor upgrade to wheel motors. Stuart Tomlins 1/05/2008 Implement bearing assembly upgrades to main blower. 1/05/2008 Stuart Tomlins 1/05/2008 Stuart Tomlins 1/05/2008 Engage dedicated tradesmen (2) for a two month period. Conduct Daily Downtime & Planned Work compliance reviews identifing corrective actions. (2 month period) Stuart Tomlins 10/03/2008 Stuart Tomlins 10/03/2008 Communicate improvement plan & weekly fleet performance to crews Modify the Maintenance Structure to support EH4500 fleet operating on 7DR Review the onsite Hitachi Project Managers role and expectations to align with Callides requirements. Stuart Tomlins 15/03/2008 Sean Halliday Hold monthly EH4500 improvement meetings with Hitachi. Danny Jamieson ↑ Availability ↓ in 'Wait Parts' delays. ↑ Availability ↑ Availability ↑ Availability ↑ Availability Complete Completed. No problems. Complete Not done yet. Currently doing stat training. Complete Complete Modifications being trialled Parked. A/C performance has improved thru other actions. Complete Complete Complete Complete Complete ↑ Availability, ↓ in 'Wait Labour' delays. ↑ Availability, ↓ in 'Wait Labour' delays. Complete Complete 1/04/2008 ↑ Availability ↑ Availability, ↓ in 'Wait Labour' delays. ↑ Availability, ↓ in 'Wait Labour' delays. 17/03/2008 ↑ Availability Complete 4/03/2008 ↑ Availability Complete. Users forum. Complete Complete Complete Siemens 123 Stuart Tomlins Implement front wheel bearing retainer plate upgrade. Dedicated Supervisor allocated to EH4500 for two months period to drive scheduled maintenance tasks and generate focus on completing maintenance backlog. ↑ Availability Park. Too expensive. Parked. No value at this stage. Hoist Cylinder Increase focus and urgency on executing the maintenance strategy. ↑ in Scrap tyre life, ↓ in tyres scrapped due to cuts. Electrical fault Implement 'known' EH4500 Product Improvements By When Lube Fault Improve Air Conditioner system reliability 30/05/2008 Steering Brakes/retarder Strut Blower Engine code Coolant leak/low Siemens link/ fault Front wheel Bearing/Hub Air conditioner Axle/drives Tyres Improve driveline reliability Who Oil leak 0 Status Rod Nichols Fuel tank/hydraulic tank Reduce downtime related to Engines Action Steel work/Tray 200 Performance Measures BI Project - Tyre life improvement Minor maintenance (blank) Problem Statement Reduce downtime related to Tyre Management Engine fault Hours 2007 2005 - 2008 included trucks 1151-1164 (full fleet) 2003 included trucks 1151-1156 2004 included trucks 1151-1160 600 2006 Year Budget Defect backlog reduction 120 60% Work Orders MA% Improvement Project Focused on….. •Reducing Work Order backlog •Implementing a number of improvements One Year Target (%) Three Year Target (%) This was done by….. •Developing a plan •Assigning a dedicated supervisor & labour resource •Focussed effort to reduce backlog Fleet Availability (%) 65% Mar-09 140 Feb-09 70% Jan-09 160 Dec-08 75% Nov-08 180 Oct-08 80% Sep-08 200 Aug-08 85% Jul-08 220 Jun-08 90% May-08 240 Apr-08 95% Mar-08 260 Feb-08 100% Jan-08 # of Outstanding Jobs EH4500 Availability vs Workorder Backlog 280 Maintenance Injury Rates Through the Projects Duration Total Maintenance Injuries vs Availability on Trucks 90% 7 Defect Elimination Campaign 4 75% 3 70% 2 65% 1 Truck Fleet Availability Total Injuries in Maintenance Nov-08 Oct-08 Sep-08 Aug-08 Jul-08 Jun-08 May-08 Apr-08 Mar-08 0 Feb-08 60% Jan-08 Availability (%) 5 80% 2 per. Mov. Avg. (Total Injuries in Maintenance) Injury Moving Average 6 85% Some perspective 2831 defects over 12 month period (EH4500) Estimate at least 5 hazards per defect 14155 hazards on 1 fleet Hazard exposure Risk = Consequence x Likelihood Defect elimination Reduced exposure Example Defect Elimination Projects Problem-5XH Alternator Plugs ground faults Root Cause Dust & water ingress from poor plug location & inadequate sealing Benefit Solution •Reduced downtime (34hrs/yr) •Hard wire cables into termination strip •Reduce maintenance costs •Reduced hazard exposure •Replace plug with gland plate Problem – Premature final drive failures Root Cause •Oil viscosity too low •Wear metal generated causing wide spread deterioration Benefit Solution •Reduced gear and bearing wear •Change to costly synthetic lube •Maximise life of oil & final drives components •Implement kidney filtration •Reduce hazard exposure by extending the time between maintenance & reducing failures Problem – Reverse Light Damage Root Cause Poor light location Benefit Solution Reduced downtime by 50hrs per yr Relocate the light position to under the rock deflector shield Reduced maintenance costs Reduced hazard exposure fixing these lights Problem – Starter Motor Testing Duration Root Cause Extended service duration due to testing method required to ensure starter motors are both functioning Benefit Solution •Reduction of 40 hours servicing per year By installing 2 switches in the cab, the serviceman can turn one starter motor off via the new switches, test with ignition switch. Repeat for the second starter motor. The red guards give a visible indication of the position of the switch to overcome leaving in the wrong position •Reduced hazard exposure Problem – Difficult access to check pressure & re-charge front struts Root Cause The cause is due to the recharge points facing towards the rear of the truck. Access via a mobile platform is impeded by the steering arm Benefit Solution •Safer access of existing engine platform to check / recharge struts By rotating the struts around 180 degrees, this then allows the access via the engine bay stairs/platform •Reduction of 15 minutes per service on each truck Problem – Hydraulic contamination from lift cylinder seal erosion Root Cause Seal Saver Fitted Design of radiator fan causes exhaust dust to erode cylinder rod & seals Benefit Solution •Reduced contamination levels in the hydraulic system which will reduce the failure rate on the hydraulic pumps and cylinders Install Kevlar seal savers to the lift cylinders to prevent erosion and contamination •Reduced hazard exposure are change outs will occur less frequently The benefits of the defect removal & elimination program are: Reduced unplanned callouts to equipment in the field Better hazard control in planned work situations Reduced exposure means reduced risk Reduced maintenance costs Increased asset performance Cultural shift Great teamwork and energy in finding solutions Summary Defect backlog management and defect elimination are key factors in reducing hazard exposure for tradespeople Build momentum by involving your trades teams Solutions are generally inexpensive, simple & effective