Is it DONE done?
The Final Walkthrough ?
What is
Commissioning (Cx)?
Definition
Past & Present
What is Cx NOT!
Objectives
Economics
Impediments
Process
Case Studies
Building Performance Together
What is
Commissioning (Cx)?
Definition
Past & Present
What is Cx NOT!
Objectives
Economics
Impediments
Process
Case Studies
Building Performance Together
What is
Commissioning (Cx)?
Definition:
“A quality-focused process for enhancing the delivery
of a project. The process focuses on verifying and
documenting that the facility and all of its systems and
assemblies are planned, designed, installed, tested,
operated, and maintained to meet the Owner’s Project
Requirements.” Draft ASHRAE Guideline 0-2000X, The Commissioning Process
What is a
Commissioning Authority
Project Success Advocate
Problem Solver
Generalist not Specialist
Quality Process Focus
Develops Detailed Cx Plan
Skilled Communicator
Verifies & Documents
Facilitates Training
Building Performance Together
What is
Commissioning (Cx)?
Definition
Past & Present
What is Cx NOT!
Objectives
Economics
Impediments
Process
Case Studies
Building Performance Together
The PAST
The 70’s - Energy Crisis
Building Performance Together
The PAST
The 80’s – Energy Analysis
Variable Air Volume Standard
Building Automation Systems &
Evolution Away from
Pneumatics
Simple to Complex HVAC
Design to Maintain Comfort &
Reduce Energy
Utility Company Demand Side
Management Programs
Specialization & Division in
HVAC Knowledge
Building Performance Together
The PAST
The 90’s – Energy Growth
Increased Awareness of Need to
Verify
Increased Facility Operator
Sophistication
Increased Service Industry &
Reliance on Better HVAC
Emergence of Commissioning
Industry
Building Performance Together
The PRESENT
The 2000’s – Awareness
Greening of America & World
Leadership in Energy Efficient
Design
Concern about Carbon Emissions
Technology Advancements &
Energy Costs Creating Favorable
Alternate Energy Climate
Major Growth of Cx
Industry
Building Performance Together
What is
Commissioning (Cx)?
Definition
Past & Present
What is Cx NOT!
Objectives
Economics
Impediments
Process
Case Studies
Building Performance Together
What is Cx NOT?
(but encompasses)
NOT: Testing, adjusting and balancing (TAB)
NOT: Contractor’s startup
NOT: Engineer’s installation “observation”
NOT: Performance verification alone
NOT: Limited to HVAC systems or Controls systems
NOT: Routinely included in Professional Design
Consultant’s fees
NOT: MEP coordination (may assist)
DOES NOT: Have responsibility to direct or make
corrections to identified deficiencies
Building Performance Together
What is
Commissioning (Cx)?
Definition
Past & Present
What is Cx NOT!
Objectives
Economics
Impediments
Process
Case Studies
Building Performance Together
Objectives/Perspectives
Owner
Accept an optimized building
Minimized warranty issues
Minimized energy costs
Minimized O&M costs
Maximized functionality
Report on construction process
Building Performance Together
Objectives/Perspectives
Design Team
Constructed according
to design, no less
Identify construction
issues early
Independent
perspective on design
issues
Extra set of observation
“eyes”
Contracting Team
Constructed according
to design, no more
Identify design issues
early
Independent
perspective on
construction issues
Open the project on
schedule & in budget
Minimized warranty
issues
Building Performance Together
Objectives/Perspectives
Cx Agent
Constructed according to design,
no more, no less
Participate in a team environment
Achieve success through the success of
others
Identify functionality issues & resolve prior to
Owner acceptance
Building Performance Together
What is
Commissioning (Cx)?
Definition
Past & Present
What is Cx NOT!
Objectives
Economics
Impediments
Process
Case Studies
Building Performance Together
Commissioning Economics
Function of Systems’ Complexity & Extent of
Services
0.5 to 3% of Total Constructions Cost
1.5 to 4% of Mechanical System Cost
.5 to 3% of Electrical System Cost (Source:
Commercial Energy Systems)
Whole Building Commissioning: $0.5 to $1.50 Per
Square Foot
Operating Costs: 8 to 20% Below NonCommissioned Buildings (Source: Kennett, NIBS)
Building Performance Together
What is
Commissioning (Cx)?
Definition
Past & Present
What is Cx NOT!
Objectives
Economics
Impediments
Process
Case Studies
Building Performance Together
Impediments to Cx
No perceived need
Additional construction costs
Perceived potential delays in construction
Savings difficult to quantify
Contractor resistance
Building Performance Together
What is
Commissioning (Cx)?
Definition
Past & Present
What is Cx NOT!
Objectives
Economics
Impediments
Process
Case Studies
Building Performance Together
Commissioning Process
Commissioning
Plan
Owners
Functional
Requirements
Design
Document
Reviews
Basis of
Design
Review
PLAN
DESIGN
Cx
Report and
Systems Manual
O & M Document
Review
Revised
Plan
Scoping
Meetings
PreFunctional
Checklist
PF
Functional
Testing
FPT
Start-up
CONSTRUCTION
Warranty
Review
O&M
Seasonal
Training
Testing
RCx
OCCUPANCY
Project Timeline
Building Performance Together
Documentation
Commissioning Team
Basis of Design
Design Intent
Overview of Cx
Procedures
Pre-Functional
Checklists
Functional Performance
Testing Scenarios
Issues and Resolutions
Logs
Building Performance Together
Pre-Functional Checkout
Building Performance Together
Functional Performance Test
Building Performance Together
What is
Commissioning (Cx)?
Definition
Past & Present
What is Cx NOT!
Objectives
Economics
Impediments
Process
Case Studies
Building Performance Together
Case Study –
Hydronic Systems
No HW pump check valves
35% of HW valves leaking by
Incorrect boiler pressure relief valves
Incorrect boiler staging
Reduced CHW variable speed pump setpt from 20#
to 12#
Cooling Tower bypass valve sticking with both valves
closed.
45% of CHW & HW valves not fully closing off.
Primary & secondary chilled water flows unbalanced.
Building Performance Together
Case Study –
Hydronic Systems
Main chilled water DP control valve failed
closed
Steam condensate tank overflow discharges
directly to floor drain
Condensate tank pumps level switches failed
No condensate return unit for DHW
HW system contaminated and strainers
plugged
Thermometers not installed
Thermometer ranges incorrect
Building Performance Together
Case Study –
Airside Systems
Main fans ran with isolation damper closed in
bypass mode.
Static pressure hi limits do not shut down fans
in bypass mode.
Optimization programming modes failed
Main relief fans capacities too small
AHU control valve too small & does not meet
design temps.
Rebalanced 80% of OSA intake volumes
75% of MAU safeties not operating properly.
Building Performance Together
Case Study –
Miscellaneous
No interlock between main AHU’s and VAV terminals
Poor resolution and inaccurate reading of VAV CFM
No heat on VAV reheat coils from contamination.
Fan coil units sizes too large
Programming modes incorrect for VAV operation
No fiber optic connection to main fire panel
Problems w/ hot/neutral reversed on 120v power.
Lighting system panel BMS circuits jumpered out and
graphics incorrect.
Emergency Generator cannot meet design load
Building Performance Together
References
Associated Air Balance Council (AABC) & ACG (AABC Cx Group)
Building Commissioning Association (BCA)
www.nibs.org
Portland Energy Conservation Inc. (PECI)
Us Dept of Energy – Rebuild America Guide Series
National Institute of Building Sciences
Portland Energy Conservation, Inc. and Oak Ridge National Laboratory
eren.ed.ornl.gov/commercialproducts/retrocx.htm
Building Commissioning – The key to Quality Assurance
www.ashrae.org
A Practical Guide for Commissioning Existing Buildings
www.bcxa.org
American Society of Heating, Refrigerating, and Air Conditioning Engineers
(ASHRAE)
www.aabchq.com; www.commissioning.org
www.peci.org
Rebuild America
www.rebuild.gov/productservices/sc_bldgcomm.htm
Building Performance Together
What is Building
Commissioning
Questions?
Building Performance Together